F2 - Long-term construction contracts Flashcards
Under the completed contract method, revenue is recognized when _____________________. However, expected losses are recognized _______________.
The contract is complete.
Immediately in their entirety.
Percentage of completion formula:
Step 1: Compute gross profit of completed contract.
Contract Price - estimated total cost = Gross Profit
Step 2: Compute “% of completion”:
Total Cost to date / Total estimated cost of contract
Step 3: Compute gross profit earned (profit to date)
Step 1 X Step 2 = Profit to Date
Step 4: Compute gross profit earned for current year
Profit to Date at current FYE - Profit to Date at beginning of period = Current year-to-date Gross Profit
Under percentage of completion method, an estimated loss on the total contract is recognized:
Immediately in the year it is discovered. Any previous gross profit or loss reported in prior years must be adjusted for when calculating the total estimated loss.
When a company uses the U.S. GAAP “completed contract” method to account for long-term construction contracts, Revenue is recognized when:
The job is completed, NOT when progress billings are collected or when they exceed recorded costs.
Percentage of completion formula (simplified)
[(Total costs incurred/total expected costs) X (Total expected gross profit)] - total gross profit previously recognized.
Under the percentage of completion method, if the sum of cumulative costs incurred plus cumulative gross profit recognized exceeds cumulative billings, the excess is reported as a _________________. If cumulative billings exceeds the sum of cumulative costs incurred plus cumulative gross profit recognized, the difference is reported as a _________________. If the two amounts are equal __________________.
Current Asset
Current Liability
No asset or liability is recognized.