1
Q

Architect and Contractor total days to process submittals

A

“Reasonable time” stated in agreement, usually 10 days or 2 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Date of Commencement or Contract Time begins

A
  1. Date of signing O/C agreement
  2. Date stated in O/C agreement
  3. Issuance by Owner of a formal Notice to Proceed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Contract time ends

A

Date of substantial completion written on the Certificate of Substantial Completion issued by the Architect, and signed by O/A/C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cause: additional cost, time delays, unknown conditions or contractual conflicts

Concerned party must initiate claim for requesting a change order within ___ days of occurrence

A

21 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Time limits for claims

A

O/A/C can revisit a previous dispute and resolved claim 10 years after the date of substantial completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Respond to a claim under IDM dispute

A

Designated IDM (usually architect according to A201) has 10 days to respond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Period covered by each Application for Payment

A

G702 and G703

1 calendar month ending on the last day of the month or as stated in the agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contractor to submit an Application for payment to the Architect (G702)

A

Submit 10 days prior to date established on schedule of values (if stipulated sum)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Days allotted to Architect and Owner for processing each progress payment

A

“Reasonable time” but generally 14 days total

A201 - Architect has 7 days, after receipt of contractor’s pay app, to issue owner a certificate of payment, or notify parties of reasons for withholding certification.

Owner must pay Contractor within time provided in contract, or within 7 days after date established in contract for payment. Should CC Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Days allotted to O/A for processing Final Payment

A

“Reasonable time”
Generally 37 days total

A201 - Architect has 7 days, after receipt of contractor’s pay all to issue certificate

A101 - Owner must pay final payment no later than 30 days after issuance of final certificate of payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Warranty Period

A

Begin at substantial completion and last 1 year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Required project inspection by Architect

A
  1. Substantial Completion

2. Final completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Bidders allotted time for bid preparation

A

2 week min

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Mechanic’s Lien

A

Required to be filed within 30 to 90 days after the last work is performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Suit to enforce bond

A

2 years from date on which final payment is due

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Owner wants to terminate contract with contractor

A

7 days notice prior to termination

17
Q

Days allotted to Architect for payment to consultant

A

10 days from receipt

18
Q

All design phases

A

7-12 months typically;

SD: 1-2 months
DD: 2-4 months
CD: 3-7 months
Bidding/negotiation: 3-6 weeks

19
Q

Owner and Architect review and approve subcontractor and super replacements

A

10 days prior to date of notice

20
Q

Contractor may STOP WORK within 7 days notice, until payment had been received if;

A
  1. Architect doesn’t issue pay app within 7 days of receipt

2. Owner doesn’t pay contractor within 7 days after established date in contract