Earned Value Management Flashcards

1
Q

PV

A

Planned Value (Budgeted Cost of Work Scheduled)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV

A

Earned Value (Budgeted Cost of Work Performed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC

A

Actual Cost (Actual Cost of Work Performed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

SV

A

Schedule Variance = Earned Value - Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A

Cost Variance = Earned Value - Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SPI

A

Schedule Performance Index = EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI

A

Cost Performance Index = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EAC

A

Estimate At Completion = AC + (BAC - EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC using the current Cost Performance Index

A

EAC = BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EAC using the current CPI and SPI

A

EAC = AC + (BAC - EV) / (CPI x SPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the TCPI

A

To-Complete Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Formula to calculate TCPI in order to complete on plan

A

TCPI = (BAC - EV) / (BAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

VAC

A

Variance At Completion = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Formula to calculate TCPI in order to complete the current EAC

A

TCPI = (BAC - EV) / (EAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

ETC

A

Estimate to Completion:
ETC = EAC - AC or
ETC = Re-estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

EAC at the planned rate

A

EAC = AC + BAC - EV

17
Q

EAC when the original plan is no longer valid

A

EAC = AC + Bottom-Up ETC