Discharge of Contract Flashcards
What happens when a contract is discharged?
- It is terminated
What is discharge by performance?
- When a contract becomes discharged, as both parties have fulfilled their contractual obligations
What was decided in Cutter v Powell (1795)?
- If a party fails to perform the contract in its entirety, they are entitled to nothing under the contract from the other party
What are the ways in which the harsh rule in Cutter v Powell (1795) can be mitigated? (4)
- Substantial performance
- Severable contracts
- Acceptance of past performance
- Prevention of performance
What is the doctrine of substantial performance?
- If a party has done substantially what was required under contract, the party can recover the amount appropriate to what has been done under the contract
Name three key cases for substantial performance
- Dakin & Co v Lee (1916)
- Hoeing v Isaacs (1982)
- Bolton v Mahadeva (1972)
What happened in Dakin & Co v Lee (1916)?
- Defendants promised to build a house according to spec
- Failed to carry out exactly all specs
- Entitled to recover the contract price as it was bad workmanship/negligence NOT abandonment of the job
- Basically they did a shit job but it still counts
What happened in Hoeing v Isaacs (1952)? What two things were held?
- Contract for decoration
- There were defects that cost £55 to repair
- Held that an employer cannot deprive a contractor of any payment due to defects
- Also held - whether the entire performance of a contract is a condition precedent to payment depends on the constitution of the specific contract
What was held in Bolton v Mahadeva (1972)? Why?
- The claimant’s attempt to enforce the payment (also house decorating with defects) was denied as there was no substantial performance
When is a contract severable?
- When payment becomes due at various stages of performance, rather than in one lump sum when performance is complete
Give an example of a severable contract
- If one hires a childminder for six weeks and pays weekly, the childminder can claim the first week’s pay even if they then refuse to work the following five weeks
What happens under acceptance of part performance?
- Where one of the parties has performed the contract, but not completely, if the other side has shown willingness to accept the part performance the strict rule in Cutter v Powell will usually not apply
When may acceptance of part performance occur?
- When there has been a shortfall in the delivery of goods or where a service is not fully carried out
What is a key case in acceptance of past performance?
- Sumpter v Hedges (1898)
What happened in Sumpter v Hedges (1898)?
- Claimant was unable to finish building work on the defendant’s land (did half)
- The claimant argued that the defendant had accepted part performance as he had completed the work himself
- Held - claim failed as the defendant has no choice but to complete the work himself
What happens under prevention of performance?
- If one party prevents the other party from carrying out his or her obligations because of some act or omission, then the rule in Cutter v Powell cannot are
Under prevention of performance, the party trying to perform may have an action for what?
- Damages
Name two key cases for prevention of performance
- Planche v Colburn (1831)
- Startup v Macdonald (1843)
What happened in Planche v Colburn (1831)?
- Claimant agreed to write book for defendant
- Claimant had completed a great deal when the defendant cancelled
- Defendant refused to pay
- Claimant entitled to damages as defendant had prevented the performance
What happened in Startup v Macdonald (1843)
- Claimant delivered oil late, bit still within designated time frame
- Defendant refused to accept delivery as it was late
- Claimant entitled to damages for non-acceptance