Earned Value Management (EVM) Flashcards
1
Q
Which EVM formula should be used to calculate a forecast?
A
EAC (Estimate at Completion)
2
Q
What is CV?
A
- Cost Variance
- Difference between work done and money spent
- Should be positive for under budget (negative indiciates over budget)
3
Q
What is CPI?
A
- Cost Performance Index
- Rate of how current spending to earning on a project
- Should be 1 or over for projects under budget
CPI of 0.9 = Project is 10% over budget
4
Q
What is SV?
A
- Schedule Variance
- Difference between amount of work we should have completed vs. the amount actually completed
- Should be positive for ahead of schedule
5
Q
What is SPI?
A
- Schedule Performance Index
- Rate of how we are meeting the project schedule
- Should be 1 or over for a project to be ahead of schedule
SPI of 0.7 = Project is 30% behind schedule