FINANCIAL MGMT Flashcards
ACTUAL COST (AC)
cost of the work that has been completed at a specific point int time, including any work started ahead of schedule; also known as actual cost of work performed
ANALAGOUS ESTIMATES
Use for relatively quick, high level estimating. Process of using a previous program or project of similar characteristics (size, cost, scope) to estimate a new program or project. Requires expert judgment by a group. Quantitatively based duration estimates are used also and can include PERT estimations.
BASELINE
Estimate that the program or project tries to achieve; e.g., cost, scope, time, etc.
BOTTOM-UP ESTIMATING
A detailed estimating approach that usually involves team input; as the team builds the pieces of the estimate, they build the total estimate from the bottom up.
BUDGET
The total amount of money expected to be spent on a program or project based on the original cost estimates plus any approved changes
BUDGET AT COMPLETION (BAC)
Total program or project budget; amount of money planned to be spent by the time the program or project is complete; sum of all planned value (PV)
BUDGET PROGRAM COSTS
The process of evolving detailed program and project budgets that are based on project estimates
CHART OF ACCOUNTS
A list of accounts used by the accounting or Pg Mgmt System. Track budgets, work packages, projects, etc that have a baseline cost and actual cost to report. A structure used to monitor cost that usually aligns with a company’s accounting system and the work breakdown structure of the program or project. The Budget Program Cost processes uses the chart to show where the funds are allocated.
COST PERFORMANCE INDEX (CPI)
A ratio that shows the current efficiency of money being spent on the program or project; CPI = EV/AC, a value of one means you are getting out what you put in (which is good), less than one is bad, and greater than one is good
COST VARIANCE (CV)
The difference between the value of what has been built (EV) and the cost of what has been built (AC); CV = EV-AC, a value of zero (0) means theprogram or project is creating what it should for the planned cost, a negative value means the program or project is over budget, and a positive value means the program or project is under budget
DEFINITIVE ESTIMATES
A cost estimate that provides an accurate estimation of the program or project cost; the final estimate that will be used before impelmentatioin of the program or project begins; the tolerance range is +/- 10%
DEVELOP PROGRAM FINANCIAL PLAN
The process of determining development and management procedures for the program budget and component pay schedules
DIRECT COST
Cost that is directly applicable to the porgram or project; e.g., test computer for SW being created on the program or project, IC chips, or labor used on the project
EARNED VALUE (EV)
work that has actually been accomplished or completed up to a particular point in time; the percent complete of each activity multiplied by the planned value; also known as budgeted cost of work performed (BCWP)
EARNED VALUE MANAGEMENT (EVM)
Show the status of the program or project for scope, time, and cost. Produces a quantifiable status of the program or project instead of a “gut feel” estimate.
ESTABLISH PROGRAM FINANCIAL FRAMEWORK
The process of determining the program’s financial climate and the milestones for funding availability
ESTIMATE TO COMPLETE (ETC)
Represents the projected total estimate remaining to be spent, based on the current efficiency (CPI) with which you are spending money on the program or project; ETC = EAC-AC
INDIRECT COST
Cost that is not directly accrued on the program cost; e.g., electricity, taxes, rent
LIFE CYCLE COSTING
Consideration of not just program or project cost, but total ownership (operations and support) cost of the item created by the program or project
MONITOR AND CONTROL PROGRAM FINANCIALS
The process of tracking and regulating cost variances at the program level and closing out finances for the program and its components
PLANNED VALUE (PV)
Represents the total costs that should have been spent up to a particular point in time (excluding any work started ahead of schedule); also known as budgeted cost of work scheduled (BCWS)
PROGRAM FINANCIAL FRAMEWORK
configuration for determining and managing program funding sources. Defines the flow of money into and out of a program in the most efficient and effective manner possible with the focus on elimination of waste.
PROGRAM FINANCIAL PLAN
Component of the program management plan that details the budget baseline, contract schedules and payments, funding milestones and schedules, processes for measuring and reporting financial information, processes for subcontractor payments, and all financial efforts
RESERVE ANALYSIS
A techniquein “Estimate Pg Costs”. Done to determine the amount of reserves needed for a program or project.
RESERVES
budget money set aside for difficult to predict items; also known as contingency reserves
RETAINAGE
A part of the payment that the buyer retains per the terms of the contract until the program or project is complete; used to ensure that the seller completes the work per the terms of the contract