ESC Inspector Flashcards

1
Q

3.02 Stone Construction Entrance

A

A stabilized stone pad with a filter fabric underliner located at points of vehicular ingress and egress on a construction site, used to reduce the amount of mud transported onto paved public roads by motor vehicles or runoff.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

3.03 Construction Road Stabilization

A

The temporary stabilization of access roads, subdivision roads, parking areas, and other on-site vehicle transportation routes with stone immediately after grading. To reduce erosion of temporary roadbeds by construction traffic durring wet weather. To reduce the erosion and subsequent regrading or permanent roadbeds between the time of initial grading and final stabilization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

3.04 Straw Bale Barrier

A

A temporary sediment barrier consisting of a row of entrenched and anchored straw bales. To intercept and detain small amounts of sediment from disturbed areas of limited extent in order to prevent sediment from leaving the construction site. To decrease the velocity of sheet flows.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

3.05 Silt Fence

A

A temporary sediment barrier consisting of a synthetic fiber fabric stretched across and attached to supporting posts and entrenched. To intercept and detain small amounts of sediment from disturbed areas during construction operations in order to prevent sediment from leaving the site. To decrease the velocity of sheet flows and low-to-moderate level channel flows.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

3.06 Brush Barrier

A

A temporary sediment barrier constructed at the perimeter of a disturbed area from the residue materials available from clearing and grubbing the site. To intercept and retain sediment from disturbed areas of limited extent, preventing sediment from leaving the site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

3.07 Storm Drain Inlet Protection

A

A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems prior to permanent stabilization of the disturbed area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

3.08 Culvert Inlet Protection

A

A sediment filter located at the inlet to storm sewer culverts. To prevent sediment from entering, accumulating in and being transferred by a culvert and associated drainage system prior to permanent stabilization of a disturbed project area. To provide erosion and drainage patterns change, causing original control measures to be ineffective or in need of removal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

3.09 Temporary Diversion Dike

A

A temporary ridge of compacted soil constructed at the top or base of a sloping disturbed area. To divert storm runoff from upslope drainage areas away from unprotected disturbed areas and slopes to a stabilized outlet. To divert sediment-laden runoff from a disturbed area to a sediment-trapping facility such as a sediment trap or sediment basin.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

3.10 Temporary Fill Diversion

A

A channel with a supporting ridge of soil on the lower side, constructed along the top of an active earth fill. To divert storm runoff away from the unprotected slope of the fill to a stabilized outlet or sediment-trapping facility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

3.11 Temporary Right-of-Way Diversion

A

A ridge of compacted soil or loose rock or gravel constructed across disturbed rights-of-way and similar sloping areas. To shorten the flow length within a sloping right-of-way, thereby reducing the erosion potential by diverting storm runoff to a stabilized outlet.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

3.12 Diversion

A

A channel constructed across a slope with a supporting earthen ridge on the lower side. To reduce slope length and to intercept and divert stormwater runoff to stabilized outlets at non-erosive vegetation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

3.13 Temporary Sediment Trap

A

A temporary ponding area formed by constructing an earthen embankment with a stone outlet. to detain sediment-laden runoff from small disturbed areas long enough to allow the majority of the sediment to settle out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

3.14 Temporary Sediment Basin

A

A temporary barrier or dam with a controlled stormwater release structure formed by constructing an embankment of compacted soil across a drainageway. To detain sediment-laden runoff from disturbed areas in “wet” and “dry” storage long enough for the majority of the sediment to settle out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

3.15 Temporary Slope Drain

A

A flexible tubing or conduit extending from the top to the bottom of a cut or fill slope. To temporarily conduct concentrated stormwater runoff safely down the face of a cut or fill slope without causing erosion on or below the slope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

3.16 Paved Flume

A

A permanent paved channel constructed on a slope. to conduct stormwater runoff safely down the face of a slope without causing erosion problems on or below the slope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

3.17 Stormwater Conveyance Channel

A

A permanent, designed waterway, shaped, sized, and lined with appropriate vegetation or structural material used to safely convey stormwater runoff within or away from a developing area. To provide for the conveyance of concentrated surface water to a receiving channel or system without damage from erosion.

17
Q

3.18 Outlet Protection

A

Structurally lined aprons or other acceptable energy dissipating devices placed at the outlets of pipes or paved channel sections. To prevent scour at stormwater outlets, to protect the outlets structure, and to minimize the potential for downstream erosion by reducing the veolocity and energy of concentrated stormwater flows.

18
Q

3.19 Riprap

A

A permanent, erosion-resistant ground cover of large, loose, angular stone with filter fabric or granular underlining. To protect the soil from the erosive forces of concentrated runoff To slow the velocity of concentrated runoff while enhancing the potential for infiltration. To stabilize slopes with seepage problems and/or non-cohesive soils.

19
Q

3.20 Rock Check Dams

A

Small temporary stone dams constructed across a swale or drainage ditch. To reduce the velocity of concentrated stormwater flows, thereby reducing erosion of the swale or ditch. This practice also traps sediment generated from adjacent areas or the ditch itself, mainly by ponding of the stormwater runoff. Field experience has shown it to perform more effectively than silt fence or straw bales in the effor the stabilize “wet-weather” ditches.

20
Q

3.21 Level Spreader

A

An outlet for dikes and diversions consisting of an excavated depression constructed at zero grade across a slope. To convert concentrated runoff to sheet flow and release it uniformly onto areas stabilized by existing vegetation.

21
Q

3.22 Vegetative Streambank Stabilization

A

The use of vegetation in stabilizing streambanks. To protect streambanks from the erosive forces of flowing water.

22
Q

3.23 Structural Streambank Stablization

A

Methods of stabilizing the banks of live streams with permanent structural measures. To protect streambanks from the erosive forces of flowing water.

23
Q

3.24 Temporary Vehicular Stream Crossing

A

A temporary structural span installed across a flowing watercourse for use by construction traffic. Structures may include bridges, round pipe arches, or oval pipes. To provide a means for construction traffic to cross flowing streams without damaging the channel or banks. To keep sediment generated by construction traffic out of the stream.

24
Q

3.25 Utility Stream Crossing

A

A strategy for crossing small waterways when in-stream utility construction is involved. To help protect sediment from entering the stream from construction within approach areas. to minimize the amount of disturbance within the stream itself.

25
Q

3.27 Turbidity Curtain

A

A floating geotextile material which minimizes sediment transport from a disturbed area adjacent to or within a body of water. To provide sedimentation protection for a watercourse from up-slope land disturbance or from dredging or filling within the watercourse.

26
Q

3.26 Dewatering Structure

A

A temporary settling and filtering device for water which is discharges from dewatering activities. To filter sediment-laden water prior to the water being discharged off-site.

27
Q

3.28 Subsurface Drain

A

A perforated conduit such as a pipe, tubing or tile installed beneath the ground to intercept and convey ground water. To prevent sloping soils from becoming excessively wet and subject to sloughing. To improve the quality of the growth medium in excessively wet areas by lowering the water table. To drain stromwater detention areas or structures.

28
Q

3.29 Surface Roughening

A

Providing a rough soil surface with horizontal depressions created by operatinf a tillage or other suitable implement on the contour, or by leaving slopes in a roughened condition by not fine-grading them. To aid in establishment of vegitative cover with seed. To reduce runoff velocity and increase infiltration. To reduce erosion and provide for sediment trapping.

29
Q

3.30 Topsoiling

A

Methods of preserving and using the surface layer of undisturbed soil, often enriched in organic matter, in order to obtain a more desirable planting and growth medium. To provide a suitable growth medium for final site stabilization with vegetation.

30
Q

3.31 Temporary Seeding

A

The establishment of a temporary vegetative cover on disturbed areas by seeding with appropriate rapidly growing annual plants. To reduce erosion and sedimentation by stabilizing disturbed areas that will not be brought to final grade for a period of more than 30 days. To reduce damage from sediment and runoff to downstream or off-site areas, and to provide protection to bare soils exposed during construction until permanent vegetation or other erosion control measures can be established.

31
Q

3.32 Permanent Seeding

A

the establishment of perennial vegetative cover on disturbed areas by planting seed. To reduce erosion and decrease sediment yield from disturbed areas. To permanently stabilize disturbed areas in a manner that is economical, adaptable, to site conditions, and allows selection of the most appropriate plant materials. To improve wildlife habitat. To enhance natural beauty.

32
Q

3.33 Sodding

A

Stabilizing fine-graded areas by establishing permanent grass stands with sod. To establish permanent turf immediately. To prevent erosion and damage from sediment and runoff by stabilizing the soil surface. To reduce the production of dust and mud associated with bare soil surfaces. To stabilize drainage ways where concentrated overland flow will occur. For use as a filtering device for sediments in areas prior to achieving permanent stabilization.

33
Q

3.34 Burmudagrass and Zoysiagrass Establishment

A

The establishment of vegetative cover with hybrid Bermudagrass or Zoysiagrass by planting sprigs, stolons, or plugs. To reduce erosion and decrease sediment yield from disturbed areas. To stabilize disturbed areas with a specific plant material suited to the site at a cost of less than would be incurred by installing sod. To establish vegetative cover more rapidly than would be possible using seed.

34
Q

3.35 Mulching

A

Application of plant residues or other suitable materials to the soil surface. To prevent erosion by protecting the soil surface from raindrop impact and reducing the velocity of overland flows. To foster the growth of vegetation by increasing available moisture and providing insulation against heat and cold.

35
Q

3.36 Soil Stabilization Blankets and Matting

A

The installation of a protective covering (blanket) or a soil stabilization mat on a prepared planting areas of a steep slope, channel or shoreline. To aid in controlling erosion or critical areas by providing a microclimate which protects young vegetation and promotes its establishment. In addition, some types of soil stabilization mats are also used to raise the maximum permissible velocity of turf grass stands in channelized areas by “reinforcing the turf” to resist the forces of erosion during storm events.

36
Q

3.37 Trees, Shrubs, Vines, & Ground Covers

A

Stabilizing disturbed areas by establishing vegetative cover with trees, shrubs, vines, or ground covers. To aid in stabilizing soil in areas where vegetation other than turf is preferred. To provide food and shelter for wildlife habitat is desirable.

37
Q

3.38 Tree Preservation and Protection

A

Protection of desirable trees from mechanical and other injury during land disturbing and construction activity.

38
Q

3.39 Dust Control

A

Reducing surface and air movement of dust during land disturbing, demolition and construction activities.