Digitize Fox Collection Flashcards
Estimated footprint for preservation quality scanning (4K uncompressed)
7 PB
Estimated data storage footprint for access project (2k compressed)
300 tb
Out of pocket Cost to complete the project in 3 years
870,000
Effort commitment to complete project in 3 years, expressed as marginal increase
25% or $375,000
Out of pocket cost to complete the project in 5 years
$670,000
Effort commitment to complete the project in 5 years
10% or $250,000
Out of pocket cost to complete the project in 12.5 years
$270,000
Effort commitment to complete the project in 12.5 years
5% or $310,000 (probably too high as time goes on–loose correction by not including salary inflation in figures)
Amount of nitrate we would have on site on average business day in 3 year plan
50 lbs or more
Amount of nitrate we would store on site in average business day in 5 year plan
25 lbs or more
Specs for files
Apple prores 422 HQ
Target time period for pilot
2 months
Target number of scans for pilot
100
Target number of total scans
26000
Scanning ratio for production phase
4.75:1