Energy and Atmosphere Flashcards
Cx Plan includes the following when pursuing EA-C Demand Response?
One performance test of full demand-response plan.
Proves that all equipment responds as planned and all parties understand their roles.
Carbon Offset?
Reduction in emissions of carbon dioxide or green house gases made to compensate for/offset an emission made elsewhere.
Exceptional Calculation Method applies to which EA Ps/Cs?
EA-P Minimum Energy Performance
EA-C Optimize Energy
To meet EA-C Optimize Energy project team will address nonregulated load savings by?
Using exceptional calculation method (ECM) in a whole-building energy simulation.
Green-e energy certification applies to which EA-C?
EA-C Green Power and Carbon Offsets
Which circumstances call for use of solar gardens or community renewable energy systems to be included in calcs for EA-C Renewable Energy Production?
If project owns/leases the system for 10 years and it is located in same utility service area.
EA-Cs eligible for exemplary performance?
EA-C Optimize Energy Performance
EA-C Renewable Energy Production
Calculations for EA-C Renewable Energy Production are based on which factor?
Building’s annual energy cost.
Eligible energy sources for EA-C Renewable Energy Production?
Photovoltaic Solar Thermal Wind Biofuel (Sometimes) Low-Impact Hydroelectricity Wave and Tidal Energy Geothermal Energy (Sometimes)
PV panels at health project
2,000,000 kWh of annual electricity @ $.075/kWh
50,000 Therms of annual gas @ $.75/therm
150 kW PV array will generate 200,000 kWh of electricity/year.
How many points would team earn for EA-C Renewable Energy Production?
2 points - 1 point = 1-4%, 2 point = 5-9%, 3 point = 10%
Annual Energy Cost = (2mil kWh x $.075/kWh) + (50k therms x $.75/therm) = $187.5K
Cost of Renewable Energy = (200K kWh x $.075/kWh) = $15K
% Renewable Energy Cost = (15k/187.5k) = 8%
Residential project.
Estimated Energy Consumption = $125K/year
What is $ equivalent of renewable energy required for exemplary performance of EA-C Renewable Energy Production?
$18,750
Exemplary performance = 15% of total annual energy cost
150K x .15% = 18.5K
RECs can be used to mitigate the effects of which scope emissions?
Scope 2 Emissions, Electricity Use
Owner interested in making power purchase agreement with 3rd party for photovoltaic array canopies on project’s parking lot.
Which circumstances can points can be claimed under EA-C Renewable Energy Production
Agreement must last for 10 years and owner gets to retain environmental benefits from renewable energy.
Office Bldg
Electricity Use Scope 2 = 6075.8 mtCO2e/yr
No gas use
What is minimum amount of annual carbon offsets they should purchase?
3037.9 mtCO2e/yr
Acceptable sampling strategy when executing functional testing for commissioning process (Cx)?
Sample 10 units or 10% of units.
Which systems must be commissioned for EA-P Fundamental Commissioning and Verification?
MEP
Renewable Energy Systems
Requirements for BE under EA-P Fundamental Commissioning Verification?
None. Covered in OPR and BOD
Yes for EA-C Enhanced Commissioning Option 2
What is power utilization effectiveness?
Measure of data center efficiency.
Power needed to operate and cool data center vs. power drawn by IT equipment.
Project phase the commissioning authority must be engaged in to perform EA-P Fundamental Commissioning Verification?
Latest CxA must be engaged is by the end of the design development phase.
Documents the CxA submit to owner prior to building occupancy EA-C Enhanced Commissioning?
Up to date O&M manuals Operator training Functional performance test reports Up to Date issues log Updated CxA plan that outlines plans for 10-month operational review.