EXAM 3 Flashcards

1
Q

What is the primary purpose of Inventory

A

The primary purpose of inventory is to decouple supply and demand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What rule does inventory follow?

A

Inventory typically follows the 80-20 rule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Planning and control (4)

A
  • master scheduling
  • material requirements planning
  • production activity control
  • vendor order management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A Top-Down Model of Manufacturing Planning and Control Systems

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Master Scheduling (2)

A
  • A detailed planning process that tracks production output
  • States exactly when and in what quantities specific products will be made.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The Master Schedule Record (5)

A

– Forecasted demand
– Booked orders
– Projected inventory levels
– Production quantities
– Units still available to meet customer needs (Available to Promise)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The MPS must be realistic in terms of what can be ______

A

Manufactured

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Forecasted demand?

A

A company’s best estimate of the demand in any period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are Booked Orders?

A

Confirmed demand for products

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the Master Production Schedule (MPS) (2)

A
  • The amount of product that will be finished and available for sale at the beginning of each week
    – The MPS must be realistic
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Projected Ending Inventory

A

Estimate of what inventory levels will look like at the end of each WEEK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Available to Promise

A

Indicates the number of units that are available for sale each week, given those that have already been promised to customers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Planning Horizon

A

The amount of time MRP record extends into the
future.

The longer the production and supplier lead times, the longer the planning horizon must be.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How long must Panning Horizons Be?

A

at LEAST as long as the longest LEAD time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Material Requirements Planning (MRP)

A

translates the master production schedule into planned orders for the actual parts and components needed to produce the master schedule items.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does MRP manage?

A

MRP manages dependent demand inventory

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

MRP is based on (4)

A

– The bill of material (BOM)
– Backward Scheduling
– Explosion of the bill of material
- Inventory Record File

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How accurate must BOM and Inventory Record Be to be effective?

A

BOM and Inventory records need to be 99%+ accurate
for MRP to be effective

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Bill of material (BOM)

A

A listing of all parts and raw materials that go into an assembly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Exploding the BOM

A

The process of working backward from the master production schedule for a level 0 item to determine the quantity and timing of orders for the various subassemblies and components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

The MRP Record (6)

A

– Gross Requirements
– Scheduled Receipts
– Planned Receipts
– Planned Orders
– Projected Ending Inventory
– Net Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Material Requirements Planning (MRP) is a dependent demand system for ___________?

A

planning components below the product or end item level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

In MRP, the due date for a component will equal _________?

A

the start date of the parent item

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A valid Master Production Schedule (MPS) needs to include ________ (3)

A
  • A part Number
  • Quantity
  • Date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is an MRP Explosion referred to as?

A

The level by level netting of requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

When configured properly, MRP allows organizations to increase customer service levels while also decreasing inventory levels by time phasing requirements.

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is the feature in MRP that allows a Planner to trace the requirement for a component item up to the end item product it is needed for.

A

Pegging

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Prerequisites for a successful MRP system include (4)

A
  • Bill of Material file
  • Inventory Record file
  • Master Production Schedule
  • a computer to manipulate data.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Review CLOSED LOOP CHART

A
30
Q

What type of system is MRP

A

exception-based system

31
Q

What are the Pegging Requirements?

A

trace every order for lower-level items through all the levels of the BOM, up to the Master Production Schedule

32
Q

What type of chart does the Shop Floor Control Look like?

A

Funnel Chart

33
Q

Major Functions of Shop Floor Control (6)

A

1) Assigning priority to shop order
2) Maintaining Work-In-Process (WIP)
3) shop order status information
4) output data for capacity control purposes
5) Providing quantity for WIP Inventory
6) Providing measures of efficiency/production

34
Q

Shop Floor Control is concerned with _________

A

executing the Master Production Schedule on the factory floor, using Input/Output Control

35
Q

Loading meaning

A

assigning tasks to a particular work center to be performed
during a schedule period

36
Q

Dispatching meaning

A

sequencing tasks within a work center

37
Q

Expediting Meaning

A

giving extra attention to improve the progress of particular
orders.
Instructor Observation: Manufacturing organizations that excel at Expediting are typically poor at Planning.

38
Q

Job sequencing rules (3)

A

– First come, first served (FCFS)
– Earliest due date (EDD)
– Critical ratio (CR)

39
Q

Critical ratio Calculation

A
40
Q

What does the Critical Ratio Total mean

A

▪ Critical Ratio = 1 indicates that the amount of task
time equals the amount of time left, hence any
time spent waiting will make the job late.
▪ Critical Ratio < 1 indicates that the job is going to
be late unless something changes.
▪ Jobs with the lowest Critical Ratio are scheduled
to go first.

41
Q

Dispatching Techniques (8)

A
  • Earliest Due Date
  • Shortest Processing Time
  • Longest Processing Time
  • Slack per Remaining Operation
  • First Come, First Serve
  • Critical Ratio
  • Available Capacity at next Operation
  • Random
42
Q

Shop Floor Control executes the Master Production Schedule on the factory floor.

A

TRUE

43
Q

The Routings file shows the steps of how a product is built and is akin to a roadmap for manufactured items.

A

TRUE

44
Q

The basic law of Input / Output control states that Inputs must be less than or equal to outputs, or backlogs will increase.

A

TRUE

45
Q

Key work order metrics include (3)

A
  • schedule adherence
  • work order aging
  • closed work orders with open requirements.
46
Q

Just-in-time

A

A philosophy of manufacturing based on
planned elimination of all waste and on continuous
improvement of productivity

47
Q

Lean

A

A philosophy of production that emphasizes the
minimization of the amount of all the resources (including
time) used in the various activities of an enterprise. It
involves identifying and eliminating non-value-adding
activities in design, production, supply chain
management, and dealing with customers

48
Q

What is Waste

A

Any activity that does not add value to the good
or service in the eyes of the consumer.

49
Q

Eight commonly recognized sources of waste

A

– Overproduction
– Waiting
– Unnecessary transportation
– Inappropriate process
– Unnecessary inventory
– Unnecessary/excess motion
– Defects
– Underutilization of employees

50
Q

The Lean Perspective on Inventory

A

The buildup of inventory hides the problems/disruptions that may occur but at a cost.

51
Q

What does inventory do to problems?

A

It hides them

52
Q

In Lean operations, waste is identified as…

A

anything that “consumes resources but does not add value”

53
Q

Lean Six Sigma

A

combines the organizational elements and tools of Six Sigma with Lean’s focus on waste reduction

54
Q

Lean Supply Chain Management

A

minimize the level of resources required to carry out all supply chain activities

55
Q

Kanban system

A

A production control approach that uses
containers, cards, or visual cues to control the production and
movement of goods through the supply chain

56
Q

Key Characteristics of a Kanban System

A

– Uses simple signaling mechanisms to indicate when
specific items should be produced or moved.
– Can be used to synchronize activities either within a plant
or between different supply chain partners.
– Are not considered planning tools, but rather control
mechanisms that are designed to pull parts or goods
through the supply chain based on downstream demand.

57
Q

Two-card kanban system

A

A special form of the
Kanban system that uses one card to control production
and another card to control movement of materials.
– Move card – A kanban card that is used to indicate
when a container of parts should be moved to the
next process step.
– Production card – A kanban card that is used to
indicate when another container of parts should be
produced

58
Q

What is a pull system

A

– downstream demand sets off a chain of events that pulls material through the various process steps.
– A kanban system is also called a pull system.

59
Q

The Toyota Production System (TPS) pioneered lean thinking and may be the most copied and imitated business process in history.

A

TRUE

60
Q

Logistics is only 8% of GDP in the USA, but
without it the other 92% can’t happen

A

TRUE

61
Q

Logistics Management Activities (6)

A

– Transportation
– Warehousing
– Material handling
– Packaging
– Inventory management
– Logistics information systems

62
Q

Five Transportation Modes

A
  • Water
  • Air
  • Highway
  • Pipeline
  • Rail
63
Q

What is the largest transportation method

A

Trucking accounts for the largest percent of freight movement in the USA, and Less Than Truckload (LTL) shipments are most commonly used.

64
Q

Hub and Spoke System

A

A form of warehousing in which strategically placed hubs are used as sorting or transfer facilities

65
Q

What is Warehousing and what does it do? (4)

A

– Lower inventory-related costs
– Reduce transportation costs
– Improve operational flexibility
– Shorten lead times

66
Q

Different Types of Warehousing (4)

A
  • Spot Stock
  • Cross Docking
  • Assortment
  • Reverse Logistics
67
Q

Consolidation Warehousing

A
68
Q

Cross Docking

A
69
Q

Third-party logistics providers are ________

A

(3PL) are widely used due to the specialized nature and high capital costs associated with Logistics.

70
Q

Perfect Order Equation

A
71
Q

Reverse logistics system

A

A complete supply chain
dedicated to the reverse flow of products and materials
for the purpose of returns, repair, remanufacture, and/or
recycling

72
Q

Software as a Service (SaaS) and Cloud have enabled smaller companies to access improved tool sets.

A

TRue