Estimates & Cost Plans Flashcards

1
Q

What types of estimate are there?

A

a) Budget / feasibility
b) Cost estimate
c) Cost plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How can a feasibility / budget be priced / presented?

A
  • Rate per m2 or per functional unit
  • May be presented as a range
  • Benchmark the efficiencies (NIA:GIA, units per core, wall:floor, solid:glaze
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What information do you need to be able to carry out an estimate?

A
  • Type of building (function)
  • New build or extension
  • Location
  • Size
  • Indication of quality
  • Site visit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the % error on an estimate?

A

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of an order of cost estimate?

A

To arrive at a cost limit for the client and establish affordability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which design phases would you provide a cost estimate?

A

Stages 0-2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is included in a cost estimate alongside the cost?

A
  • Construction cost
  • Preliminaries
  • Contractor’s OH&P
  • Risk
  • Inflation
  • Assumptions & Exclusions
  • Cost reconciliation
  • Programme
  • Benchmarking (Reconciliation)
  • VE Proposals
  • Basis of Estimate – drawings / specifications list
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Name the elemental structure of a cost plan?

A
  • Facilitating Works
  • Substructure – excavation and substructure
  • Superstructure – frame, upper floors, external walls, roof, internal finishes
  • FFE
  • Services
  • External works
  • Prelims
  • OHP
  • Risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is contingency?

A
  • A sum included in the estimate to cover unknown expenses or unmitigated risks during the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are preliminaries?

A
  • They define the scope of works
  • Include the project, lists of drawings, description of the site, scope of work, details of management arrangements
  • Often contain items for pricing which are general items needed by the contractor to carry out the work that cannot be attributed to specific items of work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Name some preliminaries sections

A

Fixed
Time related
which should be based on the project particulars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What should be considered when assessing preliminaries levels?

A

a) Length of contract
b) Location – accessibility, space restrictions, accommodation possibilities etc
c) Type of project – new build / refurb, tower / one story etc
d) Size of project
e) Need for temporary works
f) Need for security
g) Limitations on method and sequencing of works, working hours – supervision requirements
h) Sectional completion
i) Availability of services
j) Level of contractor’s designed works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What would you consider when benchmarking? And how might you benchmark?

A

£/m2, £/unit, £/sq.ft

Location
Time
Abnormals
Procurement 
Tender strategy
Type of Contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does TPI show?

A

Comparison of lowest accepted tender for new work to account for market conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the BCIS?

A
  • Provides construction cost and price information through publications, online services and price books
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a cost plan?

A
  • It is used by the cost consultant to control the development of the design
  • It identifies the client’s agreed cost limit and how the money is to be allocated to the different parts of the building
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the difference between a cost estimate and a cost plan?

A
  • Cost plan is a plan of costs for the works in preparation for turning into a cost report to check against.
  • Estimate is a forecast of construction cost
18
Q

What is an estimate? What is the % on cost certainty?

A

Carried out usually prior to Cost Planning
o Set a realistic cost limit
o Ascertain 85/90% cost certainty

19
Q

Explain the function of a budget estimate and how you would carry one out?

A

To provide budgetary and a true reflection on the clients budget

20
Q

What design info needed for OOC?

A
Accomodation schedule
Nr of units
Area Plans
Functionality
£/m2 allowances
Min Storey heights
NRM1 Risks
21
Q

What design info for a cost plan?

A
Stage Report (all disciplines)
Elevations
GAs
Landscaping
Specification (FFE)
Structural Design
BIM Model
22
Q

What have you excluded in one of your cost plans?

A
Brexit related impacts
Demolition of Interim Landscaping
Covid 19
Inflation
Professional Fees
VAT
Section 106
Stats
23
Q

What is the purpose of an OOC?

A

To form a cost limit for the client

24
Q

What is a cost plan? And its purpose?

A

An elemental breakdown of the Cost Plan which may be further developed

Enhances cost control throughout DD

25
Q

£/ft2 on benchmarking for a development like this?

A

£260 - £360/sq.ft

26
Q

In your Cost Plan did you factor in anything for Brexit, inflation etc?

A

Import Tariffs

Exchange rate

27
Q

How to build up a rate by first principles?

A
Don't have a rate to benchmark or pricing document.
Labour
Plant 
Materials
OHP
SC Design
Prelims
Risk
28
Q

What abnormals may you have on a cost plan?

A

Site Constraints
Planning conditions
Stats
Pre-existing buildings

29
Q

What is included in Facilitating Works?

A

All elements included within Section 0
Demolition works, works involving the
removal of hazardous and deleterious materials, and soil stabilisation

30
Q

What are the steps of undertaking a cost plan?

A
Establish a team for cost plan
Upload Drawings to CATO 
Design queries & responses
Prepare quants in line with NRM1
Prepare rates (market test / benchmark)
Benchmark 
Reconciliation
Submit draft for comment
Issue final / present
31
Q

How would you include preliminaries in your cost plans?

A

Benchmark

Fixed / Time related costs as stipulated by NRM

32
Q

What is a cost reconciliation?

A

Reconciling from your original estimate showing elementally movements, showing the client where cost movements have been

33
Q

What are the constituent parts of your cost plan?

A
Building Works Estimate
Preliminaries
Design Team Fees 
OH&P
Risk Allowance
Inflation
34
Q

What would you use as a first instance to provide inflation to your cost plan?

A

Mace have direct tender returns from construction Greater visibility on actual tender returns
More comparable projects to benchmark and TPI

35
Q

What would you adjust cost plans to consider different procurement routes?

A

As the design has been developed further I’d expect items such as
Risk
Prelims
Design Fees to be different

36
Q

Have you managed the cost plan? If so, what was the process you undertook as a first instance?

A

Establish a team

Coordinate design queries and meetings

37
Q

How might costs differ based on the procurement route / tendering strategy?

A

All based on
Design
Risk
Prelims

Increase in prelims for two stage but likely less risk
More risk / design fees in single stage

38
Q

What types of inflation are you aware of?

A

TPI

Construction

39
Q

What is Building Works, Base, Cost Limit?

A

Building - Facilitating, Building Works, Prelims, OHP
Base - all above + design fees
Cost limit - all above exl inflation

40
Q

Where would you expect tenders to come back against your cost plan?

A

Generally I’d expect this to be within 5% of my S3 Cost Plan, however, I would utilise visibility on tender returns to understand and ascertain what the market is showing on tender returns.

Generally,

Some higher / lower tenders
Cost Plan is assessed on current market conditions
Risks on projects

41
Q

How is a cost estimate impacted by procurement / tendering strategies?

A

TBC??