Defining the Project Budget and Risk Plans Flashcards

1
Q

Security Policy

A

a document (or documents) that outlines the minimum standards required to secure the organization’s technology-related systems, assets, and data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Physical Security

A

involves securing physical assets such as mobile devices, removeable media devices, access to facilities, and more

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Operational Security

A

includes policies for performing background checks and security clearances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Digital Security

A

security policies that are related to access and permissions to digital assets. This may include systems, data, communication equipment and more. Access is typically role-based

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Multifactor Authentication (MFA)

A

a process whereby the user must use two or more methods to verify their identity during the sign-in process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Need-to-know

A

Involves relaying the least amount of information needed for their activity, and nothing more

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Work effort

A

the total time it will take for a person to complete the task if they do nothing else from the time they start until the task is complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Three-point estimate

A

an average of the most likely estimate, the optimistic estimate, and the pessimistic estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost baseline

A

the total expected cost for the project. Once approved, it’s used throughout the remainder of the project to measure the overall cost performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project budget

A

used to track the actual expenses incurred against the estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Capital Expenses (CapEx)

A

apply to assets that are expected to provide benefit to the organization for an extended time into the future

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Operational Expenses (OpEx)

A

include all expenses needed to run the day-to-day activities of the business such as administrative costs, training, travel, supplies, materials, salaries, rent, and leases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Contingency reserve

A

also known as a buffer, is a certain amount of money set aside to cover costs resulting from possible adverse events or unexpected issues on the project

funds are controlled by the project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Management reserve

A

an amount set aside by upper management to cover future situations that can’t be predicted

funds are controlled by upper management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Expenditure tracking

A

measures the project spending to date, determining the burn rate (how fast you go through the money), and tracking expenditures to the cost baseline so that stakeholders can see what was planned verses what was actually spent on the project

is the mechanism you’ll use to report on the current state of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Burn rate

A

the rate at which you are spending funds over time

total budget / time period

17
Q

Earned Value Management (EVM)

A

a performance measurement technique that compares what your project has produced to what you’ve spent by monitoring the planned value, earned value, and actual costs expended to produce the work of the project

18
Q

Planned Value (PV)

A

the approved budget assigned to the work to be completed during a given time period

19
Q

Actual Cost (AC)

A

money that’s actually been expended during a given time period for completed work

20
Q

Earned Value (EV)

A

the value of the work completed to date compared to the budget

21
Q

Cost Variance (CV)

A

measures the actual performance to date against what’s been spent

CV = EV - AC

22
Q

Schedule Variance (SV)

A

compares an activitiy’s actual progress to date to the estimated progress and is represented in terms of costs

Tells you whether the schedule is ahead of or behind what was planned for this period

SV = EV - PV

negative number = behind schedule

positive number = on or ahead of schedule

23
Q

Cost Performance Index (CPI)

A

measures the value of the work completed at the measurement date against the actual cost. It is the most critical of all the EVM measurements because it tells you the cost efficiency for the work completed to the date or at the completion of the project

                                                          CPI = EV / AC

If CPI > 1 = you are spending less than the anticipated at the measurement date

If CPI < 1 = you are spending more than the anticipated at the measurement date

24
Q

Risk

A

a potential future event that can have either negative or positive impacts on the project

25
Q

Risk Planning

A

deals with how you manage the areas of uncertainty in your project

26
Q

Risk Identification

A

the process of determining and documenting the potential risks that could occur on your project

27
Q

Risk register

A

a list of risks that includes an identification number, risk name, risk description, risk owner, and response plan

28
Q

Force majeure

A

catastrophic in nature and are outside the control of the organization and cannot be addressed with a risk response plan. Often addressed using a disaster recovery plan or cybersecurity incident response plan

might include war, employees going on strike, pandemics, cyber attacks, natural disasters, etc.

29
Q

SWOT Analysis

A

Involves analyzing the project from each of these perspectives: Strengths, Weaknesses, Opportunities, and Threats

Strengths and Weaknesses = internal

Opportunities and Threats = external

30
Q

Risk Analysis

A

identifies risks that have the greatest possibility of occurring and the greatest impact to the project if they do occur