Flow Line Systems Flashcards

1
Q

Precedence Diagram notation

A

Top - Letter
Bottom Left - number of dependent activities
Bottom Right - Time required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you know how to order a Precedence Diagram

A

Heuristic rules:
order by (if the same, move down to next importance)

  • order of greatest dependence
  • most time required
  • greatest positional weight (most successors)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Balance Delay

A

= 100 − Assembly Line Efficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Assembly Line Efficiency

A

= Σt/(N x CT) X100

Cycle Time (CT)
Number of workstations (N)
Sum of task times (Σt)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Total Idle Time

A

= (N x CT) − Σt

Cycle Time (CT)
Number of workstations (N)
Sum of task times (Σt)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Total Time Available

A

= (N x CT)

Cycle Time (CT)
Number of workstations (N)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Minimum number of workstations required

A

Σt/CT

Cycle Time (CT)
Sum of task times (Σt)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly