EPC and OM Flashcards

1
Q

EPC vs EPCM (4)

A

accountability:

  • EPC: contractor are fully accountable
  • EPCM: owners have multiple points of accountability

risk:

  • EPC: contractor hold all risk
  • EPCM: owners hold all risk

time:
- EPC: first date of completion
- EPCM: no fixed completion schedule

price:
- EPC: fixed price or lump sum contract
- EPCM: material and time contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EPC service (4)

A
  • end to end contract arrangement to ensure project is complete
  • engineer: preparing, and survey
  • procurement: scope and requirement
  • construction: coordinate activity with subcontractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Total cost of ownership (TCO) (4)

A
  • what you see: direct cost
  • what you don’t see: indirect cost, total lifecycle cost
  • external: over time charge, holiday charges
  • internal: opportunity cost, resource cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Time and material (1)

A
  • contract guarantee profit for supplier, creates schedule, and cost overrun for buyer
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Typical project value leakage area (6)

A
  • contract structure does not align with project strategy
  • lack of specification and evaluation
  • design change
  • lack of experience
  • limited and non-existent
  • change order management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Mitigating project risk (6)

A
  • scope change: technical issues sometimes due to lack of supplier analysis
  • design delay: outsource of project supplier should be overviewed
  • new technology: provision of technology or construction wrap
  • financial stability: supplier qualification
  • supplier delay delivery: build a relationship
  • insufficient skilled labour: agree with key labour agencies
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Reason for contract change (4)

A
  • market conditions
  • technical issues
  • government/regulatory
  • requirement change
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Liquidated damage (3)

A
  • delayed LD: delay completion by 15-20%
  • performance LD: working in process with plant or equivalent. failure to meet specification
  • overall LD: 25-30% of contract value for EP contract, higher than usually found in non project finance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EPC contract (1)

A
  • contractor is the supplier of equipment which forms the greater part of project cost and it further subcontract civil work (preparation of project site)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

DB contract (2)

A
  • Civil work form the main part of contract cost, equipment supply is procured through sub-contractors
  • supply of equipment difference
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Other EPC consideration (3)

A
  • environmental guarantee
  • bonuses
  • position to contracting authority and offtakers: charges LD with late completion, incentive to ensure on time completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Project company termination (2)

A
  • LD alone may not cover project against poor performance

- may require construction contractor to restore the site to its original conditions and repay all sums

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why do engineer do anywayd (4)

A
  • due diligent report
  • monitor EPC
  • monitor plant/assets
  • assist during commercial operation date and asset handover
How well did you know this?
1
Not at all
2
3
4
5
Perfectly