Financials Flashcards

1
Q

PV

A

Planned Value, the value of work planned to be completed to a point of time,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV

A

Earned Value, the measure of work performed expressed in terms of the budget authorized for that work, EV= Sum of the planned value of completed work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC

A

Actual Cost, the actual cost of all work completed to a point of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BAC

A

Budget at Completion, the value of planned work, the project cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A

Cost Variance, the difference of value of the work completed to the actual cost, CV= EV - AC, + under planned cost, - over planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV

A

Schedule Variance, the difference between the value of work completed to the actual cost, SV =EV-PV, + ahead of schedule, - behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

VAC

A

Variance at Completion, the estimate difference in cost at the completion of the project, VAC = BAC-EAC, + under planned cost, - over planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPI

A

Cost Performance Index, the measure of cost efficiency of budgeted resources expressed as the ratio of EV to PV, CPI = EV/AC, 1< CPI under, 1>over

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SPI

A

Schedule Performance Index, a measure of schedule efficiency, SPI= EV/PV 1> behind, 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EAC

A

Estimate at Completion, the expected total cost of completing work, EAC =BAC/CPI, EAC=AC+BAC-EV, EAC = AC + BOTTOM UP ETC, EAC = AC + [(BAC-EV)/(CPI X SPI)]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

ETC

A

Estimate to Complete, the expected cost to finish all work, ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI

A

To Complete Performance Index, the efficiency that must be maintained in order to compete on plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly