Formulas Flashcards
Planned Value
Percent complete of where the project should be.
PV = Percent Planned x Budget at completion (BAC)
PV = 55% x $250,000 PV = 137,500
Earned Value
The value of work that you have accomplished.
EV = percent complete x Budget at completion (BAC)
EV = 40% x $250,000 EV = $100,000
Cost Variance
The difference between the earned value and the Actual Cost. This tells you if you’re under budget or over budget.
CV = Earned Value (EV) - Actual Cost (AC)
CV = $100 - $112
CV = $-12
The negative indicates that we spent more than what was earned.
Schedule Variance
Tells you if you are ahead of schedule or behind schedule.
A negitive number indicates you are behind schedule.
A positive number indicates you are ahead of schedule.
SV = Earned Value (EV) - Planned value (PV) SV = $100 - $137 SV = $-37
Cost Performance Index
Tells you if you are over or under on Cost.
CPI = Earned Value (EV) / Actual Value (AC) CPI = $100 / $112 CPI = 0.89
The closer we are to the number “1” the better we are performing on cost.
Schedule Performance Index
A measure of how close the project is to being completed compared to the schedule.
SPI = EV / PV SPI = $100 / 137 SPI = 0.37
an SPI above 1 equates to being ahead of schedule, whereas an SPI under 1 means you’re behind schedule. And, if your SPI is equal to 1, your project is exactly on schedule.
Estimate at Completion
Estimate the cost of a project at completion. How much money we are going to have at the end of the project.
EAC = Budget at completion (BAC) / Cost Performance Index (CPI) EAC = $250 / 0.89 EAC = $280
Estimate to Completion
How much more you need to get to the end of the project.
ETC = Estimate at completion (EAC) - Actual Cost (AC) ETC = $280 - $112 ETC = $168
We need $168 more based on our current performance.
To-Complete Performance Index (BAC)
TCPI is the calculated Cost Performance Index that is achieved on the remaining work to meet the specified management goal, such as the BAC or the EAC.
TCPI = Time to complete based on Performance Index, BAC. TCPI = (BAC - EV) / (BAC - AC) ← Notice this is based on BAC. TCPI = ($250 - $100) / ( $250 - $112) TCPI = ($150) / ($138) TCPI = 1.09
The further below the number “1” the better we are hitting our target. This is above one so we are not likely to hit the BAC target.
Time to complete based on Performance Index (EAC)
TCPI is the calculated Cost Performance Index that is achieved on the remaining work to meet the specified management goal, such as the BAC or the EAC.
TCPI = (BAC - EV) / (EAC - AC) ← Notice this is based on EAC. TCPI = ($250 - $100) / ( $280 - $112) TCPI = ($150) / ($168) TCPI = 0.89
The below the number “1” the better we are hitting our target. This is below one so we are likely to hit the EAC target.
Variance at completion
VAC = Budget at completion (BAC) - Estimate at completion (EAC) VAC = $10,000 - $8,500 VAC = $1,500
If the VAC value is positive, that indicates the project will complete under budget.
If the VAC value is negative, that indicates the project will finish over budget.
Three Point Estimate
Used in Schedule management. Finds an average of Optimistic, Most Likely, and Pessimistic (screenshot in folder). Also called the Triangular Distribution.
(O+ML+P)/3 = Estimate
(25+45+75)/3=48.33 hours
PERT Estimate
Program Evaluation and Review Technique. This is weighted towards the most likely, 4 times the most likely value. Also called beta distribution (screen shot in folder).
(O+(4ML)+P)/6 = Estimate (25+(4*45)+75)/6 = 46.66 hours
SPACE
.
Ev pi / / pi S C v - - v P Ac