Formulas Flashcards

1
Q

Planned Value

A

Percent complete of where the project should be.
PV = Percent Planned x Budget at completion (BAC)

PV = 55% x $250,000
PV = 137,500
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value

A

The value of work that you have accomplished.

EV = percent complete x Budget at completion (BAC)

EV = 40% x $250,000
EV = $100,000
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Variance

A

The difference between the earned value and the Actual Cost. This tells you if you’re under budget or over budget.

CV = Earned Value (EV) - Actual Cost (AC)
CV = $100 - $112
CV = $-12
The negative indicates that we spent more than what was earned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule Variance

A

Tells you if you are ahead of schedule or behind schedule.
A negitive number indicates you are behind schedule.
A positive number indicates you are ahead of schedule.

SV = Earned Value (EV) -  Planned value (PV)
SV = $100 - $137 
SV = $-37
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Performance Index

A

Tells you if you are over or under on Cost.

CPI = Earned Value (EV) / Actual Value (AC)
CPI = $100 / $112 
CPI = 0.89 

The closer we are to the number “1” the better we are performing on cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Performance Index

A

A measure of how close the project is to being completed compared to the schedule.

SPI = EV / PV
SPI = $100 / 137
SPI = 0.37

an SPI above 1 equates to being ahead of schedule, whereas an SPI under 1 means you’re behind schedule. And, if your SPI is equal to 1, your project is exactly on schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate at Completion

A

Estimate the cost of a project at completion. How much money we are going to have at the end of the project.

EAC = Budget at completion (BAC) / Cost Performance Index (CPI)
EAC = $250 / 0.89
EAC = $280
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimate to Completion

A

How much more you need to get to the end of the project.

ETC = Estimate at completion (EAC) -  Actual Cost (AC)
ETC = $280 - $112
ETC = $168 

We need $168 more based on our current performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

To-Complete Performance Index (BAC)

A

TCPI is the calculated Cost Performance Index that is achieved on the remaining work to meet the specified management goal, such as the BAC or the EAC.

TCPI = Time to complete based on Performance Index, BAC.
TCPI = (BAC - EV) / (BAC - AC) ← Notice this is based on BAC.
TCPI = ($250 - $100) / ( $250 - $112)
TCPI = ($150) / ($138)
TCPI = 1.09 

The further below the number “1” the better we are hitting our target. This is above one so we are not likely to hit the BAC target.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Time to complete based on Performance Index (EAC)

A

TCPI is the calculated Cost Performance Index that is achieved on the remaining work to meet the specified management goal, such as the BAC or the EAC.

TCPI = (BAC - EV) / (EAC - AC) ← Notice this is based on EAC.
TCPI = ($250 - $100) / ( $280 - $112)
TCPI = ($150) / ($168)
TCPI = 0.89 

The below the number “1” the better we are hitting our target. This is below one so we are likely to hit the EAC target.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Variance at completion

A
VAC = Budget at completion (BAC) - Estimate at completion (EAC)
VAC = $10,000 - $8,500
VAC = $1,500

If the VAC value is positive, that indicates the project will complete under budget.
If the VAC value is negative, that indicates the project will finish over budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Three Point Estimate

A

Used in Schedule management. Finds an average of Optimistic, Most Likely, and Pessimistic (screenshot in folder). Also called the Triangular Distribution.

(O+ML+P)/3 = Estimate
(25+45+75)/3=48.33 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PERT Estimate

A

Program Evaluation and Review Technique. This is weighted towards the most likely, 4 times the most likely value. Also called beta distribution (screen shot in folder).

(O+(4ML)+P)/6 = Estimate
(25+(4*45)+75)/6 = 46.66 hours
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

SPACE

A

.

               Ev
     pi /              /  pi
S                           C
     v -                 -  v
            P     Ac
How well did you know this?
1
Not at all
2
3
4
5
Perfectly