Earned Value Management Vocab Flashcards
Planned Value - define
budgeted value of work planned to be done at a given time
Earned Value - define
budgeted value of work completed at a given time
Actual Cost - define
actual cost of work completed
Budget at completion - define
the original cost baseline plus or minus all approved cost changes
Estimate at completion - define
expected total project cost (forecasted based on performance to date)
estimate to completion - define
expected remaining cost (now until project completion)
Variance at completion - define
expected variance over/under budget
Cost variance - formula
EV - AC
Negative is bad, Positive is good. Zero is on budget.
Schedule Variance - formula
EV - PV
Negative is bad, Positive is good, Zero is on schedule
Cost Performance Index - formula
EV/AC
Under 1 is bad, Over 1 is good, Exactly 1 is on budget
Schedule Performance Index - formula
EV/PV
Under 1 is bad, Over 1 is good, Exactly 1 is on schedule
Estimate at Completion - formula
AC + (BAC-EV)
AC plus work remaining, use budget rate (variances atypical)
(BAC/CPI)
Assumes same rate of spending will continue (variances typical)
AC + [(BAC-EV)/(CPI*SPI)]
Assumes current cost and schedule performance will continue
Estimate to Completion - formula
EAC - AC
Expected cost of work remaining
Variance at Completion - formula
BAC - EAC
Negative is bad, Positive is good, Zero is on budget
To Complete Performance Index - formula
(BAC - EV) / (BAC - AC)
CPI needed to complete project within budget
(BAC - EV) / (EAC - AC)
CPI needed to hit EAC - Assumes original budget unachievable