Eddington Flashcards

1
Q

On Eddington you discussed value engineering opportunities with the brick framing. Can you explain?

A

“Elements of the design included rotated brickwork and projectect brickwork for architectural interest. This increased as a proportion across the building as the design developed.

Due to the additional labour required compared to a traditional brick bond, the cost saw an increase from £145m2 to circa £250m2. Ultimately design reduced amount of brick framing by 1/3

Reduced by 150m2 - totalling saving of circa £15k

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

On Eddington you discuss the measurement and costing of the frame. How did you go about this?

A

”- Quantified in line with NRM.

  • Columns as a linear m

Build up of the GF slab included excavation, earthwork support, compacting, hardcore, blinding, DPM, insulation, concrete, reinformcened and powerfloat finish - SLAB NOT PART OF FRAME

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

On Eddington how did you cost the concrete and reinforcement?

A

”- Costed concrete on a m3 basis at £175 / m3 at the time (Aug 21)
- Costed reinforcement on a T basis at £1,500 per tonne
- Reinformcenet levels and thicknesses of concrete advised by engineer “

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

On Eddington you used CFA. Why? What other type of piling are there?

A

“Works were being done in an area with other buildings close to residential units. Determined CFA would be quieter and prevent vibrations disturbing new foundations of local buildings

’- Other type of displacement piling would be bored
- Also driven piling which can be vibrated in to the ground “

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How did you VE the piling?

A

”- I reviewed the types of pile tests. I was advised by the structural engineer that pile tests may reduce the diameter of the concrete pile required
- Compared no pile testing (750 diam), working pile testing and preliminary pile testing
- Preliminary pile testing enabled the concrete diameter to be reduced and saved 163m3 of concrete
- OVerall saving of £300k as saved time and concrete and reinforcement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly