Earned Value Flashcards
1
Q
BAC (Budget at Completion)
A
Gesamt Budget
2
Q
AC (Actual Cost)
A
Alle bisher ausgegebenen Kosten des Projektes.
3
Q
PV (Planned Value)
A
Geplanter Wert
4
Q
SPI (Schedule Performance Index)
A
EV / PV
4
Q
PC (Percent Complete)
A
EV / BAC x 100
5
Q
SV (Schedule Variance)
A
EV - PV
6
Q
CV (Cost Variance)
A
EV - AC
7
Q
CPI (Cost Performance Index)
A
EV / AC
9
Q
VAC (Variance at Completion)
A
BAC - EAC
10
Q
EAC (Estimate at Completion)
A
BAC / CPI
11
Q
ETC (Estimate to Complete)
A
EAC - AC
12
Q
TCPI (To Complete Performance Index)
A
(BAC - EV) / ETC
13
Q
EV (Earned Value)
A
Fertigstellung (%) x BAC