EVM Flashcards

1
Q

PV (Planned Value)

A

PV = Total Budget * % Work planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV (Earned Value)

A

EV = Total Budget * % Work completed

EV = Percent Completed * Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Variance

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule Variance

A

SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Performance Index

A

CPI = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Performance Index

A

SPI = EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate at Completion (EAC)

A

EAC = BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimated Time to Complete

A

Original Time Estimate/SPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Positive CV

A

UNDER budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Negative CV

A

OVER Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Positive SV

A

AHEAD of Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Negative SV

A

BEHIND Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

CPI >=1

A

Efficiency in Utilizing
Resources allocated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

CPI < 1

A

Not efficient in utilizing
resources allocated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

SPI >= 1

A

Efficient in utilizing time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

SPI < 1

A

Not Efficient in Utilizing Time

17
Q

What is the cost baseline?

A

Represents the original, approved budget for the project.
erves as a reference point for measuring and controlling the project’s cost performance.

18
Q

Explain how earned value management can be used to control costs and measure project performance

A

Cost Control: EVM enables managers to track actual costs against the planned budget (AC vs. EV). By analyzing the Cost Variance (CV), they can take corrective actions to control costs and keep the project within budget.

Performance Measurement: EVM provides a quantitative measure of how the project is performing in terms of cost and schedule adherence. It helps in assessing whether the project is meeting its objectives as planned.

Decision-Making: EVM equips project managers with actionable insights to make informed decisions regarding resource allocation, schedule adjustments, or changes to mitigate any deviations from the plan.