Exam Prep Flashcards
An element of the project scope statement is: A. Acceptance criteria. B. A stakeholder list. C. A summary budget. D. High-level risks.
A. Acceptance criteria.
Which document describes the necessary information to determine if a project is worth the required investment? A. Cost baseline B. Service level agreement C. Memorandum of understanding D. Business case
D. Business case
Which input to the Plan Risk Management process provides information on high-level risks? A. Project charter B. Enterprise environmental factors C. Stakeholder register D. Organizational process assets
A. Project charter
Which item is an example of personnel assessment? A. Resource calendar B. Tight matrix C. Team-building activity D. Focus group
D. Focus group
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project? A. Feedback analysis B. Stakeholder analysis C. Communication management plan D. Stakeholder management plan
“D. Stakeholder management plan
Stakeholder engagement plan. Described in Section 13.2.3.1. The stakeholder engagement plan provides
guidance and information on managing stakeholder expectations”
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project? A. Procurement documents B. Communications plan C. Project charter D. Stakeholder register
C. Project charter
The Identify Stakeholders process is found in which Process Group? A. Initiating B. Monitoring and Controlling C. Planning D. Executing
A. Initiating
An input to Develop Project Charter is a/an: A. Business case. B. Activity list. C. Project management plan. D. Cost forecast.
A. Business case.
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project? A. Project Risk Management B. Project Human Resource Management C. Project Scope Management D. Project Stakeholder Management
D. Project Stakeholder Management
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements? A. Stakeholder register B. Scope management plan C. Stakeholder management plan D. Project charter
A. Stakeholder register
In which Knowledge Area is the project charter developed? A. Project Cost Management B. Project Scope Management C. Project Time Management D. Project Integration Management"
D. Project Integration Management
The ability to influence cost is greatest during which stages of the project? A. Early B. Middle C. Late D. Completion
A. Early
The ability to influence cost is greatest at the early
stages of the project, making early scope definition critical (see Section 5.3).
Which process involves developing an approximation of the monetary resources needed to complete project activities? A. Estimate Costs B. Control Costs C. Determine Budget D. Plan Cost Management
A. Estimate Costs
Which tool or technique is used in the Develop Project Management Plan process? A. Pareto diagram B. Performance reporting C. SWOT analysis D. Expert judgment
D. Expert judgment
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk: A. Responses B. Appetite C. Tolerance D. Attitude
A. Responses
An output of the Manage Stakeholder Engagement process is: A. change requests B. enterprise environmental factors C. the stakeholder management plan D. the change log
A. change requests
Which process numerically analyzes the effect of identified risks on overall project objectives?
A. Plan Risk Management
B. Plan Risk Responses
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis
C. Perform Quantitative Risk Analysis
Which Collect Requirements output links the product requirements to the deliverables that satisfy them? A. Requirements documentation B. Requirements traceability matrix C. Project management plan updates D. Project documents updates
B. Requirements traceability matrix
A temporary endeavor that creates a unique product or service is called a: A. Project B. Plan C. Program D. Portfolio
A. Project
The process of prioritizing risks for further analysis or action is known as:
A. Plan Risk Management.
B. Plan Risk Responses.
C. Perform Qualitative Risk Analysis.
D. Perform Quantitative Risk Analysis.
C. Perform Qualitative Risk Analysis.
Stakeholder satisfaction should be managed as a key project: A. Benefit B. Initiative C. Objective D. Process
C. Objective
Which cost is associated with non conformance? A. Liabilities B. Inspections C. Training D. Equipment
A. Liabilities
Identify Risks is part of which Process Group? A. Planning B. Executing C. Closing D. Initiating
A. Planning
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the: A. Project management plan. B. Project charter. C. Work breakdown structure. D. Stakeholder register.
B. Project charter.