Discharge of contract Flashcards
What case is an example of discharge by performance?
Cutter v Powell (1795)
Cutter v Powell (1795)
Cutter was a crew member on a ship with payment due on completion of a voyage. He died 19 days before the journey ended and his widow was refused the payment as he had not fully performed the contract.
What case is an example of divisible contracts?
Bolton v Mahadeva (1972)
Bolton v Mahadeva (1972)
The claimant had contracted to install central heating and supply a bathroom suite to the defendant. The heating system was defective, and it cost £179 to remedy the defect, It was held that Bolton could not claim the installation cost, as he had failed to perform the contract. However, supply of the bathroom suit was divisible from the overall payment, and that had to be paid for.
What case is an example of one party prevents the other from completing performance?
Planche v Colburn (1831)
Planche v Colburn (1831)
The claimant was asked to write a book by the defendant with payment due on completion. The claimant wrote half the book when the defendant changed his mind and asked him to stop. The claimant was entitled to part payment for partly performing his contract.
What case is an example of acceptance of part performance?
Sumpter v Hedges (1898)
Sumpter v Hedges (1898)
The claimant contracted to build a barn for the defendant but then abandoned the project half-way through. It was held that the defendant did not have to pay for part performance as the defendant did not have a choice but to accept part performance. The defendant only had to pay for materials the claimant had left behind and used by the defendant to complete the building.
What cases are examples of substantial performance?
Bolton v Mahadeva (1972)
Hoenig v Isaacs (1952)
Hoenig v Isaacs (1952)
A contract to decorate and furnish a flat was held to be substantially performed as full performance only lacked repairs to a bookcase and replacement of a wardrobe door. The total contract cost £750 and it was held that a reduction of £55 be made to cover the bookcase and wardrobe door.
What cases are examples of discharge by frustration - Destruction or unavailability of the subject matter ?
Taylor v Caldwell (1863)
Gamerco SA v ICM/Fair Warning (Agency) Ltd (1995)
Taylor v Caldwell (1863)
Caldwell agreed to rent a music hall for a series of concerts over four days from Taylor. After the contract was agreed, but before the concerts had taken place, the music hall was destroyed by fire. It was held that performance of the contract was impossible; therefore, the contract was frustrated, and both parties were released from their obligations under it.
Gamerco SA v ICM/Fair Warning (Agency) Ltd (1995)
A contract was frustrated when a stadium hired for a rock concert became unsafe and it was not possible to find a alternative venue in time.
What cases are examples of discharge by frustration - Death or illness of one of the contracting parties
Condor v Barron Knights (1966)
Atwal v Rochester (2010)
Condor v Barron Knights (1966)
A drummer with the Barron Knights became ill and was advised by his doctor to limit performances to four nights a week. It was held that the contract was frustrated as the ability to work only four nights was incompatible with the nature of work. The claimant’s health was preventing him for performing his contractual duties; thus, any contractual obligations were unenforceable.