Creating a Project Schedule Flashcards

1
Q

Four types of logical relationships

A

finish-to-start, start-to-start, start-to-finish, finish-to-finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Work Breakdown Structure (WBS)

A

A deliverables-oriented hierarchy that defines the work of the project and can be used on projects of any size or complexity.

Takes the major deliverables from the scope statement and decomposes them into smaller, more manageable components.
Includes all the work required to complete the project.

It’s the basis for time and cost estimates, and resource assignments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

WBS Dictionary

A

a list of ever deliverable and each of their components contained in the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Critical Path Method (CPM)

A

creates a schedule by determining float time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Float time

A

the difference between the early and late start dates, and the early and late finish dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Duration Compression

A

a technique used to shorten a project schedule to meet a mandated completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Crashing

A

shortens task duration by adding more resources to the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Fast tracking

A

where two tasks are started in parallel that were previously schedule to start sequentially

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Milestones

A

mark major project events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Gantt Chart

A

One of the most common ways to display project schedules; displayed as bar charts that span the entire project timeline. May show milestones, deliverables, and all the tasks of a project, including their durations, start and end dates, and the resources assigned to each task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Sequencing

A

the process of identifying relationships between project activities and sequencing them in proper order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Dependencies

A

relationships between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Analogous estimating

A

also called “top-down estimating”, is a technique that uses actual durations from similar tasks on a previous project. It is typically the least accurate means of obtaining an estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Expert Judgment

A

an estimating technique where the people most familiar with the work determine the estimate. Most frequently used on Agile projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Parametric Estimating

A

a quantitative estimating method that multiplies the quantity of work by the rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Bottom-Up Estimating

A

an estimating technique that obtains individual estimates for each project activity and then adds them all to arrive at a total estimate for the work package. It is a good technique to use when you aren’t sure about the type or quantity of resources you’ll need for the project.

17
Q

Project Management Plan

A

defines how the project is executed, how you’ll measure performance, and how it’s closed

18
Q

Performance Measurement Baseline

A

consists of the scope, schedule, and cost baselines

19
Q

Scope Baseline

A

includes the scope statement, WBS, and WBS dictionary. Is used throughout the remainder of documents and will also be used as a basis to determine the outcomes of change requests

20
Q

Work Package Level

A

the lowest level of WBS where resources, time, and cost estimates are determined

21
Q

Predecessor task

A

a task that exists on a path with another task and occurs before the task in question

22
Q

Successor task

A

a task that exists on a common path with another task and occurs after the task in question

23
Q

Network diagram

A

used to depict project activities and the interrelationships and dependencies among these activities

24
Q

Resource leveling

A

Attempts to balance out the resource assignments to get tasks completed without overloading the individual. Can change the critical path and project end date

25
Q

Resource smoothing

A

Accommodates resource availability by modifying activities within their float times without changing the critical path or project end date.

26
Q

Program Evaluation and Review Technique (PERT)

A

a chart that was created by the Navy as a way to manage the project and forecast the project schedule with a high degree of reliability. Uses three-point estimates known as the weighted average to calculate estimates for task duration. Weighted average consists of three estimates: optimistic, pessimistic, and most likely. Formula is: optimistic + pessimistic + (4 x most likely) / 6

27
Q

Scope Management Plan

A

describes how the deliverables will be validated

28
Q

Code of accounts identifier

A

a unique number assigned to each component of the WBS. It is documented in the WBS dictionary and is tied to the chart of accounts

29
Q

WBS Levels

A
  1. Project name
  2. Major project deliverables, project phases, or subprojects
30
Q

Velocity

A

used to determine how long it will take to complete the work of the iteration by measuring the speed the team progresses.