Design Planning and Scheduling (Week 6) Flashcards
What is the engineering design process?
- Specification Development/
Planning Phase
Determine need, customer and
engineering requirements
Develop a project plan - Conceptual Design Phase
Generate and evaluate concepts
Select best solution - Detail Design Phase
CAD models
Engineering drawings
Design documentation
Part specification
Prototype evaluation - Production Phase
Component manufacture and assembly
Plant facilities/capabilities - Service Phase
Installation, use, maintenance and safety - Product Retirement Phase
Length of use, disposal, and recycle
What is design planning
Planning is what need to be done and in what order
it consists of identifying the key tasks (or activities) in a project and ordering them in a sequence in which they should be performed. A project plan is a document that defines the tasks that need to be completed during the design process
What is design scheduling
Design scheduling is when things need to be done, it consists of putting the plan into a calendar
What are the steps of planning the design project
- Identifying Key Tasks
- Stating measurable objectives for each task
- Estimating the personnel needed and time required to meet the objectives
- Developing a sequence for the tasks
- Estimating product development costs
Explain the identifying the tasks step
-Although the tasks should be as specific as possible, the may be vague statements such as “generate concepts” at the early stages of the project.
Explain the state measurable objects step
Each objective must be:
* Easily understood
* Specific
* Feasible (possible, given the personnel, equipment, and time available)
* Defined not as activities to be performed, but as results to be achieved (usually in terms of paperwork produced or prototypes developed)
Step 2A—State the Objective for Task 1
(Product Development Specification)
* Customer requirements identified
* Competition identified and evaluated
* Measurable engineering targets (PDS) for the product
established
Step 2B—State the Objective for Task 2
(Concept Generation and Selection)
* Sketches of several potential concepts, based on a clear
understanding of the functions required
* Evaluation of each concept relative to customer
requirements
* Decision matrices that document the selection of the two
best concepts
Step 2C—State the Objective for Task 3
(Detailed Design)
* Detailed drawings of all components
* Assembly drawings
* Schematics
* Code
* Parts list (Bill of Materials—BOM)
* Manufacturing and assembly procedure
Explain the estimating the personnel needed step
- For each task, identify who on the design team (by job
title) will be responsible for meeting the objectives, what
percentage of their time will be required, and over what
period of time they will be needed - For each person on each task, it will be necessary to
estimate not only the total time requirement but the
distribution of this time - Finally, the total time to complete the task must be
estimated
Typical personnel and time requirements: - Design of elemental assemblies, brackets, plates, straps. All design work
is routine and/or requires only simple modifications of an existing
product. 1 designer for 1 week - Design of elemental devices such as mechanical toys, locks, and scales,
or complex single components. Most design work is routine or calls for
limited original design. 1 designer for 1 month - Design of complete machines and machine tools. Work involved is mainly
routine, with some original design. 2 designers for 4 months - Design of high-performance products that may utilize new (proven)
technologies. Work involves some original design and may require
extensive analysis and testing. 5 designers for 8 months
Explain the Developing a Sequence for the tasks step
- The goal is to have each task accomplished before its
result is needed and, at the same time, to make use of all
of the personnel all the time - The simplest and most commonly used scheduling tool is
the Gantt (or bar) chart - A Gantt chart is a graphical representation of the
duration of tasks against the progression of time
http://www.ganttchart.com/
What is a Gantt Chart?
- A Gantt chart is a horizontal bar chart developed as a
production control tool in 1917 by Henry L. Gantt, an
American engineer and social scientist - Provides a graphical illustration of a schedule that helps to
plan, coordinate, and track specific tasks in a project - On the Gantt chart:
1. Each task is plotted against a time scale (i.e., weeks,
months, etc.)
2. The total personnel requirement for each time unit is
plotted
3. The schedule of design reviews and milestones is shown
Note that, a standard Gantt chart does not show the
dependence of one task upon another