Estimates & Cost Plans Flashcards

1
Q

What types of estimate are there?

A

a) Budget / feasibility
b) Cost estimate
c) Cost plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How can a feasibility / budget be priced / presented?

A
  • Rate per m2 or per functional unit
  • May be presented as a range
  • Benchmark the efficiencies (NIA:GIA, units per core, wall:floor, solid:glaze
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What information do you need to be able to carry out an estimate?

A
  • Type of building (function)
  • New build or extension
  • Location
  • Size
  • Indication of quality
  • Site visit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the % error on an estimate?

A

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of an order of cost estimate?

A

To arrive at a cost limit for the client and establish affordability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which design phases would you provide a cost estimate?

A

Stages 0-2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is included in a cost estimate alongside the cost?

A
  • Construction cost
  • Preliminaries
  • Contractor’s OH&P
  • Risk
  • Inflation
  • Assumptions & Exclusions
  • Cost reconciliation
  • Programme
  • Benchmarking (Reconciliation)
  • VE Proposals
  • Basis of Estimate – drawings / specifications list
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Name the elemental structure of a cost plan?

A
  • Facilitating Works
  • Substructure – excavation and substructure
  • Superstructure – frame, upper floors, external walls, roof, internal finishes
  • FFE
  • Services
  • External works
  • Prelims
  • OHP
  • Risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is contingency?

A
  • A sum included in the estimate to cover unknown expenses or unmitigated risks during the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are preliminaries?

A
  • They define the scope of works
  • Include the project, lists of drawings, description of the site, scope of work, details of management arrangements
  • Often contain items for pricing which are general items needed by the contractor to carry out the work that cannot be attributed to specific items of work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Name some preliminaries sections

A

Fixed
Time related
which should be based on the project particulars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What should be considered when assessing preliminaries levels?

A

a) Length of contract
b) Location – accessibility, space restrictions, accommodation possibilities etc
c) Type of project – new build / refurb, tower / one story etc
d) Size of project
e) Need for temporary works
f) Need for security
g) Limitations on method and sequencing of works, working hours – supervision requirements
h) Sectional completion
i) Availability of services
j) Level of contractor’s designed works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What would you consider when benchmarking? And how might you benchmark?

A

£/m2, £/unit, £/sq.ft

Location
Time
Abnormals
Procurement 
Tender strategy
Type of Contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does TPI show?

A

Comparison of lowest accepted tender for new work to account for market conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the BCIS?

A
  • Provides construction cost and price information through publications, online services and price books
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a cost plan?

A
  • It is used by the cost consultant to control the development of the design
  • It identifies the client’s agreed cost limit and how the money is to be allocated to the different parts of the building
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the difference between a cost estimate and a cost plan?

A
  • Cost plan is a plan of costs for the works in preparation for turning into a cost report to check against.
  • Estimate is a forecast of construction cost
18
Q

What is an estimate? What is the % on cost certainty?

A

Carried out usually prior to Cost Planning
o Set a realistic cost limit
o Ascertain 85/90% cost certainty

19
Q

Explain the function of a budget estimate and how you would carry one out?

A

To provide budgetary and a true reflection on the clients budget

20
Q

What design info needed for OOC?

A
Accomodation schedule
Nr of units
Area Plans
Functionality
£/m2 allowances
Min Storey heights
NRM1 Risks
21
Q

What design info for a cost plan?

A
Stage Report (all disciplines)
Elevations
GAs
Landscaping
Specification (FFE)
Structural Design
BIM Model
22
Q

What have you excluded in one of your cost plans?

A
Brexit related impacts
Demolition of Interim Landscaping
Covid 19
Inflation
Professional Fees
VAT
Section 106
Stats
23
Q

What is the purpose of an OOC?

A

To form a cost limit for the client

24
Q

What is a cost plan? And its purpose?

A

An elemental breakdown of the Cost Plan which may be further developed

Enhances cost control throughout DD

25
£/ft2 on benchmarking for a development like this?
£260 - £360/sq.ft
26
In your Cost Plan did you factor in anything for Brexit, inflation etc?
Import Tariffs | Exchange rate
27
How to build up a rate by first principles?
``` Don't have a rate to benchmark or pricing document. Labour Plant Materials OHP SC Design Prelims Risk ```
28
What abnormals may you have on a cost plan?
Site Constraints Planning conditions Stats Pre-existing buildings
29
What is included in Facilitating Works?
All elements included within Section 0 Demolition works, works involving the removal of hazardous and deleterious materials, and soil stabilisation
30
What are the steps of undertaking a cost plan?
``` Establish a team for cost plan Upload Drawings to CATO Design queries & responses Prepare quants in line with NRM1 Prepare rates (market test / benchmark) Benchmark Reconciliation Submit draft for comment Issue final / present ```
31
How would you include preliminaries in your cost plans?
Benchmark | Fixed / Time related costs as stipulated by NRM
32
What is a cost reconciliation?
Reconciling from your original estimate showing elementally movements, showing the client where cost movements have been
33
What are the constituent parts of your cost plan?
``` Building Works Estimate Preliminaries Design Team Fees OH&P Risk Allowance Inflation ```
34
What would you use as a first instance to provide inflation to your cost plan?
Mace have direct tender returns from construction Greater visibility on actual tender returns More comparable projects to benchmark and TPI
35
What would you adjust cost plans to consider different procurement routes?
As the design has been developed further I'd expect items such as Risk Prelims Design Fees to be different
36
Have you managed the cost plan? If so, what was the process you undertook as a first instance?
Establish a team | Coordinate design queries and meetings
37
How might costs differ based on the procurement route / tendering strategy?
All based on Design Risk Prelims Increase in prelims for two stage but likely less risk More risk / design fees in single stage
38
What types of inflation are you aware of?
TPI | Construction
39
What is Building Works, Base, Cost Limit?
Building - Facilitating, Building Works, Prelims, OHP Base - all above + design fees Cost limit - all above exl inflation
40
Where would you expect tenders to come back against your cost plan?
Generally I'd expect this to be within 5% of my S3 Cost Plan, however, I would utilise visibility on tender returns to understand and ascertain what the market is showing on tender returns. Generally, Some higher / lower tenders Cost Plan is assessed on current market conditions Risks on projects
41
How is a cost estimate impacted by procurement / tendering strategies?
TBC??