CDS - Misc Flashcards
What is the standard width of an exit corridor?
44 inches
Floor area required for one stationary wheelchair
30” x 48”
Means of egress consists of 3 parts. They are:
- The exit access:
Portion that leads to the entrance of an exit. Travel distance is regulated - The exit:
Portion that provides a protected (1 or 2 hr rating) and fully enclosed path of egress - The exit discharge:
Portion between exit and public way
An area of refuge is designed to ________
Keep individuals who are unable to exit a building safe during a fire
During construction, architect realizes that some of the weld tests required on structural steel was not included in the specs. Who is required to pay?
Owner.
Contractor covers cost of tests specified. Any omitted is at owner’s expense
If price escalates for the cost of material from the time of bid to when it’s needed and purchased for construction, is the Contractor entitled to a change order?
No, not typically in a lump sum contract.
If there is an Escalation clause set forth however, the owner is responsible to pay.
Owner may be inclined to accept an escalation clause with the thinking that it would ease Bidders to pad their numbers less.
Special conditions -vs.- Supplementary Conditions
Supplementary Conditions are modifications to the general conditions to accommodate the legal, physical, or climatic conditions of the project.
Special Conditions are only for those requirements that will change from project to project, such as; soil borings, traffic control, reference docs / codes, inspections and tests
If a change in the work result in an increase in the construction sum, the following methods may be used to determine the amount of increase:
1.
2.
3.
- Lump sum
- Unit prices
- Cost plus fee
Division 11
Equipment
If the common path of egress travel is greater than _____ feet, provide 2 exits.
- Except in H occupancy group.
- Sometimes common path can be extended to 100 feet if certain conditions are met
75 feet
The maximum rise of an ADA ramp is _____
30 inches
A305
Contractor’s qualification statement
Vertical loads on building may be caused by: 1. 2. 3. 4.
- Winds
- Differential settlement
- Expansive soils
- Frost settlement caused by non-uniform soil conditions
An architect is designing a project in a hot-arid climate. What are 3 strategies they can employ to bring in daylight but not heat
Light shelves
Fritted glass
North-facing glass
A305 (Contractor’s qualification statement) requires what following supplemental document to be provided by the applicant?
Financial statement
Occupancy group table:
ABEFHIMRSU
Assembly Business Educational Factory and industrial Hazardous Institutional Mercantile Residential Storage Utilities
Standard of care is measured by what?
The professional skill and care provided by Architects practicing in the same or similar locality under similar circumstances
Sound Transmission Class (STC) vs. Impact Isolation Class (IIC)
Is the method of rating acoustic efficiency of various wall and floor systems in isolating airborne sound transmission. STC ratings aren’t appropriate in considering the effect of impact noises on floor assemblies caused by foot traffic or machinery (impact noises). For that purpose Impact Isolation Class (IIC) is used.
Shop drawings show a Contractor __________
How to install a specific item of equipment or material
Acceptable accessible route slope
1:20. Slopes greater are considered a ramp (min 1:12)
Liquidated Damages
Included in the Owner/Contractor agreement. Is an amount of money stipulated in the contract chargeable against the contractor as reimbursed damages for not finishing in time / where delayed construction results in actual loss to the owner.
Amount of damage due for each day lost should be provided in the Supplementary Conditions.
- specifying recycled materials and products
- designing a materials flow plan for the contractor and user
- specifying masonry over wood construction
And, - assisting owner and contractor in a waste management plan
Are all ways the Architect can _________________
Decrease the amount of construction related waste
What is the maximum length of a corridor with a dead end?
20 feet standard
Occupant load factor
The amount of floor area presumed to be occupied by one person
Certificate of Substantial Completion (G704)
G704:
A document prepared by the Architect stating the work is substantially complete, thereby establishing the date of substantial completion.
Has to be signed by the O, A, and C
Primary purpose of building code fire safety regulations
To provide for life safety and to enable occupants to safely evacuate a building
A701
Instruction to Bidders
Fiduciary
Party to whom another party entrust property for safe keeping
Division 04
Masonry
Total Cost of a Project
In addition to direct cost of construction;
- professional fees
- land costs
- furnishings and Equipment
- financing and legal costs
- cost of inspection and tests
These additional costs are usually about 20% of the cost of construction
Division 05
Metals
Where are sustainability provisions found?
In Division 01 general requirements
Division 10
Specialties
An ADA riser has a maximum dimension of ___ inches?
7 inches maximum! 4 inches minimum
Minimum passage width for two wheelchairs
60”
The Contractor uncovers conditions that differ from the contract docs. How many days do they have to provide notice to the Owner and Architect?
21 days
A705
List of subcontractors
According to ADA guidelines, a curb ramp running slope shall not exceed ____
1:12
What does the project manual include that the contract documents do not?
Bidding forms / bidding info
The contract docs however additionally include working drawings, addenda, and change orders
Cluster Zoning results in ______
Permanent community open space.
Division 07
Thermal and moisture protection
Division 06
Wood and Plastics