Equipment Installation Flashcards

1
Q

Before new equipment arrives at the plant, plans for installing it are made by the

Equipment manufacturer
Maintenance supervisor
Plant engineer
Plant superintendent

A

Plant engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When pouring a concrete footing, you should hold the steel rods in position with

Metal clips
Tack welding
Tie wires
Wooden braces

A

Tie wires

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The best materials for filling around a foundation are gravel and

Black dirt
Broken stone
Clay
Ground concrete slabs

A

Ground concrete slabs 

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The type of bolt to anchor the equipment is usually specified by the

Equipment manufacturer
Maintenance department
Plant engineer
Plot plan

A

Equipment manufacturer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How long must new concrete sit before you can install equipment on it

Seven days
14 days
21 days
28 days

A

28 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Adding reinforcing steel to concrete increases the_____strength

Compressive
Sheer
Tensile
Yield

A

Tensile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Ready mixed concrete must be used within_____hour after mixing

One
Two
For
Six

A

One

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Retainers on the sides of horizontally, reciprocating equipment keep it from

Impacting
Over speeding
Vibrating
Walking

A

Walking 

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

To isolate anchor bolts, when mounting equipment on pads, surround the bolts with

Coil springs
Neoprene tubing
Plastic sleeves
Steel bushings

A

Neoprene tubing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What type of wrench should you use for tightening anchor bolts?

Long handled
Pneumatic
Stilson
Torque

A

Torque

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which type of isolator is used to control vibration for large pieces of equipment, such as forging hammers

Cork Mat
Felt Mat
Spring mounts
Waffle mat

A

Spring mounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which of the following should be used to set equipment, anchor bolts in an existing foundation

Coarse concrete
Fine Concrete
Grout
Mortar

A

Grout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What must you do first before disconnecting the electrical wiring to existing equipment

Check the line voltage
Open the switch box
Shut off the power
Tape, the exposed wire ends

A

Shut off the power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When moving equipment with a crowbar, what should you use between the bar and the floor?

A piece of pipe
A thin steel plate
A wad of waste material
A wood block

A

A wood block

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which of the following makes the strongest sling

Chain
Manila rope
Synthetic webbing
Wire rope

A

Chain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The common dial indicator is usually used with a________base

Brass
flexible
Magnetic
Semi rigid

A

Semi rigid

17
Q

Which of the following does not have the accuracy needed to level equipment

Bench level
Master precision level
Mechanics level
Optical level

A

Bench level

18
Q

Which of the following is true for aligning mating parts on a piece of equipment

Check alignment in one plane only
Only vertical alignment is necessary
Use a separate reference point for each part
Use one reference point for all parts

A

Use one reference point for all parts

19
Q

A mechanics level is precise enough for align

Conveyors
Lathes
Milling machines
Any of the above

A

Conveyors 

20
Q

The external airlines on equipment usually terminate just beyond a filter or a

Compressor
Pressure gauge
Reducer valve
Regulator 

A

Regulator

21
Q

You can keep the fluid pressure in a line near a present level with a____valve

Bypass
regulating
Relief
Start up

A

Regulating

22
Q

A copy of the manufactures test data is often attached to the_____of new equipment

Control panel
Crate
Manual
Switchbox

A

Manual

23
Q

High temperatures during equipment start up is usually caused by

Bad ventilation
Break not released
Poor lubrication
Running the equipment to fast

A

Poor lubrication

24
Q

The temporary filters used for flushing a lube. Oil system should have _______ the permanent filter,

A large capacity, than
A larger weave, than
A smaller capacity, than
The same capacity as

A

A larger capacity than 

25
Q

An allowable start up temperature for a piece of equipment is usually_________% above or below the normal operating temperature

5
10
15
20

A

5