Document Questions Flashcards
What is the HGCRA?
Housing Grants Regeneration Act 1996 (HGRCA)
What is the Construction Act?
Was born following the Egan and Latham reports to prevent adverse and ambiguous terms in construction contracts to :
Introduction intended to ensure payments made promptly, included:
The right to be paid in interim, periodic or stage payments.
The right to be informed of the amount due, or any amounts to be withheld.
The right to suspend performance for non-payment.
The right to adjudication.
Disallowing pay when paid clauses.
What is the Local Democracy, Economic Development and Construction Act 2009?
Due dates Pay-when-certified clause Payment notices Default payment notices Pay less notices Changes to suspension of the works
What is the Scheme for Construction Contracts?
When construction contracts do not comply with the Housing Grants, Construction and Regeneration Act.
What are the options within NEC?
Option A: Priced contract with activity schedule.
Option B: Priced contract with bill of quantities.
Option C: Target contract with activity schedule.
Option D: Target contract with bill of quantities.
Option E: Cost reimbursable contract.
Option F: Management contract.
Option G: Term contract (for the appointment of a consultant based on a priced schedule of tasks).
What are the sections within the JCT?
Articles CPs Section 1 - Definitions Section 2 - Carrying out the Works Section 3 - Control of the Works Section 4 - Payment Section 5 - Changes Section 6 - injury, damage and insurance Section 7 - assignment, third party rights and collateral warranties; Section 8 - termination; Section 9 - settlement of disputes. Schedules
Name some Relevant Events?
- Variations
- Instructions
- Deferment of possession
- Antiquities
- Suspension due to non-payment
- Any impediment, prevention or default by the Employer
- Work, or failure by, statutory undertaker
- Exceptionally adverse weather
- Loss or damage caused by Specified Perils
- Civil commotion / terrorism
- Strike, lock-out
- Exercise of statutory power by UK Government
- Delay in receipt of any necessary permission or approval of any statutory body
- Force majeure
Name some Relevant Matters?
- Variations
- Instructions
Postponement of work
Instructions on Provisional Sums
Opening up for inspections or testing (unless work is defective)
Errors, discrepancies and divergences - Antiquities
- Impediment, prevention or default by the Employer
What is the difference between NEC3 and NEC4?
TBC
What are the payment provisions in the Construction Act?
Claim for Payment
+ 5 days = Payment Notice
+ 17 days (from IV Date) = Payment Date
- 7 days from payment date = Pay Less Notice
How does the NEC deal with prelims?
These are not explicitly mentioned in the NEC but should be included in your price to deliver the works
What are Z clauses?
Z clauses can be used and inserted into NEC contracts to allow the parties to agree additional terms and conditions, in order to cater for specific needs relating to a project and the terms of its delivery
Why did you propose a PCG over a Performance Bond?
Lovell had financially strong parent company who would be capable of completing the work should Lovell default or go insolvent
Saving for my client
Less requirements to prove this like there would be with a conditional Performance Bond
Why did your advise your client to use JCT over other forms of contract and how did you advise this?
In a formal report (section incl in my Procurement Route)
Familiarity Tried and tested Common in the sector Experience with client Contractors understand Risk allocation to the Contractor more
What constitutes a construction contract?
A large section in the Construction Act but in summary it is
The construction, alteration, repair, maintenance, extension or demolition of buildings or structures.
What are the key differences between the NEC / JCT?
Project Manager Works Information (ERs) Compensation Events (time/money) Time Constraints on CE's C.Es are both time and cost No Prov Sums Programme is a contractual document EWNs No Schedule of Rates NEC is a lot more collaborative NEC dispute resolution is different NEC does not reference other clauses like the JCT