ECCS Flashcards

1
Q

What is the ECCS Acceptance Criteria per 10CFR50.46?

A
  • C - Maintain the core in a coolable geometry
  • L - Maintain Long term decay heat removal
  • O - Limit cladding oxidation to < 17% of the total cladding thickness (Zirc-hydriding concern)
  • T - Maintain peak cladding temperature < 2200F (Above 2200F, the Zirc-Water reaction becomes exothermic)
  • H - Limit H2 production to 1% of the total H2 that could be generated by the Zirc-Water reaction if all of the cladding reacted

CLOTH

Coolable
Long Term Cooling
Oxidation
Temperature, Max
Hydrogen generation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Discuss the Post Accident Sources of Hydrogen.

A
  • Zirc – RCS Water reaction - Requires core uncovery and cladding temperature >2200F
  • Corrosion and decomposition of metals inside Containment - decomposition of Zinc & Al due to High Temp
  • Radiolysis of water - Decomposition of water due in the presence of a gamma flux -Slow but most significant source
  • Hydrogen that was entrained in the RCS due to normal Hydrogen overpressure of VCT
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

List the SIAS actuation setpoints.

A

a) PZR Pressure: {1600 psia} [1736 psia]
b) CTMT Pressure: {5 psig} [3.5 psig]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Discuss the Refueling Water Tank (RWT).

A

{Aluminum} [Stainless steel]
* Volume: {525,000 gallons} [554,000 gallons]
* {Unit 1 Injects Sodium Hydroxide (NaOH) in outlet piping when CSAS is generated. which is corrosive to aluminum. On Unit 1 the Containment Spray Pump Recirc valves are maintained in a normally locked closed position to prevent introduction of sodium hydroxide (NaOH) into the aluminum RWT. Also, the NaOH flow path to the suction of the CS pump is isolated prior to opening the CS pump’s minimum recirculation line valves to support pump surveillance testing }
* Vented to Atmosphere

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Discuss the RWT Volume Design Bases.

A

a) Acceptable ECCS water volume to remove decay heat, CTMT sump recirc & maintain Rx subcritical.
b) Volume to supply the HPSI, LPSI, & CS pumps in injection mode for 20 minutes, {305,600} [330,000] After ~ 20 minutes, RAS actuates and 1 HPSI on sump can remove Decay Heat
c) The RWT is sized to contain sufficient water to fill the refueling water canal, transfer tube, and the refueling cavity to 24 feet greater than Rx vessel flange
d) Since the refueling water tank is not provided with missile shielding, the safety injection tanks have been credited as a backup water source for RCS makeup during safe shutdown.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Discuss RWT Level Transmitters.

A
  • 4 Transmitters
  • Alarms & Actuations:
    a) Tank Overflow @ ~ 38’ 3” (overflow to a local catch basin and eventually enter plant storm drains
    b) Hi-Hi level alarm @ 37’ 9”:
  • {Closes V3459 – RWT return header isolation valve. Normally locked closed anyway}
  • [Closes LCV-07-12- RWT return header isolation valve. Normally closed]
  • Interlocks prevent overfilling the RWT during Rx Cavity pump down using the by LPSI pump
    c) Hi level alarm @ 37’ 6” (~ 6” from spillover piping)
    d) Lo level alarm @ 33’
    e) 2 out of 4 detectors {≤ 4 feet} [6 feet]
  • Shuts RWT outlet isolation valves (MV-07-1A & B); and
  • Opens CTMT Sump suction valves (MV-07-2A & B)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Discuss RWT Tech Spec Requirements.

A

RWT boron concentration
≥ 1900 ppm and ≤ 2200 ppm

RWT borated water temperature
≥ 55°F and ≤ 100°F

Water volume is
≥ 477,360 gallons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Discuss the HPSI Pumps.

A
  • The HPSI pumps function to inject borated water into the reactor coolant system if a break occurs in the reactor coolant pressure boundary
  • Used to fill the SITs when RCS pressure is > 1500 psia and plant is not on solid plant pressure control
  • Powered from 4160V A3/B3
  • Auto Start on a SIAS signal
  • Sequence on 6 second load block following LOOP
  • Design Flow 345 gpm (includes recirc flow)
  • Recirc Lines – combined with LPSI pumps (~ 30 gpm) (Discussed below)
  • Run Out Flow ~ 650 gpm {640} [685] gpm
  • Shutoff Head 1250 psig
  • {The CTMT Spray Pumps can be used to supply additional NPSH to the HPSI Pumps from just downstream of SDC HXs via motor operated valves V3662 & V 3663, ensuring NPSH post RAS}
  • Seal water is self-supplied from the pump discharge
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Discuss HPSI Pump Design Basis.

A
  • For small break LOCA’s: With a higher RCS pressure, the HPSI pumps will ensure that the injected flow is sufficient to meet the ECCS acceptance criteria. Since sump recirc is unlikely due to the break size, the HPSI pumps continue injecting into the RCS to provide makeup for spillage out the break while a normal cooldown is implemented.
  • For a Large break LOCA: The HPSI pumps are sized such that one pump will deliver saturated water at a flow rate sufficient to maintain the core flooded, matching decay heat boil-off at the time the safety injection system switches to the recirculation mode not less than 20 minutes after the LOCA.
  • For Recirc Phase: The HPSI pumps are also used during recirculation to maintain water level over the core following the LOCA. For long term core cooling, the HPSI pumps are manually realigned for simultaneous hot and cold leg injection. This ensures flushing and ultimate subcooling of the core coolant independent of break location.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Discuss HPSI Minimum Flow Recirc Lines.

A

Unit 1:
* Each ECCS pump recirc line connects to a shared LPSI & HPSI pump min flow RWT return line.
* Recirc flow returns through two in-series MOV’s (MV-3659 & 3660 - ‘A’ Safeguards Room)
* Valves are normally open with power disabled via control room key switches (shown below)
* Procedurally, power is restored to the valves via the key switch prior to RAS
* Once power is restored, the valves auto close signal on an RAS signal.
* The purpose of the closure is to prevent the highly radioactive water most like present during a LOCA from recircing back to the RWT, creating a rad concern and a potential unmonitored release path
* Because of the common line / valve arrangement, single failure concerns are present. “OFF/ON” key switch (56 & 57) operated power lockout switches are located on RTGB 106. They are used to remove power to the valves making the valves passive components such that a single active failure can NOT disable both trains and prevent premature isolation

Unit 2:
* Two recirc lines exist with two isolation valves on each line. One MOV & One SOV. No single failure concern exists]
* A train (V-3659 & V-3495)
* B Train (V3660 & V-3496)
* Automatically close on a RAS signal. Same closing basis as Unit 1
* The SOV’s (V-3495 & 3496) fail closed on a loss of power
* The SOV’s can be operated from RTGB 206 or locally using Close / Locked Open key switches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Discuss HPSI Injection Header / Throttle Valves (8) (7’s - A Train; 6’s - B Train).

A
  • 8 valves total. 4 valves on each train. Supplies all 4 Cold legs
  • A Hdr – {Aux Hdr} [A Hdr], A Hdr relief at 2485 psig and 132 gpm capacity for alternate CHG thru A Hdr
  • B Hdr – {HP Hdr} [B Hdr], B Hdr relief at 1750 [1585] psig at 5 gpm capacity
  • Normally Closed - Open on SIAS
  • Controlled from RTGB switch (CLOSE / AUTO / OPEN) or by Local PBs
  • MOV’s can be throttled closed to control HPSI flowrate, (once throttling criteria is met)
  • Powered from associated MCC A5/B5 & A6/B6
  • On a LOOP following a SIAS, if the valves were throttled, they will fully re-open once power is restored
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Discuss HPSI Throttling Criteria.

A
  • 1 SG available for heat removal with NR Level being maintained or restored to between 60-70%
  • RCS subcooling greater than or equal to 20F subcooling
  • PZR Level > 30% and not lowering
  • RVLMS Sensors 4-8 are covered OR no abnormal differences (> 20F) between Th and Rep CET
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Discuss Hot Leg Injection.

A
  • Used to flush boron precipitation from the top of the core and prevent flow blockages
  • Large LOCA in Cold Leg could result in bulk boiling in core)
  • Start 4-6 hours following LOCA if not on SDC
  • Time Basis:
    a) 4 Hrs – Sufficient minimum time for decay heat removal to try and prevent the hot leg injection from flashing to steam which could steam void the core
    b) 6 Hrs – Maximum time limit ensures hot leg injection is effective. Start the hot leg injection before the flow blockage is too severe and complete blockage is present.
  • {Unit 1 was not originally designed for hot leg injection. Three potential flowpaths were later created to fufill this function. The 3 methods will be discussed in detail later}
  • [Unit 2 was designed with dedicated Hot and Cold leg injection lines. System design provides simultaneous flow]
  • On either Unit, simultaneous hot and cold leg injection is initiated 4-6 hours after a LOCA as long as any ONE of the following conditions exist:
    a) RCS subcooling is less than minimum subcooling based on REP CET temperature.
    b) PZR level is less than 30%.
    c) RVLMS indicates hot leg nozzles are not full; sensors 4 through 8 are NOT covered, or the difference between THOT and REP CET temperature is greater than 20ºF
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Discuss where Hot Leg injection flow is coming from.

A

Unit 1:
* Primary : A or B LPSI Pump via warmup line to opposite train Th suction line
Otherwise flow would short cycle back to the running LPSI pump suction
HPSI pumps provide cold leg injection
* 1st Alternate: 1A HPSI Pump via the Charging System through both the regenerative heat exchanger (RHX) and the RHX bypass line to the pressurizer auxiliary spray line.
1B HPSI pump provides cold leg injection
* 2nd Alternate: CTMT Spray Pump: provides hot leg injection via A or B hot leg supply headers
HPSI pumps provide cold leg injection

Unit 2:
* [Unit 2 was designed with dedicated Hot and Cold leg injection lines. System design provides simultaneous flow]
* A or B HPSI pump provided simultaneous Hot leg and Cold Leg injection from HPSI pumps via a split 50/50, at least 220 gpm to each (orifices balance flow)
* The other HPSI pump provides cold leg injection only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Discuss LPSI Pumps.

A
  • Primary function is to injecting large quantities of borated water into the RCS during an emergency involving a large pipe rupture. Sufficient flow is delivered under these conditions to satisfy ECCS acceptance criteria
  • The second function of the LPSI pumps is to provide shutdown cooling flow through the reactor core and shutdown cooling heat exchangers
  • Powered from 4160V A3/B3
  • Sequence on 3 second load block following LOOP. Will restart only if previously running from a SIAS
  • Design Flow: {3000 gpm} [3100 gpm] (includes recirc flow)
  • Run out Flow: {4500 gpm} [4600 gpm]
  • Recirc flow:{40 gpm} [100 gpm]
  • Shutoff Head: 185 psig
  • Auto start on SIAS
  • Auto stops on RAS - Designed to prevent long term dead head operation of the LPSI pumps during small break LOCA’s
  • {Seal coolers on Unit 1 LPSI pumps supplied from CCW}
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Discuss “Some LPSI Procedure Stuff:.

A
  • {LPSI pump flow < 1200 gpm (SDC Mode) or < 1000 gpm (SI Mode) can cause pump degradation}
  • {Operating a LPSI pump for > 20 min at flows < 40 gpm or 2 hours at flows < 800 gpm can cause pump degradation}
  • [LPSI pump flow < 1000 gpm can cause pump degradation]
  • [Operating a LPSI pump for > 1 hour at < 100 gpm can cause pump degradation]
17
Q

Discuss LPSI Injection Header Valves (4) – (5s).

A
  • Relief valve[s] set at 535 psig; 5 [45] gpm capacity, normally closed, Open on SIAS
  • Normally Closed - Open on SIAS
  • Controlled from RTGB switch (CLOSE / AUTO / OPEN) or by Local PBs
  • MOV’s can be throttled closed to control HPSI flowrate, (once throttling criteria is met)
  • Powered from associated MCC A5/B5 & A6/B6
  • On a LOOP following a SIAS, if the valves were throttled, they will fully re-open once power is restored
18
Q

Discuss LPSI Discharge Flowpath.

A
  • Unit 1 pumps each discharge through normally open MOV’s (V3206 & 3207)
  • Unit 1 discharges combine into a common discharge header and pass through AOV (FCV-3306)
  • FCV-3306 has a MOV Bypass Valve (MV-03-2)
  • MV-03-2 is maintained open in the safety injection mode due to single failure criteria concerns for FCV-3306
  • Unit 2 has individual discharge headers with a manual valve and MOV for each pump (FCV-3306 & 3301)
  • These valves are locked open with a key switch when aligned for safety injection
  • Can be used to throttle flow while on SDC.
  • 2A LPSI pump supplies 2A1 & 2A2 loops; 2B supplies 2B1 & 2B2 loops
19
Q

Discuss LPSI Termination Criteria.

A

RCS Pressure > 200 psia and controlled

20
Q

Discuss Charging Pumps as they relate to ECCS.

A
  • The charging pumps are credited as supporting the Emergency Core Cooling System (ECCS) in delivering high pressure flow during a Small Break Loss of Coolant Accident (SBLOCA).
  • Powered from vital 480 V load centers (A2, B2, AB)
  • The charging pumps may be susceptible to gas binding due to gas desorption and accumulation in the charging pump suction piping under certain circumstances following ECCS actuation. [Nuclear Grade Air Traps (NGAT) have been installed to monitor, collect, and vent any gas accumulation.]
21
Q

Discuss Safety Injection Tank Design Basis.

A
  • Flood core with borated water following a depressurization of RCS as a result of a LOCA
  • The tanks contain borated water at 1900-2200 ppm, which is the minimum required boron concentration assumed in the large break LOCA accident analyses
  • SITs have been credited as a backup water source for RCS makeup during safe shutdown
  • During normal operation, the SITs are isolated from the RCS by check valves
  • SITs can also be isolated by motor operated isolation valves
  • During normal operation all four MOVs are maintained OPEN and DE-ENERGIZED to make the SITs a passive system (NO single failure concerns).
  • Normal operating level is maintained between high and low level alarms.
  • Normal operating pressure is maintained between high and low pressure alarms.
  • Pressure is maintained {240 to 260 psig} [540 to 570 psig]
  • Method for filling SITs is based on RCS pressure.
  • High/Low level & pressure alarms – Prior to T/S being reached. Action needed
22
Q

Discuss Safety Injection Tank Tech Spec Requirements.

A

Verify each SIT isolation valve is fully open.
Verify borated water volume in each SIT is {≥ 1090 cubic feet and ≤ 1170 cubic feet}
[≥ 1420 cubic feet and ≤ 1556 cubic feet]

Verify nitrogen pressure in each SIT is
{≥ 230 psig and ≤ 280 psig}
[≥ 500 psig and ≤ 650 psig]

Verify boron concentration in each SIT is
≥ 1900 ppm and ≤ 2200 ppm.

23
Q

Discuss SIT Nitrogen valves.

A

Vents
Unit 1
One AOV,
fail closed on loss of air or power

Unit 2
Two SOV’s
energized to open, fail closed on loss of power

Overpressure protection
Unit 1
1” relief valve on each SIT relieves to containment atmosphere
280 psig

Unit 2
1” relief valve on each SIT relieves to containment atmosphere
669 psig

24
Q

Discuss SIT Outlet Valves.

A
  • Open with power removed > 1750 psia in Modes 1 – 3 [Modes 1- 3 with conditions]
  • FSAR Long Term Cooling Plan requires outlet isolation valves be closed 1 to 3 hours following an event.
    a) Prevents injecting a large quantity of nitrogen (non-condensable) gas into the RCS.
    b) Prevents nitrogen blanketing of S/G tubes & preserves S/G for two-phase cooling.
  • Alarm when not fully open. Verified open every 12 hours. With valves de-energized, only way to verify the valve open is absence of annunciator

Unit 1
Control Switch:
“PIC BYPASS CLOSE / CLOSE / OPEN / LOCAL”
Can be operated locally with OPEN / CLOSE pushbuttons when the RTGB switch is in the LOCAL position
* OPEN: Valve will open. Normal Position
* LOCAL: Operate locally with CLOSE/OPEN PBs (doesn’t override auto)
* CLOSE: Valves closes if PZR pressure < 350 psia (Provided no SIAS exists)

  • PIC BYPASS CLOSE: Bypasses PZR pressure interlock to close valve (Provided no SIAS exists)

Auto open signal:
SIAS
&
RCS pressure > 350 psia based on PIC 1103-1104
2 Outlet Valves per transmitter

Open signal block:
On Unit-1, the pressure signal can be blocked by placing control switch to PIC Bypass,
SIAS can NOT be blocked

Power Supply:
MCC A5/B5

Unit 2
Control Switch:
CLOSE / LOCKED OPEN keyswitch on RTGB-206
Another 3 position local keyswitch for each valve is located at the Transfer Panels:
CLOSE / LOCKED REMOTE / OPEN
This local keyswitch must be in its LOCKED REMOTE position for the Control Room keyswitch to operate.
* Locked Open: Will open valve (provided remote operation enabled)
* Local switch in Open: Will open valve
* Close: valve closes if PZR pressure is < 276 psia (Provided no SIAS exists and provided remote operation enabled)

Auto open signal:
SIAS
&
RCS pressure > 500 psia based on PIC 1103-1106.
A separate transmitter for each valve

Open signal block:
No block available

Power Supply:
MCC A6/B6

25
Q

Discuss SIT Fill/Drain Valves.

A
  • Automatic isolation on SIAS
  • Each tank has Nitrogen supply valve and air operated relief valve 250 [669] psig
  • Fill valves used to port check valve leakage from RCS to SITs
  • Filled by HPSI or LPSI via fill AOV & fill/drain AOV (fails closed)
  • Prcs > 1500 psia filled with HPSI (when not on solid pressure control)
  • Prcs < 1500 psia filled with LPSI (SIT pressure must be < 185 psig and SDC recirc secured)
  • Can be drained to RWT or RDT
26
Q

Discuss Plant Cooldown in relation to ECCS.

A
  • Can block auto initiation of SIAS at Prcs < 1725 [1836] psia
  • Must manually actuate SIAS if conditions warrant
  • 1 HPSI pump may remain operable for use as a boron injection flowpath

Unit 1
* Close SIT Isolation Valve breakers when Trcs < 500F and Prcs < 1500 psia
* Close SIT Outlet Valve when Prcs < 325 psia
* Disable 1 HPSI pump prior to Trcs 270F (disch valve & breaker)
* Disable the second HPSI between 250F and 236F (switch in Stop and disch valve)
Not required to be disabled if any of the following:
Pzr Manway removed.
Rx Head removed.
Used for boration flow path

Unit 2
* Depressurize SITs to 235-240 psig when Prcs is 675-1750 psia
* Close SIT Outlet Valve when Trcs < 325F and Prcs < 276 psia
* One HPSI pump is disabled prior to entering Mode 5 (racking out breaker)
* After < 200ºF second HPSI pump is disabled (switch in STOP or pump racked out).
Not required to be disabled if any of the following:
Pzr Manway removed.
Rx Head removed.
Used for boration flow path

27
Q

Discuss HPSI Normal Ops.

A
  • Both trains of the HPSI System are in standby, lined up for emergency operation, whenever the plant is in mode 1, 2, or 3 above 1750 psia.
  • Pump suction & discharge valves are locked open with all 8 HPSI header isolation valves closed.
  • Can be used for filling SITs > 1500 psia or recirculating SI headers.
  • RWT outlets are open, CNTMT sump valves are closed.
  • Can be aligned for use as part of boration flow path.
  • CCW cooling to bearings and seal coolers on both Unit 1 & 2.

Both Units
* For pump switch position aspect of determining pump operability, the following applies:
* If automatic start capability is required for current plant mode, pump control switch shall remain in AUTO or START at all times when pump is considered operable.
* If automatic start capability is NOT required for current plant mode, pump control switch may be in any position. Power must be available to motor through a racked in or closed breaker.

Unit 1
* Operating a HPSI pump continuously at flows less than 114 gpm can cause pump damage.

Unit 2
* HPSI pump required minimum flow requirements]
* Short term (2 hours or less in 24 hours) - greater than 70 gpm.
* Continuous minimum flow (greater than 2 hours) - greater than114 gpm.

28
Q

Discuss LPSI Normal Ops.

A
  • Normally aligned for Safety Injection
  • Used for SDC when shutdown
  • Can be used for filling SITs if SIT pressure is below shutoff head.
  • Can transfer RWT water to HUTs via the RDT
  • Minimum flow requirements
  • Pumps are CCW cooled on Unit 1 only
    Unit 1
    LPSI pump flow limits:
  • Operating a LPSI pump continuously at flows less than 1200 gpm, as indicated on FIC-3306, SDC RETURN FLOW, or 1000 gpm, as determined by sum of FI-3312, LPSI LOOP 1A2 FLOW, FI-3322, LPSI LOOP 1A1 FLOW, FI-3332, LPSI LOOP 1B1 FLOW, and FI-3342, LPSI LOOP 1B2 FLOW, can cause pump degradation.
  • Operating a LPSI pump for greater than 20 minutes at flows less than 40 gpm or 2 hours at flows less than 800 gpm can cause pump degradation.
  • The maximum flow that can pass through 1A and 1B LPSI pump minimum flow recirculation lines is between 90 and 100 gpm each.
  • LPSI pump runout flow as indicated on FIC-3306, SDC RETURN FLOW, is 4117 gpm. If a LPSI pump is operated at indicated flows greater than 4117 gpm, pump cavitation may occur, which could result in pump damage.
    Unit 2
    LPSI pump flows limits:
  • Operating a LPSI pump continuously at flows less than 1000 gpm can cause pump degradation.
  • Operating a LPSI pump for greater than 1 hour at flows less than 100 gpm can cause pump degradation.
  • LPSI pump runout flow is 4600 gpm. If a LPSI pump is operated at flows greater than 4600 gpm, pump cavitation could occur which could result in pump damage.
  • The maximum flow that can pass through the 2A and 2B LPSI pump minimum flow recirculation lines is between 115 and 125 gpm.
29
Q

Discuss SIT Normal Ops.

A

Plant start up
* Verify SIT outlet valves open automatically.
* Unit 1, when pressure exceeds 350 psia
* Unit 2, prior to pressure exceeding 515 psia
Plant shut down
* SIAS is blocked at 1725 [1836] PSIA.
* Unit 1 SITs isolated when RCS <325 psia.
* Unit 2 SITs depressurized to 235-240 psig when RCS pressure is <1750 psia, >675 psia.
* Unit 2 SITs are isolated when RCS < 276 psia and < 325ºF.
* Required to be operable in Modes 1 - 3 with RCS pressure greater than or equal to 1750 psia [Modes 1 - 3 with conditions].
* Each SIT is isolated from the RCS by two check valves in series.
* An MOV, located between the two check valves, is normally open and de-energized.
* Should RCS pressure drop below the pressure of the SIT, the contents of the SIT will discharge into the RCS.
Precautions
* During high pressure safety injection (HPSI) pump operation, either to fill SITs or to recirculate the safety injection (SI) headers, only one HPSI header isolation valve shall be open at any given time to prevent over pressurizing the RWT return header.
* SITs shall NOT be filled when RCS is on solid system pressure control.
* Notify personnel in containment before venting SITs to expect a loud noise.
* When pressurizing SITs nitrogen Dewar should be used for initial pressurization and bulk make-up. Nitrogen tube trailer or nitrogen bottles should be used to adjust tank pressure once bulk make-up / initial pressurization is complete.
* During plant cooldown, RCS pressure must be maintained greater than SIT pressure until SITs are isolated, to prevent SIT discharge to RCS.
* During valve alignment surveillance evolutions with RCS pressure less than 300 psia, SIT isolation valves must be positioned in the closed position to prevent inadvertent dumping of contents.

30
Q

Discuss RAS Actuation.

A
  • CNMT Sump isolation valves (MV-07-2A & MV-07-2B) open in 30 seconds
  • RWT outlet valves (MV-07-1A & MV-07-1B) close in 90 seconds
  • Alarm if either set of valves fail to go to correct positions after a time delay
  • {Mini-flow Recirc lockout keyswitch placed to ON before RAS and to OFF after RAS}
  • {HPSI suctions aligned to CS downstream of SDC HXs prior to RAS (for NPSH)}
  • LPSI stops, Small break LOCA; LPSI will be deadheaded with Min flow isol, S/D to prevent damage.
31
Q

Discuss SIAS Actuation.

A
  • Opens Cold Leg injection valves, 8 HPSI, 4 LPSI
  • Starts HPSI & LPSI pumps
  • Open signal to SIT outlet valves and SDCHX outlet valves
  • Closes SI Loop Check Valve Leakage Valves
  • Closes SIT Fill / Drain Valves [also 4 solenoid Fill/Drain valves]
  • [Closes Hot Leg 2A / 2B Check Valve Leakage Valves]
  • [Closes SI to RWT / VCT Valves]
  • Starts ECCS Emergency Exhaust Fans, HVE-9A & HVE-9B, Aligns ECCS Dampers
32
Q

Discuss SIAS / CIAS Reset Criteria.

A
  • HPSI Throttling Criteria Met, SIAS & CIAS has been verified, TSC Concurrence (If operational).
33
Q

Discuss CCW for ECCS Pumps Seal Cooling – required for Operability.

A

{Unit 1 - HPSI, LPSI, & CS pumps}
[Unit 2 – HPSI & CS pumps]

34
Q

Discuss FSAR as it applies to ECCS.

A
  • Cooldown at 75 degrees per hour is assumed to begin within 1 hour of a LOCA.
  • Cool down of the pressurizer is assumed to begin within 1.5 to 2 hours of a LOCA.
  • For small break LOCAs that will use SDC for long term cooling this allows a cooldown and depressurization to reach SDC entry criteria to occur.
  • SIT venting or isolation is assumed to occur in 2-3 hours after a LOCA to prevent excessive nitrogen injection into the RCS which could inhibit heat transfer through the S/Gs.
  • Commence simultaneous hot/cold leg injection within 4 - 6 hours of LOCA. This prevents boron precipitation
35
Q

Discuss ECCS response to LOCA.

A
  • LOCA size determines RCS pressure drop
  • SIAS at 1600 psia [1736 psia]
  • When RCS pressure drops below HPSI Pump shutoff head, the pumps begin injecting into the RCS (~1250 psia)
  • When RCS pressure drops below SIT pressure, their contents are injected into the RCS (~250 [550] psi)
  • If pressure drops below LPSI pump shutoff head, the LPSI pumps begin to inject (~185 psi)
36
Q

Discuss ECCS response to SIAS with LOOP.

A
  • Closure of the EDG output breaker starts the load sequencing timers
    LPSI
  • Pumps start after a 3 second time delay.
  • Header isolation valves stroke open as soon as power is restored.
    HPSI
  • Pumps start after 6 second time delay.
  • Header isolation valves stroke open as soon as power is restored.
    SIT’s
  • If SIT outlets were closed with power available, they work the same as they do for SIAS as soon as power is restored.
37
Q

Discuss ECCS response to SIAS with delayed LOOP.

A

EDG running with output breaker open from SIAS
Delayed LOOP
* Loads strip.
* EDG breaker closes.
* SIAS loads resequence block load onto EDG
* SI Valves 0 sec (not stripped)
* LPSI pumps 3 sec
* HPSI pumps 6 sec

38
Q

Discuss ECCS response to LOOP with Delayed SIAS.

A
  • EDG breaker opens
  • Loads strip
  • EDG breaker recloses
  • SIAS loads sequence onto EDG
  • SI Valves 0 sec (not stripped)
  • LPSI pumps 3 sec
  • HPSI pumps 6 sec