Design Economics and Cost Planning Flashcards

1
Q

What is the official title for NRM 1?

A

Order of cost estimating and cost planning for capital building works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the latest edition of NRM 1?

A

3rd Edition October 2021

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Using NRM 1, how do you structure the cost planning for ‘2. Super-structure’

A

2.1 Frame (m2)
2.2 Upper floors (m2)
2.3 Roof (m2)
2.4 Stairs and ramps (nr)
2.5 External walls (m2)
2.6 Windows and external doors (m2)
2.7 Internal walls and partitions (m2)
2.8 Internal doors (nr)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Using NRM 1, how do you structure the cost plan for ‘8. External Works’

A

8.1 Site preparation works
8.2 Roads, paths, paving’s and surfacing’s
8.3 Soft landscapes, planting and irrigation systems
8.4 Fencing, railings and walls
8.5 External fixtures
8.6 External drainage
8.7 External services
8.8 Minor building works and ancillary buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly