Days Flashcards
Architect and Contractor total days to process submittals
“Reasonable time” stated in agreement, usually 10 days or 2 weeks
Date of Commencement or Contract Time begins
- Date of signing O/C agreement
- Date stated in O/C agreement
- Issuance by Owner of a formal Notice to Proceed
Contract time ends
Date of substantial completion written on the Certificate of Substantial Completion issued by the Architect, and signed by O/A/C
Cause: additional cost, time delays, unknown conditions or contractual conflicts
Concerned party must initiate claim for requesting a change order within ___ days of occurrence
21 days
Time limits for claims
O/A/C can revisit a previous dispute and resolved claim 10 years after the date of substantial completion
Respond to a claim under IDM dispute
Designated IDM (usually architect according to A201) has 10 days to respond
Period covered by each Application for Payment
G702 and G703
1 calendar month ending on the last day of the month or as stated in the agreement
Contractor to submit an Application for payment to the Architect (G702)
Submit 10 days prior to date established on schedule of values (if stipulated sum)
Days allotted to Architect and Owner for processing each progress payment
“Reasonable time” but generally 14 days total
A201 - Architect has 7 days, after receipt of contractor’s pay app, to issue owner a certificate of payment, or notify parties of reasons for withholding certification.
Owner must pay Contractor within time provided in contract, or within 7 days after date established in contract for payment. Should CC Architect
Days allotted to O/A for processing Final Payment
“Reasonable time”
Generally 37 days total
A201 - Architect has 7 days, after receipt of contractor’s pay all to issue certificate
A101 - Owner must pay final payment no later than 30 days after issuance of final certificate of payment
Warranty Period
Begin at substantial completion and last 1 year
Required project inspection by Architect
- Substantial Completion
2. Final completion
Bidders allotted time for bid preparation
2 week min
Mechanic’s Lien
Required to be filed within 30 to 90 days after the last work is performed
Suit to enforce bond
2 years from date on which final payment is due