Earned Value Management Flashcards
PV
Planned Value (Budgeted Cost of Work Scheduled)
EV
Earned Value (Budgeted Cost of Work Performed)
AC
Actual Cost (Actual Cost of Work Performed)
SV
Schedule Variance = Earned Value - Planned Value
CV
Cost Variance = Earned Value - Actual Cost
SPI
Schedule Performance Index = EV/PV
CPI
Cost Performance Index = EV/AC
EAC
Estimate At Completion = AC + (BAC - EV)
EAC using the current Cost Performance Index
EAC = BAC / CPI
EAC using the current CPI and SPI
EAC = AC + (BAC - EV) / (CPI x SPI)
What is the TCPI
To-Complete Performance Index
Formula to calculate TCPI in order to complete on plan
TCPI = (BAC - EV) / (BAC - AC)
VAC
Variance At Completion = BAC - EAC
Formula to calculate TCPI in order to complete the current EAC
TCPI = (BAC - EV) / (EAC - AC)
ETC
Estimate to Completion:
ETC = EAC - AC or
ETC = Re-estimate