Earned value mgmt formulas Flashcards
Cost variance
Ev - ac
Positive :-) Under budget
Negative :-( Over budget
Earned value
Percent complete * bac
Planned value
What proj s/b worth
Budget at completion
What the proj budget is
Schedule variance
EV-PV
Positive means :-) ahead of schedule
Negative means :-( behind schedule
Variance at Completion
Projection of being over or under budget based on current performance
BAC-EAC
Cost Performance Index
EV/AC
Shows overall cost efficiency of proj
>1 means under budget
<1 means over budget
Schedule Performance Index
EV/PV
Shows overall schedule adherence
>1 means ahead of schedule
<1 means behind schedule
Estimate at completion (EAC) - standard formula
Forecasts final proj costs based on current performance
BAC/Cpi
Estimate at Completion - Future work at planned costs formula
AC+BAC-EV
Estimate at Completion (EAC) - CPI and SPI affect remainder of project
AC + [BAC-EV/(CPIxSPI)]
Estimate at Completion - Initial estimates flawed
AC + estimate for remainder of proj
Estimate TO complete
Predicts how much more the remainder of the project will cost
EAC-AC
To complete performance index (TCPI) - Utilizing BAC
Predicts likelihood of achieving BAC
(BAC-EV)/(BAC-AC)
Greater than 1 - harder to complete and meet BAC
Less than 1 - easier to complete and meet BAC
To complete performance index (TCPI) - Utilizing EAC
Predicts likelihood of achieving EAC
(BAC-EV)/(EAC-AC)
Greater than 1 - harder to complete and meet EAC
Less than 1 - easier to complete and meet EAC