Q

If ground water is encountered during pipe trench excavation, the trench bottom must be stabilized by:

A

Over Excavating approximately 12” and filling to grade with gravel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

____ is the largest size aggregate used for structural fill

A

12”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A typical drainage trench should be at least ____ wide and at least ___ below the pipe

A

18” wide, 12” below

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A 6:3 slope means

A

3- foot rise or drop for every 6 feet of horizantal distance or a 6 foot rise orr drop for evey 3 feet of horizantal distance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Material excavated from the trench and piled adjacent to it, mut be maintained so that the toe of the slope is a minimum ___ from the edge of trench

A

2 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Damp proofing prevents?

A

penetration of moisture through the foundation wall in below-grade applications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the minimum clearance required under all portions of pipe?

A

6 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Underpinning is used when?

A

An excavation goes below foundations of the existing structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When filling unsuitable areas a general rule of thumb for dirt to aggregate is?

A

Figure one cubic yard of dirt for every 2 tons of aggregate used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Coarse grain soils have ___ % dry weight of the consituent material retained on the no. 200 sieve.

A

50%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Trench excavation in advance of pipe laying must not exceed ____ feet in length

A

150 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

For maximum compaction, material backfilled into a trench should be placed with ___ lifts

A

6 inch lifts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Asphalt is sprayed at a rate of?

A

0.10 to 0.15 gallons per yard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Minimum allowance in compaction?

A

90%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cut and fill

A

Cut (c) = lower than the ref. point

Fill (f) = higher than the ref. point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Hub

A

Small stake driven into the ground to identify some reference point

17
Q

Reference stake

A

Identifies hub’s elevation and situation in relation to the pipeline.

18
Q

Sta 2 + 50
El 2,500 ^47
C 9^63

A

Reference hub is 250 feet from the starting point

Flow line of pipe is 9.63 feet below the hub

Hub’s elevation is 2,500.47

Flow line elevation is 2,490.84

19
Q

For violating a blustake provision what is the maximum fine per violation?

A

$5,000