EVM Flashcards

1
Q

Control costs

A

The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cost baseline

A

The approved version of the project budget.

the cost baseline includes contingency reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value Management (EVM)

A

Integrate scope, schedule and cost
Allows early identification of trends and variances from the baseline
Include contingencies but does not include management reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

EMV 4 key data points

A

planned value PV
Earned value EV
Actual cost AC
Budget at completion BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Variance is from the approved baseline

A

Scheduled variance SV
Cost variance CV
Schedule Performance Index SPI
Cost performance index CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Forecasting is about making estimates or predictions of conditions in the project’s future

A

Estimate to complete ETC

Estimate at completion EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Planned Value PV

A

estimated value of the work planned to be done as of a particular date.
PV is calculated BEFORE actually doing the work
Total PV for the project = budget at completion (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cumulative PV

A

= total PV = BAC = Project total budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Current PV

A

The approved budget for activities scheduled to be performed during a given period. This period could represent days, weeks, months.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Earned value EV

A

the cost of work that has actually been completed as of a particular date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Most common method for allocating budget/credit to a task

A

%Complete = the % of work performance is credited according to the actual % completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Actual cost AC

A

from invoices, deposits, receipts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Schedule Variance SV

A

= EV - PV

answers the question “ Are we ahead or behind schedule”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

SV%

A

= SV/EV

-20% SV means that, to-date, 20% of the work that was planned to be completed has not been accomplished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost Variance

A

=EV - AC

over or under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

CV%

A

negative CV% indicates project is over budget in terms of %

17
Q

Schedule performance index SPI

A

shows the efficiency of a project team in utilizing time(schedule) in a project.
= EV/PV
>1 indicates very efficient in schedule
<1 indicates less efficient

18
Q

Cost performance index CPI

A

the efficiency in utilizing resources (money) in a project

=EV/CV

19
Q

Estimate at completion EAC

A

forecast how much money and time you expect to spend to get the project performance
“How much we are expecting the total project to cost”

20
Q

EACt

EACc

A

=Project duration/SPI

=BAC/CPI

21
Q

Estimate to completion ETC

A

how much more the project will cost from this point forward until the completion
ETC=EACc - AC

22
Q

Variance at completion VAC

A

the difference between what the project was originally expected to cost vs. what it is now expected to cost
= BAC - EACc

23
Q

To-Complete cost performance indicator

TCPI

A

How efficiently must we use our remaining resources.
the future required cost efficiency needed to achieve a target BAC
=(BAC - EV) / (BAC - AC)
TCPI >1 indicates the utilization of the resources is not good enough, the remainder can be harder

24
Q

To-Complete Schedule performance indicator

TSPI

A

How efficiently must we use our remaining time.
= (BAC - EV) / (BAC - PV)
TSPI indicates the project need to work harder in utilizing the remainning time