1
Q

What is the weight of a 36-foot American standard I-beam designated S15 x 42.9? Use the equation W= w/ft x L

153.3 LB.
540.0 Lb
1544.4 LB
2145.5 Lb

A

1544.4 LB

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If both ends of a sling are attached to the hoist hook and the load is suspended by the center of the sling, what hitch is being used?

Basket
Choker
Double Basket
Double choker 

A

Basket

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

They hook should be removed from service If

The hook is discolored
The hook shows some scratches
The tip is bent or twisted
Wear has reduced the thickness by 2%

A

The tip is bent or twisted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Determine the weight of a load consisting of 100 brass rods, 6ft long and 1.5inches in diameter (the weight per linear foot is 6.51Lb)

651 lb
3906 lb
5859 lb
7890 lb

A

3906lb

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The point at which a load will balance is called

Apex
Center of gravity
Point of suspension
Stability point

A

Center of gravity 

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If the strands of a wire rope appear to spiral down to the right, and if the wire strands appear to be parallel to the rope axis, the wire rope is

Left Lang Lay
Left regular lay
Right Lang Lay
Right regular lay

A

Right regular lay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If a wire rope is classified as 6×37, the figure 37 means

Each strand of the rope contains a nominal 37 wires
The length of the rope is 37 rope lays
The rope is 37 feet long
There are a normal 37 strands in a rope

A

Each strand of the rope contains a nominal 37 wires

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of these wire rope and fittings are most efficient (assuming all are prepared correctly)?

Hand-tucked thimble slice
Speltered socket
Wedge socket
Wire-rope clips

A

Speltered socket

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

As a general rule, what are the minimum and maximum temperatures to which a wire rope sling may be exposed, and still maintain its strength

-20/ +200•F (-29/93•C)
-40/+300•F (-40/149•C)
-60/+400•F (-51/204•C)
-80/+600•F ( -62/316•C)

A

-60/+400•F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following is used to protect a rope loop from abrasion and sharp bends ?

Clip
Fist
Thimble
Wedge 

A

Thimble

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The process of joining two sections of rope by weaving the strands together is called

Seizing
Serving
Splicing
Swaging 

A

Splicing 

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which of the following hedges cannot be made with a basic single leg sling

Basket
Bridle
Choker
Vertical 

A

Bridle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The proof test value of a chain is at least _____ times the working load limit

Two
Three
Four
Five

A

Two

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The standard minimum design factor for metal mesh slings is

3
5
7
9

A

5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A fiber rope. Sling should be removed from service if it.

Becomes wet
Has been frozen and thawed
Shows kinking
Shows oil discoloration

A

Shows kinking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Nylon and polyester rope slings have a design factor of

5
7
9
11

17
Q

Before cutting a fiber rope, the ends should be________ to prevent fraying

Entwined
Spliced
Twisted
Whipped

A

Whipped 

18
Q

Synthetic webbing is spliced by

Cementing
Heat treating
Interweaving
Stitching

19
Q

The purpose of an upper limit switch is to

Cut power if a load weighs more than
Keep the load block from rising dangerously high
raise the load block when the hoist is not in use
Stop lifts at a height convenient for a job

A

Keep the load block from rising dangerously high 

20
Q

When a rigger lifts a load, a few inches, then stops to see if the load drift downward, what is he checking?

Gearbox
Hoist breaks,
Lower limit switch
Overload 

A

Hoist breaks

21
Q

A pneumatic hoist is typically used instead of an electric one, when

An electric spark could be dangerous
Coast is a factor
Lifting speed is important
The load is greater than an electric motor can handle

A

An electric spark could be dangerous

22
Q

With a double reeved hoist

The load hook travels sideways as loads are raised
The rope unwinds from one side of the drum to the other
True vertical lift is possible
Two hoist drums are involved 

A

True vertical lift is possible

23
Q

A top running crane with a bridge beams supported on legs is called a________ crane

Cantilevered
Gantry
Girder
Jib

24
Q

Hoist load chain, and sling chain

Are made of the same materials
Are subject to the same types of wear
Look similar
Receive the same heat treatment

A

Look similar 

25
One edge of the load serves as a pivot during_______ turning Double sling One hook Single sling Two hook
One hook
26
When should blocks or other holding devices be placed at the location where a load will be set? Before the load is lifted As soon as the load is lifted While the load is being moved While the load is suspended at the desired location
Before the load is lifted 
27
A lift in excess of rated capacity Can be made repeatedly once approved Does not require analysis by a qualified person Is never permitted May be authorized for a single lift
May be authorized for a single lift 
28
In general, you should not use a hoist or crane to pull a load, but it is permissible if you Attach a pulley block to the load Swing the boom of the crane to do the polling Use a manual chain, hoist in a horizontal set up Use rollers under the load
Use a manual chain, hoist in a horizontal set up 
29
As a generic rule, you should set a load on A concrete floor for stability Any surface as long as it doesn’t damage the load The sling that holds it, then tug it sharply away Wooden blocks to allow easy sling withdrawal
Wooden blocks to allow easy sling withdrawal 
30
Two hook turning of a suspended load Is accomplished with a single hoist Is the easiest turning method to use? Requires a minimum amount of planning Should be used only when absolutely necessary
Should be used only when absolutely necessary 
31
Selection of the proper sling material for a job is determined primarily by Environmental conditions Hitch arrangement Method of attachment to the load The shape of the load
Environmental conditions
32
When you secure a scaffold with Guy wires, what accessories do you use to tighten the wires to the correct tension? Cable clamps Thimbles Tumbuckles Wire rope clips
Tumbuckles
33
Unless otherwise specified, the maximum load that can safely be supported on a sectional metal scaffold is_______lb/ft2 pf work area 10 25 40 50
25
34
When using a screw jack to level a double pole scaffold, make sure The jacks base can support the weight without sinking The weight of the scaffold remains centered over the jack after leveling To replace the jack with round Timbers after leveling To work in the center of the scaffold, to avoid toppling the jack
The Jack’s base can support the weight without sinking 
35
When is ascending a ladder, make sure to Keep your back to the ladder Leave one hand free to carry tools Step carefully off the top rung Use a rope to raise needed materials
Use a rope to raise needed materials