Earned Value Management Flashcards
PV (Planned Value)
Budgeted value of work planned to be done at a given time
EV (Earned Value)
Budgeted value of work completed at a given time
AC (Actual Cost (total))
Actual cost of work completed
BAC (Budget at Completion)
The original cost baseline plus or minus all approved cost changes
EAC (Estimate at Completion)
Expected total project cost (forecasted based on performance to date)
ETC (Estimate to Completion)
Expected remaining cost (now until project completion)
VAC (Variance at Completion)
Expected variance over/under budget
CV (Cost Variance)
EV - AC
Negative is bad, Positive is good, Zero is on budget
SV (Schedule Variance)
EV - PV
Negative is bad, Positive is good, Zero is on schedule
CPI (Cost Performance Index)
EV/AC
Under 1 is bad, Over 1 is good, Exactly 1 is on budget
SPI (Schedule Performance Index)
EV/PV
Under 1 is bad, Over 1 is good, Exactly 1 is on schedule
EAC (Estimate at Completion)
.
EAC (Estimate at Completion)
.
EAC (Estimate at Completion)
.