Financials Flashcards
PV
Planned Value, the value of work planned to be completed to a point of time,
EV
Earned Value, the measure of work performed expressed in terms of the budget authorized for that work, EV= Sum of the planned value of completed work
AC
Actual Cost, the actual cost of all work completed to a point of time
BAC
Budget at Completion, the value of planned work, the project cost baseline
CV
Cost Variance, the difference of value of the work completed to the actual cost, CV= EV - AC, + under planned cost, - over planned cost
SV
Schedule Variance, the difference between the value of work completed to the actual cost, SV =EV-PV, + ahead of schedule, - behind schedule
VAC
Variance at Completion, the estimate difference in cost at the completion of the project, VAC = BAC-EAC, + under planned cost, - over planned cost
CPI
Cost Performance Index, the measure of cost efficiency of budgeted resources expressed as the ratio of EV to PV, CPI = EV/AC, 1< CPI under, 1>over
SPI
Schedule Performance Index, a measure of schedule efficiency, SPI= EV/PV 1> behind, 1
EAC
Estimate at Completion, the expected total cost of completing work, EAC =BAC/CPI, EAC=AC+BAC-EV, EAC = AC + BOTTOM UP ETC, EAC = AC + [(BAC-EV)/(CPI X SPI)]
ETC
Estimate to Complete, the expected cost to finish all work, ETC = EAC - AC
TCPI
To Complete Performance Index, the efficiency that must be maintained in order to compete on plan