EPC and OM Flashcards
1
Q
EPC vs EPCM (4)
A
accountability:
- EPC: contractor are fully accountable
- EPCM: owners have multiple points of accountability
risk:
- EPC: contractor hold all risk
- EPCM: owners hold all risk
time:
- EPC: first date of completion
- EPCM: no fixed completion schedule
price:
- EPC: fixed price or lump sum contract
- EPCM: material and time contract
2
Q
EPC service (4)
A
- end to end contract arrangement to ensure project is complete
- engineer: preparing, and survey
- procurement: scope and requirement
- construction: coordinate activity with subcontractor
3
Q
Total cost of ownership (TCO) (4)
A
- what you see: direct cost
- what you don’t see: indirect cost, total lifecycle cost
- external: over time charge, holiday charges
- internal: opportunity cost, resource cost
4
Q
Time and material (1)
A
- contract guarantee profit for supplier, creates schedule, and cost overrun for buyer
5
Q
Typical project value leakage area (6)
A
- contract structure does not align with project strategy
- lack of specification and evaluation
- design change
- lack of experience
- limited and non-existent
- change order management
6
Q
Mitigating project risk (6)
A
- scope change: technical issues sometimes due to lack of supplier analysis
- design delay: outsource of project supplier should be overviewed
- new technology: provision of technology or construction wrap
- financial stability: supplier qualification
- supplier delay delivery: build a relationship
- insufficient skilled labour: agree with key labour agencies
7
Q
Reason for contract change (4)
A
- market conditions
- technical issues
- government/regulatory
- requirement change
8
Q
Liquidated damage (3)
A
- delayed LD: delay completion by 15-20%
- performance LD: working in process with plant or equivalent. failure to meet specification
- overall LD: 25-30% of contract value for EP contract, higher than usually found in non project finance
9
Q
EPC contract (1)
A
- contractor is the supplier of equipment which forms the greater part of project cost and it further subcontract civil work (preparation of project site)
10
Q
DB contract (2)
A
- Civil work form the main part of contract cost, equipment supply is procured through sub-contractors
- supply of equipment difference
11
Q
Other EPC consideration (3)
A
- environmental guarantee
- bonuses
- position to contracting authority and offtakers: charges LD with late completion, incentive to ensure on time completion
12
Q
Project company termination (2)
A
- LD alone may not cover project against poor performance
- may require construction contractor to restore the site to its original conditions and repay all sums
13
Q
Why do engineer do anywayd (4)
A
- due diligent report
- monitor EPC
- monitor plant/assets
- assist during commercial operation date and asset handover