DSC, SUBSURFACE DISPUTE, DELAY CLAIMS, PAYMENT PROCESSING CLAIMS Flashcards
What is the difference between type I and type II DSC?
Type I: Different than in contract
Type II: Different than known and usual
Please state the procedure for DSC.
Notify owner before disturbing the conditions
Owner investigates
if agrees, adjustment of cost & time
Requires written notice
What remedies a contractor can use if no DSC clause in contract?
Fraud
Negligent misrepresentation
Withholding material information
Mutual mistake
What can an owner utilize to limit their exposure to differing site conditions?
Site investigation clause
What are the 5 types of delay analysis techniques?
Window
Impacted as-planned
Global
But-for
Collapsed as-built
What are some benefits of window technique for delay analysis?
Graphical
Court Friendly
Divides project into manageable parts
Self-checking
What are some limitations of window technique for delay analysis?
Data intensive nature
Can be manipulated by cut-off date
Requires a detailed as-planned schedule
Final Payment and the release of retainage will be made when:
Owner has assurance that all parties have been paid