Defining the Project Budget and Risk Plans Flashcards
Security Policy
a document (or documents) that outlines the minimum standards required to secure the organization’s technology-related systems, assets, and data
Physical Security
involves securing physical assets such as mobile devices, removeable media devices, access to facilities, and more
Operational Security
includes policies for performing background checks and security clearances
Digital Security
security policies that are related to access and permissions to digital assets. This may include systems, data, communication equipment and more. Access is typically role-based
Multifactor Authentication (MFA)
a process whereby the user must use two or more methods to verify their identity during the sign-in process
Need-to-know
Involves relaying the least amount of information needed for their activity, and nothing more
Work effort
the total time it will take for a person to complete the task if they do nothing else from the time they start until the task is complete
Three-point estimate
an average of the most likely estimate, the optimistic estimate, and the pessimistic estimate
Cost baseline
the total expected cost for the project. Once approved, it’s used throughout the remainder of the project to measure the overall cost performance
Project budget
used to track the actual expenses incurred against the estimates
Capital Expenses (CapEx)
apply to assets that are expected to provide benefit to the organization for an extended time into the future
Operational Expenses (OpEx)
include all expenses needed to run the day-to-day activities of the business such as administrative costs, training, travel, supplies, materials, salaries, rent, and leases
Contingency reserve
also known as a buffer, is a certain amount of money set aside to cover costs resulting from possible adverse events or unexpected issues on the project
funds are controlled by the project manager
Management reserve
an amount set aside by upper management to cover future situations that can’t be predicted
funds are controlled by upper management
Expenditure tracking
measures the project spending to date, determining the burn rate (how fast you go through the money), and tracking expenditures to the cost baseline so that stakeholders can see what was planned verses what was actually spent on the project
is the mechanism you’ll use to report on the current state of the project