EVM Flashcards
1
Q
PV (Planned Value)
A
PV = Total Budget * % Work planned
2
Q
EV (Earned Value)
A
EV = Total Budget * % Work completed
EV = Percent Completed * Planned Value
3
Q
Cost Variance
A
CV = EV - AC
4
Q
Schedule Variance
A
SV = EV - PV
5
Q
Cost Performance Index
A
CPI = EV/AC
6
Q
Schedule Performance Index
A
SPI = EV/PV
7
Q
Estimate at Completion (EAC)
A
EAC = BAC/CPI
8
Q
Estimated Time to Complete
A
Original Time Estimate/SPI
9
Q
Positive CV
A
UNDER budget
10
Q
Negative CV
A
OVER Budget
11
Q
Positive SV
A
AHEAD of Schedule
12
Q
Negative SV
A
BEHIND Schedule
13
Q
CPI >=1
A
Efficiency in Utilizing
Resources allocated
14
Q
CPI < 1
A
Not efficient in utilizing
resources allocated
15
Q
SPI >= 1
A
Efficient in utilizing time