EVM Flashcards
Control costs
The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline
Cost baseline
The approved version of the project budget.
the cost baseline includes contingency reserves
Earned Value Management (EVM)
Integrate scope, schedule and cost
Allows early identification of trends and variances from the baseline
Include contingencies but does not include management reserves
EMV 4 key data points
planned value PV
Earned value EV
Actual cost AC
Budget at completion BAC
Variance is from the approved baseline
Scheduled variance SV
Cost variance CV
Schedule Performance Index SPI
Cost performance index CPI
Forecasting is about making estimates or predictions of conditions in the project’s future
Estimate to complete ETC
Estimate at completion EAC
Planned Value PV
estimated value of the work planned to be done as of a particular date.
PV is calculated BEFORE actually doing the work
Total PV for the project = budget at completion (BAC)
Cumulative PV
= total PV = BAC = Project total budget
Current PV
The approved budget for activities scheduled to be performed during a given period. This period could represent days, weeks, months.
Earned value EV
the cost of work that has actually been completed as of a particular date
Most common method for allocating budget/credit to a task
%Complete = the % of work performance is credited according to the actual % completed
Actual cost AC
from invoices, deposits, receipts
Schedule Variance SV
= EV - PV
answers the question “ Are we ahead or behind schedule”
SV%
= SV/EV
-20% SV means that, to-date, 20% of the work that was planned to be completed has not been accomplished
Cost Variance
=EV - AC
over or under budget