Flashcards 1 - 40

1
Q

Bidders instructions:

A

Describe the company’s qualifying requirements for bidders - their licenses, labor affiliations, qualifications and bonds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Specifications;

A

Enables bidders to understand exactly what they are expected to supply and install.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The purchasing organization should clearly state:

A

its evaluation criteria; how each Criteria is weighted and what and how Proposals will be evaluated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The purpose of the invitation for bid (IFB)?

A

When a system is already designed, the IFB is used to obtain the lowest cost for the equipment, software and installation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The company should be prepared to defend its selection of qualified contractors by having?

A

Written selection criteria and results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The output of the project design phase is called the…..

A

Bid package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the four components of the bid package?

A

Bidders’ instructions
Specifications
Drawings and schedules
Hardware schedules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The component of the bid package that supplies the security system requirements in sufficient detail so bidders all know equally what is needed?

A

Specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The five most commonly supplied drawings within the bid package are?

A

Plan
Elevation
Detail
Riser diagrams
Conduit and cable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The 3 hardware schedules in the bid package that help in understanding the specific components to be provided?

D-D - CC

A

Data panel schedule
Door hardware schedule and
CCTV camera schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The group that carries out the security system procurement activities?

A

The procurement committee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A bidder’s conference is?

A

All bidders are put in a room and the project manager can explain the procurement requirements to all of them at the same time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A bidder’s conference should include what 7 things:

“Interesting Individuals Introduce Every Detail Thoroughly & Quickly.”

A

• I – Introductory remarks
• I – Introduction of evaluation team and bidders
• I – Introduction of project and key objectives
• E – Explanation of procurement process
• D – Discussion of the purpose, timeline, and evaluation criteria
• T – Tour of the site
• Q – Questions (opportunity to ask)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

To resolve a minor informality or irregularity in the bids, a company should give a bidder a chance to…..

A

Resolve any minor deficiency, such as missing information or attachments, wrong number of copies or missing signatures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The six phases of the PPS Life cycle process are?

“Please Don’t Push It Too Much.”

A

• P – Planning
• D – Design and estimation
• P – Procurement
• I – Installation, operation, and training
• T – Testing and warranty
• M – Maintenance, evaluation, and replacement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How long can the typical PPS implementation process take?

A

18 to 24 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The most important phase of the PPS life cycle is…?

A

The planning phase

18
Q

Which part of the PPS life cycle includes the procurement process?

A

Phase 3, procurement

19
Q

Three common types of procurement actions?

A

Sole source;
Request for proposal
Invitation for bid

20
Q

Three major components of the PPS procurement phase?

A

Form a Procurement committee
Prepare a bid package and
Prequalify contractors

21
Q

The procurement phase includes these 3 things:

A

Conduct a Bidders conference
Review Technical and cost evaluations
Interview and Due diligence results

22
Q

Planning, coordinating and controlling the complex and diverse activities of modern security projects is called…?

A

Project management

23
Q

Documentation that is prepared during the planning stage of procurement management is called…..the

A

Project scope document

24
Q

To ensure a PPS is comprehensive and appropriate, a project managers should….

A

Divide the project into several stages

25
Q

Two key reminders project managers should keep in mind include…?

A

keep the project on Schedule and under control

And

Determine and sequence activities

26
Q

When is a project complete?

A

All Objectives have been achieved…..and
A Transfer of knowledge has occurred from the Project team to the Operations personnel

27
Q

Risks (6) involved in Security system procurement?

“Late Systems Affect Organizations’ Third-party Risks”

A

• Late – System delivered late or over budget
• Systems – System doesn’t work as required
• Affect – System may affect existing systems or processes
• Organizations’ – The organization may be unable to recover losses after a contract breach
• Third-party – Third-party subcontractors may make claims against the company
• Risks – (Summarizes the overarching theme of these issues)

28
Q

The 7 steps that are part of the procurement process?

A

-Form a procurement committee
-Specify hardware and software requirements
-id potential integrators
-launch a competitive tender program
-select a successful bidder
-issue a purchase order and
-receive and install the products and services

29
Q

A project manager should schedule a bidders’ confernece?

A

About one week after the Request for proposal is issued.

30
Q

In selecting contractors, what 3 things must be reviewed/accomplished?

A

Qualifications reviewed
Reference checked
Interviews with the people who will do the work.

31
Q

Skills and characteristics of a good project manager fall into 2 main areas…..?

A

Process management skills - Organized, logical, analytical, self-disciplined;

People skills - Leadership, supervision, team-building and communications ability

32
Q

What is a pathway to success in project management?

A

A systematic approach with repeatable and documented work practices

33
Q

What consumes the greatest amount of project management time day to day? The _____ which includes what 4 things?

A

The control effort which includes:
gathering information,
reviewing progress,
documenting issues and
managing the overall work plan.

34
Q

The project manager should hold status meetings at least…?

35
Q

Which PPS life cycle phase includes developing a punch list and taking necessary actions to formally accept and commission the system?

A

The installation, operation and training phase

36
Q

Commissioning is…?

A

The process of ensuring all systems and components are (DITO-M) Designed, installed, tested, operated and maintained according to the operational requirements of the owner?

37
Q

A punch list is……?

A

A contract document used in the architectural and building trades to organize the completion of a construction project

38
Q

Who must receive end-user training of the PPS?

O - U - M

A

All personnel involved in operating, upgrading and maintaining the PPS

39
Q

Three types of tests that should be run when commissioning a PPS?

A

Factory acceptance tests

Site acceptance tests

Availability or reliability testing

40
Q

What should testing simulate in the PPS commissioning process?

A

Realistic conditions