Estimates & Cost Plans Flashcards
What types of estimate are there?
a) Budget / feasibility
b) Cost estimate
c) Cost plan
How can a feasibility / budget be priced / presented?
- Rate per m2 or per functional unit
- May be presented as a range
- Benchmark the efficiencies (NIA:GIA, units per core, wall:floor, solid:glaze
What information do you need to be able to carry out an estimate?
- Type of building (function)
- New build or extension
- Location
- Size
- Indication of quality
- Site visit
What is the % error on an estimate?
10%
What is the purpose of an order of cost estimate?
To arrive at a cost limit for the client and establish affordability
Which design phases would you provide a cost estimate?
Stages 0-2
What is included in a cost estimate alongside the cost?
- Construction cost
- Preliminaries
- Contractor’s OH&P
- Risk
- Inflation
- Assumptions & Exclusions
- Cost reconciliation
- Programme
- Benchmarking (Reconciliation)
- VE Proposals
- Basis of Estimate – drawings / specifications list
Name the elemental structure of a cost plan?
- Facilitating Works
- Substructure – excavation and substructure
- Superstructure – frame, upper floors, external walls, roof, internal finishes
- FFE
- Services
- External works
- Prelims
- OHP
- Risks
What is contingency?
- A sum included in the estimate to cover unknown expenses or unmitigated risks during the project
What are preliminaries?
- They define the scope of works
- Include the project, lists of drawings, description of the site, scope of work, details of management arrangements
- Often contain items for pricing which are general items needed by the contractor to carry out the work that cannot be attributed to specific items of work
Name some preliminaries sections
Fixed
Time related
which should be based on the project particulars
What should be considered when assessing preliminaries levels?
a) Length of contract
b) Location – accessibility, space restrictions, accommodation possibilities etc
c) Type of project – new build / refurb, tower / one story etc
d) Size of project
e) Need for temporary works
f) Need for security
g) Limitations on method and sequencing of works, working hours – supervision requirements
h) Sectional completion
i) Availability of services
j) Level of contractor’s designed works
What would you consider when benchmarking? And how might you benchmark?
£/m2, £/unit, £/sq.ft
Location Time Abnormals Procurement Tender strategy Type of Contract
What does TPI show?
Comparison of lowest accepted tender for new work to account for market conditions
What is the BCIS?
- Provides construction cost and price information through publications, online services and price books
What is a cost plan?
- It is used by the cost consultant to control the development of the design
- It identifies the client’s agreed cost limit and how the money is to be allocated to the different parts of the building
What is the difference between a cost estimate and a cost plan?
- Cost plan is a plan of costs for the works in preparation for turning into a cost report to check against.
- Estimate is a forecast of construction cost
What is an estimate? What is the % on cost certainty?
Carried out usually prior to Cost Planning
o Set a realistic cost limit
o Ascertain 85/90% cost certainty
Explain the function of a budget estimate and how you would carry one out?
To provide budgetary and a true reflection on the clients budget
What design info needed for OOC?
Accomodation schedule Nr of units Area Plans Functionality £/m2 allowances Min Storey heights NRM1 Risks
What design info for a cost plan?
Stage Report (all disciplines) Elevations GAs Landscaping Specification (FFE) Structural Design BIM Model
What have you excluded in one of your cost plans?
Brexit related impacts Demolition of Interim Landscaping Covid 19 Inflation Professional Fees VAT Section 106 Stats
What is the purpose of an OOC?
To form a cost limit for the client
What is a cost plan? And its purpose?
An elemental breakdown of the Cost Plan which may be further developed
Enhances cost control throughout DD