CONTRACT SPECIFICS & PERFORMANCE SECURITY Flashcards
What are the outputs you’d expect from an EA/CA?
Issuing instructions. Co-ordinating the review of information prepared by the contractor. Managing change control procedures. Reviewing the progress of the works and preparing reports for the client. Validating or certifying payments. Considering claims. Arranging handover. Certifying practical completion.
What is included in the Contract Particulars?
The contract sum.
The retention percentage.
The interim payment period.
The details of the adjudicator / arbitrator or appointing body.
Third party rights and collateral warranties.
The contract base date.
The completion date (or sectional completion dates).
Details of key personnel.
The date for possession.
What were the changes from 2011 to 2016 JCT contracts?
CDM to PD Payment - Construction Act All risk insurance Performance Bonds or PGC Intro of interim valuation date Must submit a notice of delay
What are fluctuations? And the options?
Fluctuations provisions in construction contracts for inflation
Opt A - Tax and Insurances
Opt B - Opt A + Labour & Materials
Opt C - using specific indices
What is a retention bond?
Retention bonds are typically ‘on demand’ to provide the employer with recourse
equivalent to cash retention.
Typically the employer is only able to call on an amount that would otherwise have
been held by the employer in cash retention.
What is a off site material bond?
Payments made for goods that are held by a contractor off site before they are required for a project
What is a collateral warranty?
Collateral warranties are agreements which are associated with another ‘primary’ contract.
They provide for a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract.
Explain the JCT design and build contract payment alternatives?
Alternative A - Stage Payments
Alternative B - Interim Valuations
What happens if the Employer fails to pay?
Interest chargeable
Grounds for termination by the Contractor
How would you deal with an application for payment for materials off-site?
Would need to be a Listed Item
Vesting certificate – proof that ownership will transfer to the employer on payment
Materials should be clearly labelled as for the site and set apart from other materials
Insurance until material arrives on site.
What are step-in rights in relation to collateral warranties?
Such step-in rights usually materialise on the default or insolvency of the developer and allow the principal stakeholder to step into the shoes of the developer
Standard form of CW?
JCT standard CW but client uses their own
What are Specified Perils?
Disasters: fire, lightning, explosion, storm, flood,
What is the Joint Fire Code?
Provides guidance on fire safety on site – precautions and safe working practices. Examples of content: Emergency procedures Portable fire extinguishers Hot works
What is the process of an advance payment bond?
How its taken out? What must be provided? How to certify and reduce the bond in IVs?
Contractor must provide proof of bond
In place if there is a problem or contractor does not provide proof of what the bond was for