DSC, SUBSURFACE DISPUTE, DELAY CLAIMS, PAYMENT PROCESSING CLAIMS Flashcards

1
Q

What is the difference between type I and type II DSC?

A

Type I: Different than in contract
Type II: Different than known and usual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Please state the procedure for DSC.

A

Notify owner before disturbing the conditions
Owner investigates
if agrees, adjustment of cost & time
Requires written notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What remedies a contractor can use if no DSC clause in contract?

A

Fraud
Negligent misrepresentation
Withholding material information
Mutual mistake

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can an owner utilize to limit their exposure to differing site conditions?

A

Site investigation clause

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 5 types of delay analysis techniques?

A

Window
Impacted as-planned
Global
But-for
Collapsed as-built

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are some benefits of window technique for delay analysis?

A

Graphical
Court Friendly
Divides project into manageable parts
Self-checking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are some limitations of window technique for delay analysis?

A

Data intensive nature
Can be manipulated by cut-off date
Requires a detailed as-planned schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Final Payment and the release of retainage will be made when:

A

Owner has assurance that all parties have been paid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9