Earned Value Mgmt Formulas Flashcards
What the project budget is
Budget At Completion (BAC)
What the project should be worth
Planned Value (PV)
What the project is worth
* = %Complete x BAC*
Earned Value (EV)
What the project has spent so far
Actual Cost (AC)
The difference between EV and the AC.
= EV - AC
Cost Variance (CV)
The difference between EV and PV
= EV - PV
Schedule Variance (SV)
Shows overall cost efficiency on the project.
Greater than 1 = under budget
Less than 1 = over budget
= EV/AC
Cost Performance Index (CPI)
Shows overall schedule adherence.
> than 1: ahead of schedule
< than 1: behind schedule
= EV/PV
Schedule Performance Index (SPI)
What forecasts final project costs based on current performance?
Estimate at Completion (EAC)
(standard formula)
BAC/CPI
What is the projection of being over or under budget based on urgent performance?
Variance at Completion (VAC)
BAC - EAC