Discharge Of Contracts Chapter 6 Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

4 ways contracts are discharged

A

Performance both parties did as promised

Breach one party failed to perform

Agreement. Both parties after they wish to discharge

Frustrations. Something happens which makes performance of the contract impossible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Entire performance rule

A

Both parties have stuck to their end of the promise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cutter v Powell

A

Died on route to Liverpool from Jamaica. Didn’t forfill his work therefore spouses claim failed for suing his company for wages as he didn’t perform the entire contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Bolton v Mahadeva

A

Bolton agreed to instal central heating. It worked so badly it was needed to put right for a cost. Mahadeva did not have to pay Bolton anything

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Entire contract

A

Contract depends on one party performing something. Paying for building work etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Acceptance of partial performance and case law

A

Acceptance of partial performance (parties agree to conclude contract for lesser price for what they have) £500 for 500 CD. Changes to £400 to 400 CD. New contract is formed

Must be an element of choice to decision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Substantial performance and case law

A

Hoenig v isaacs

Decorator referubished flat. Only needed some touch ups so decorator was deducted cost of touch ups from his payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Prevents performance and case law

A

Planche v Colburn

Author commissioned to write book for £100. Publisher withdrew and author got part payment of £50

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Tenders performance

A

One party requires permission to attempt performance and other party refuses. Only works if permission is required to complete performance. Contract will be deemed as completed as party has tried to perform

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Startup v Macdonald

A

Claimant attempted to deliver oil, defendant refused. Attempt at performance was deemed as adequate they were discharged from contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Severable obligations

A

One party has completed part of their obligation they may claim part payment.

Building contracts / employment contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Time of performance

A

If obligations aren’t fulfilled by time set out by parties or if it effects goods for sale then breach is applicable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Valilas v Januzaj

A

Breach did not go to the root of the contract and the court deemed time was not if the essence so no damages were awarded and no breach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Breach of contract

A

Occurs when one party fails to discharge the contract as agreed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Remedies for breach of contract

A

Innocent party can repudiate (refuse to continue with the contract)

Warranty of the contract is breached damages can be awarded but must continue with the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the fulfilment of ending a contract by agreement

A

Agreement to terminate must be a new contract

17
Q

What is finding consideration

A

Both parties come to a mutual understanding not to sue each other for not completing contract

18
Q

Accord and satisfaction

A

Is party 1 completed part contract party 2 didn’t. Party 2 can propose a promise to party 1 to give them something so party 1 doesn’t sue party 2

19
Q

Frustrations

A

Failure to complete the performance is at fault of neither party therefore neither party can be sued for breach

20
Q

Condor v The Barron knights

A

Drummer had exhaustion’s couldn’t only place 4 nights out of 7 due to doctor advice. Contract deemed frustrated

21
Q

Krell v Henry

A

Henry hires hall to watch coronation of king. King fell ill Henry declined to pay. Frustration was applied

22
Q

Supervening illegality (coming illegal after contract is formed) frustration contract

A

Fibrosa case

English company and polish company made contract. War broke out between England and Germany which took occupation of poland prior to obligations of contract being performed.

23
Q

Metropolitan water board v dick Kerr

A

Parties agreed to buying to build a reservoir contract contained clause which stated may be subject to delays. War broke out contract was deemed frustrated

24
Q

Davis v contractors v fareham urban district council

A

78 houses to be holt for counsel in 8 months for agreed price. Work took longer due to weather and staff shortages. Builders asked for additional payment due to these factors. House of Lords deemed not frustrated contract and damages not applicable

25
Q

Does self induced frustration mean for a frustrated contract?

A

No, as per The Super Servant 2.

Claimant wanted to transport oil. Had choice of two transporters. The one they picked sank the other was in use else where. Claimant tried to sue. Court held as transporter 2 was sent else where self induced frustration didn’t apply as there could have been another transporter available. Defendant could not succeed with self induced frustration

26
Q

Can financial climate be viewed as a supervening event?

A

No, not by itself as per gold group properties ltd v BDW trading ltd

27
Q

Effects of frustration

A

Bring contract to an end automatically

28
Q

What is the common law rule on frustration

A

Any loss suffered lay where it falls. No losses recoverable. As per Appleby v Myers

29
Q

Which act regulated frustration

A

Law reform frustrated contracts act 1943

30
Q

What does Law reform act 1943 dictate about effects of frustrations

A

Money paid before frustrating event is recoverable by the payer, payer does not need to pay any monies due. “Payer rule”

Payer may be allowed to retain or recover all or some of the money paid or owed to him under the contract, if expenses are incurred or the court allows it.

31
Q

Example S 1 Law reform act 1943

A

Gamerco SA v IVM

Guns and roses due to perform. Concert stopped due to safety issues at venue. Claimants who promoted contract bought forward claim to seek damages for amount owed in publicity.
Defendant who spent money preparing concert counter claimed

Court held claimant were entitled to recover money and defendant was able to claim reasonable expenses.