Design Planning and Scheduling (Week 6) Flashcards

1
Q

What is the engineering design process?

A
  1. Specification Development/
    Planning Phase
    Determine need, customer and
    engineering requirements
    Develop a project plan
  2. Conceptual Design Phase
    Generate and evaluate concepts
    Select best solution
  3. Detail Design Phase
    CAD models
    Engineering drawings
    Design documentation
    Part specification
    Prototype evaluation
  4. Production Phase
    Component manufacture and assembly
    Plant facilities/capabilities
  5. Service Phase
    Installation, use, maintenance and safety
  6. Product Retirement Phase
    Length of use, disposal, and recycle
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is design planning

A

Planning is what need to be done and in what order
it consists of identifying the key tasks (or activities) in a project and ordering them in a sequence in which they should be performed. A project plan is a document that defines the tasks that need to be completed during the design process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is design scheduling

A

Design scheduling is when things need to be done, it consists of putting the plan into a calendar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the steps of planning the design project

A
  1. Identifying Key Tasks
  2. Stating measurable objectives for each task
  3. Estimating the personnel needed and time required to meet the objectives
  4. Developing a sequence for the tasks
  5. Estimating product development costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Explain the identifying the tasks step

A

-Although the tasks should be as specific as possible, the may be vague statements such as “generate concepts” at the early stages of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Explain the state measurable objects step

A

Each objective must be:
* Easily understood
* Specific
* Feasible (possible, given the personnel, equipment, and time available)
* Defined not as activities to be performed, but as results to be achieved (usually in terms of paperwork produced or prototypes developed)
Step 2A—State the Objective for Task 1
(Product Development Specification)
* Customer requirements identified
* Competition identified and evaluated
* Measurable engineering targets (PDS) for the product
established
Step 2B—State the Objective for Task 2
(Concept Generation and Selection)
* Sketches of several potential concepts, based on a clear
understanding of the functions required
* Evaluation of each concept relative to customer
requirements
* Decision matrices that document the selection of the two
best concepts
Step 2C—State the Objective for Task 3
(Detailed Design)
* Detailed drawings of all components
* Assembly drawings
* Schematics
* Code
* Parts list (Bill of Materials—BOM)
* Manufacturing and assembly procedure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Explain the estimating the personnel needed step

A
  • For each task, identify who on the design team (by job
    title) will be responsible for meeting the objectives, what
    percentage of their time will be required, and over what
    period of time they will be needed
  • For each person on each task, it will be necessary to
    estimate not only the total time requirement but the
    distribution of this time
  • Finally, the total time to complete the task must be
    estimated
    Typical personnel and time requirements:
  • Design of elemental assemblies, brackets, plates, straps. All design work
    is routine and/or requires only simple modifications of an existing
    product. 1 designer for 1 week
  • Design of elemental devices such as mechanical toys, locks, and scales,
    or complex single components. Most design work is routine or calls for
    limited original design. 1 designer for 1 month
  • Design of complete machines and machine tools. Work involved is mainly
    routine, with some original design. 2 designers for 4 months
  • Design of high-performance products that may utilize new (proven)
    technologies. Work involves some original design and may require
    extensive analysis and testing. 5 designers for 8 months
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Explain the Developing a Sequence for the tasks step

A
  • The goal is to have each task accomplished before its
    result is needed and, at the same time, to make use of all
    of the personnel all the time
  • The simplest and most commonly used scheduling tool is
    the Gantt (or bar) chart
  • A Gantt chart is a graphical representation of the
    duration of tasks against the progression of time
    http://www.ganttchart.com/
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a Gantt Chart?

A
  • A Gantt chart is a horizontal bar chart developed as a
    production control tool in 1917 by Henry L. Gantt, an
    American engineer and social scientist
  • Provides a graphical illustration of a schedule that helps to
    plan, coordinate, and track specific tasks in a project
  • On the Gantt chart:
    1. Each task is plotted against a time scale (i.e., weeks,
    months, etc.)
    2. The total personnel requirement for each time unit is
    plotted
    3. The schedule of design reviews and milestones is shown
    Note that, a standard Gantt chart does not show the
    dependence of one task upon another
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly