Evolution 2 Utilize a Foam Carrier to deliver finished foam to a handline/deckgun Flashcards
Foam Carrier stops at supply pumper located at the hydrant. Members pull sufficient 3½” hose to attach to supply pumper. Use the hose load ending with the ______ coupling.
Fill in the blank
2.2
Female
Carrier proceeds, stretching 3½” hose to a point as close to the operation as possible. The Chauffeur connects the 3½” hose to what type of inlet of the foam carrier?
2.3 & 2.4
Gated
The chauffeur opens the gate to the large caliber self-educting foam nozzle. One member climbs onto the deck of the apparatus. Water is started. The self-educting nozzle with its pre-connected pick up tube will start to deliver finished firefighting foam. When should the member train the nozzle at the fire?
2.6 & 2.7
This member trains the nozzle at the fire when the finished firefighting foam is flowing through the nozzle.
The remaining members of the company now place a foam hand line into operation by stretching sufficient ___” hose from the pre-connected eductor.
Fill in the blank
2.8
1¾”
For example, a 310 GPM high capacity foam nozzle and a 95 GPM foam nozzle could supply 405 GPM of solution. Educting at 3% solution, there will be enough concentrate in the 1000-gallon booster tank for approximately __ minutes.
Fill in the blank
2.12
80
The pumper supplying water to the Carrier can be used to supply other handlines.
True or false
2.13
False
The pumper supplying water to the Carrier should be designated for the Carrier only.