Definitions Flashcards
Indemnification
Also called Hold Harmless Clause, is a contractual obligation whereby one party agrees to guarantee another party against loss or damage from specific liabilities.
Schedule Of Values
A statement furnished to the architect by the contractor reflecting the amounts to be allotted for the principle divisions of the work. It serves as a guide for reviewing the contractors periodic applications for payment.
Record Drawing
The show field changes that occurred during construction, which may vary from the information shown in the working drawings. They are not as built drawings. Field changes should be recorded by the contractor on a set of record prints at the site. Should be transferred to a permanent/reproducible medium by the contractor. If the architect is to do it, it is considered a change in services.
Substantial Completion
According to A201, it is the stage in the work when the work or designated portion of the work is sufficiently complete in accordance with the contract document so that the owner can occupy or utilize the work for its intended use. -Contractor Decides this point -if the contractor fails to include and item of remaining work it does not alleviate his/her responsibilities. -The architect prepares the certificate of substantial completion.
Certificate of Substantial Completion
A document prepared by the architect saying that the work is substantially complete. It generally fixes the time within which the contractor must complete the unfinished work on the punch list. It has to be signed by the Owner, Architect and the Contractor.
Retainage
Found in A101. The process in which the owner withholds money from the contractor as protection against the contractors potential failure to complete the work according to the contract documents. Retain-age should not be reduced or released without the written consent of the surety.
Quality Control
It involves carefully checking work (a contract, set of drawings, a design sketch) before it is distributed to the user (owner, contractor, and drafter)
Quality Assurance
It is a supplement to to quality control. It requires that in designing, documenting, and constructing a building, the proper resources and scrutiny are applied to each part of the process.
Total Quality Management (TQM)
It is developed in a response to the limitations of quality assurance. Quality Control + Quality Assurance + All aspect of service = Customer Satifaction.
Statute of Limitations
An ordinance which specifies the period of time within which legal action must be brought in order to obtain legal relief for damage or injury.
Liquidated Damages
It is included in the Owner/Contractor Agreement. It is the amount of money stipulated in the contract that is chargeable against the contractor as reimbursement for damages suffered by the owner because of the contractors failure to fulfill contractural obligations. They are not to be used as a penalty for the contractor. Only used if the owner suffers actual loss due to delays in construction.
Mechanic’s Lein/Lein
It is a claim against someones property, not on the person’s other assets. It provides security that labor and materials supplied to construct buildings will be paid in the event of non-payment to those who furnished the labor and materials. It forces sale of the owners property in order to satisfy a claim of payment. Clear title to the property cannot be obtained until the claim is settled. Cannot happen on public projects.
How to protect the owner form mechanics leins?
1) Retain-age
2) Labor and Materials Bond: Purchased by the contractor at the request of the owner. Guarantees payment for labor and materials should the contractor fail to pay them. (AIA A312)
3) Affidavit of Release of Leins: Contractor must submit those to receive final payment and in some cases progress payments. (AIA G706A)
Changes in work - General
If changes involve additional or reduced cost or time, they must be documented by the issuance of a change order. Other changes not involving cost or time, can be ordered by supplemental instructions (G710).
Changes in Work - Minor Changes
The architect may authorize minor changes or modification seeing it does not effect the contract time or cost. The architect can also absorb the expense for his or her services as a courtesy to the owner. The architect can use AIA G710 for that purpose - Architects Supplemental Instructions.