Delivery Methods Flashcards
Identify which of the following are project delivery systems.
CM-at –Risk
Design-Build
Competitive Bidding
Competitive Sealed Proposals
Under optimal conditions and compared to all other delivery systems, which delivery method has the shortest overall construction duration?
Design Build
When using the CM@Risk Method, the fee and general conditions are determined when the GMP is submitted.
False
Provided the conditions are optimal, which of the delivery systems typically affords the lowest unit cost?
Design Build
Which delivery system allows the contractor to control the design?
Design Build
Which project type is typically used on larger and more complex projects?
CM@Risk
RFP & RFQ are considered to be a two step process in which of the following procurement systems
Design Build
CM@Risk
Which delivery system has the greatest amount of risk for the contractor?
Design Build
Design build carries the greatest risk because the contractor is solely responsible for design and construction. Most design build contracts are based upon the owner issuing the building intent or basis of design and the contractor must have the expertise to delivery this performance specification.
Which delivery system allows the contractor to have input on the design?
Design Build
CM@Risk
The term GMP stands for
guaranteed maximum price
Design Build is permitted in all 50 states of the US
False
Contingencies should always be inside of the GMP.
False
the owner’s contingencies are never carried within the GMP, therefore the answer is false.
Which delivery system provides the owner with the lowest cost and the ability to utilize the procurement method of best value?
Competitive Sealed Proposals
Which delivery system has the least amount of risk for the contractor?
Design-Bid-Build
or optimal impact and performance, the delivery method for a project should be determined at what phase of a project?
the start of conceptual design