What are the 4 common Inputs to the 49 Processes?

A
  1. Enterprise Environmental Factors
  2. Organizational Process Assets
  3. Project Documents
  4. Project Management Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 8 common Tools & Techniques in the 49 Processes?

A
  1. Expert Judgment
  2. Data Gathering
  3. Data Analysis
  4. Data Representation
  5. Decision Making
  6. Interpersonal and Team Skills
  7. Meetings
  8. Project Management Information Systems
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 3 common Outputs of the 49 Processes?

A
  1. Change Requests
  2. Work Performance Data, Information, and Reports
  3. Updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are Enterprise Environmental Factors?

A

Things that can impact the project by influencing the organization, the project, and its outcome:
* Internal - Culture, employee capability, org structure, etc.
* External - Politics, government regulations, financial considerations, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are Organizational Process Assets?

A

Assets such as info, procedures, and knowledge bases that are kept in a central location for the team to update throughout the project:
* Project templates
* Software tools
* Historical info

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are some examples of Project Documents?

A

Any documents related to the project and used throughout the 49 processes that are not part of the PM Plan:
* Change Log
* Issue Log
* Risk Report
* Team Charter
* Project Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Project Management Plan?

A

A large document that defines how the project will be executed, monitored & controlled, and closed.
Includes management plans from all knowledge areas, schedule baseline, project lifecycle description, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Expert Judgment?

A
  • A common Tool in the planning process, this involves hiring an expert to provide specialized knowledge.
  • One of the most accurate inputs!
  • The best experts are the people doing the work on the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are some examples of the Data Gathering tool/technique?

A
  • Brainstorming
  • Focus Groups
  • Checklists
  • Questionnaires/Surveys
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are some examples of the Data Analysis tool/technique?

A
  • Alternative Analysis
  • Root Cause Analysis (RCA)
  • Variance Analysis
  • Trend Analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Data Representation?

A

Includes the various ways data can be shown to stakeholders, including:
* Flowcharts
* Diagrams
* Histograms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are some common examples of the Decision Making tool & technique?

A

*Voting
*Multicriteria Decision Analysis
*Autocratic Decision Making

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are Interpersonal and Team Skills and Meetings?

A

Methods include:
* Active Listening
* Conflict Management
* Facilitation
* Meeting Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a Project Management Information System?

A
  • Automated system a PM uses to optimize the schedule, keep track of documents and deliverables, etc.
  • Includes the org’s computer system, all software/hardware tools, work authorization system, and config management system
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Change Request?

A

Proposal to change a document, deliverable, or baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Work Performance Data?

A
  • A common output of the Executing process group
  • Raw data with no analysis applied to it (not useful by itself)
17
Q

What is Work Performance Information?

A
  • A common output of the Monitoring & Controlling process group
  • Uses the raw Work Performance Data to determine performance compared to plan
  • Comes in parts (scope, budget, etc.)
18
Q

What are Work Performance Reports?

A
  • A common output of the Monitoring & Controlling process group
  • Puts all Work Performance Information together into one comprehensive document to provide status to stakeholders
19
Q

What are Updates?

A

A common Output that includes updates to project documents, the PM Plan, etc.