CDS - Misc Flashcards

1
Q

What is the standard width of an exit corridor?

A

44 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Floor area required for one stationary wheelchair

A

30” x 48”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Means of egress consists of 3 parts. They are:

A
  1. The exit access:
    Portion that leads to the entrance of an exit. Travel distance is regulated
  2. The exit:
    Portion that provides a protected (1 or 2 hr rating) and fully enclosed path of egress
  3. The exit discharge:
    Portion between exit and public way
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

An area of refuge is designed to ________

A

Keep individuals who are unable to exit a building safe during a fire

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

During construction, architect realizes that some of the weld tests required on structural steel was not included in the specs. Who is required to pay?

A

Owner.

Contractor covers cost of tests specified. Any omitted is at owner’s expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If price escalates for the cost of material from the time of bid to when it’s needed and purchased for construction, is the Contractor entitled to a change order?

A

No, not typically in a lump sum contract.

If there is an Escalation clause set forth however, the owner is responsible to pay.

Owner may be inclined to accept an escalation clause with the thinking that it would ease Bidders to pad their numbers less.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Special conditions -vs.- Supplementary Conditions

A

Supplementary Conditions are modifications to the general conditions to accommodate the legal, physical, or climatic conditions of the project.

Special Conditions are only for those requirements that will change from project to project, such as; soil borings, traffic control, reference docs / codes, inspections and tests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If a change in the work result in an increase in the construction sum, the following methods may be used to determine the amount of increase:
1.
2.
3.

A
  1. Lump sum
  2. Unit prices
  3. Cost plus fee
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Division 11

A

Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If the common path of egress travel is greater than _____ feet, provide 2 exits.

  • Except in H occupancy group.
  • Sometimes common path can be extended to 100 feet if certain conditions are met
A

75 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The maximum rise of an ADA ramp is _____

A

30 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A305

A

Contractor’s qualification statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
Vertical loads on building may be caused by:
1.
2.
3.
4.
A
  1. Winds
  2. Differential settlement
  3. Expansive soils
  4. Frost settlement caused by non-uniform soil conditions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

An architect is designing a project in a hot-arid climate. What are 3 strategies they can employ to bring in daylight but not heat

A

Light shelves
Fritted glass
North-facing glass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A305 (Contractor’s qualification statement) requires what following supplemental document to be provided by the applicant?

A

Financial statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Occupancy group table:

ABEFHIMRSU

A
Assembly
Business
Educational 
Factory and industrial
Hazardous
Institutional 
Mercantile 
Residential
Storage
Utilities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Standard of care is measured by what?

A

The professional skill and care provided by Architects practicing in the same or similar locality under similar circumstances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Sound Transmission Class (STC) vs. Impact Isolation Class (IIC)

A

Is the method of rating acoustic efficiency of various wall and floor systems in isolating airborne sound transmission. STC ratings aren’t appropriate in considering the effect of impact noises on floor assemblies caused by foot traffic or machinery (impact noises). For that purpose Impact Isolation Class (IIC) is used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Shop drawings show a Contractor __________

A

How to install a specific item of equipment or material

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Acceptable accessible route slope

A

1:20. Slopes greater are considered a ramp (min 1:12)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Liquidated Damages

A

Included in the Owner/Contractor agreement. Is an amount of money stipulated in the contract chargeable against the contractor as reimbursed damages for not finishing in time / where delayed construction results in actual loss to the owner.

Amount of damage due for each day lost should be provided in the Supplementary Conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
  • specifying recycled materials and products
  • designing a materials flow plan for the contractor and user
  • specifying masonry over wood construction
    And,
  • assisting owner and contractor in a waste management plan

Are all ways the Architect can _________________

A

Decrease the amount of construction related waste

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the maximum length of a corridor with a dead end?

A

20 feet standard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Occupant load factor

A

The amount of floor area presumed to be occupied by one person

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Certificate of Substantial Completion (G704)

A

G704:
A document prepared by the Architect stating the work is substantially complete, thereby establishing the date of substantial completion.

Has to be signed by the O, A, and C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Primary purpose of building code fire safety regulations

A

To provide for life safety and to enable occupants to safely evacuate a building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

A701

A

Instruction to Bidders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Fiduciary

A

Party to whom another party entrust property for safe keeping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Division 04

A

Masonry

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Total Cost of a Project

A

In addition to direct cost of construction;

  • professional fees
  • land costs
  • furnishings and Equipment
  • financing and legal costs
  • cost of inspection and tests

These additional costs are usually about 20% of the cost of construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Division 05

A

Metals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Where are sustainability provisions found?

A

In Division 01 general requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Division 10

A

Specialties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

An ADA riser has a maximum dimension of ___ inches?

A

7 inches maximum! 4 inches minimum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Minimum passage width for two wheelchairs

A

60”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

The Contractor uncovers conditions that differ from the contract docs. How many days do they have to provide notice to the Owner and Architect?

A

21 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

A705

A

List of subcontractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

According to ADA guidelines, a curb ramp running slope shall not exceed ____

A

1:12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What does the project manual include that the contract documents do not?

A

Bidding forms / bidding info

The contract docs however additionally include working drawings, addenda, and change orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Cluster Zoning results in ______

A

Permanent community open space.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Division 07

A

Thermal and moisture protection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Division 06

A

Wood and Plastics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Division 12

A

Furnishings

44
Q

Number of exits required

A
  • up to max. Occupant load of the code: at least 1 exit
  • more than max occupant load: at least 2
  • common path of egress exceeds code limit: at least 2 exits
  • between 501-1000: 3 exits
  • more than 1000: at least 4 exits

(1 exit for every 250 people)

45
Q

A contract allowance for building signage is established at $50K. The signage ends up costing $5K. In accordance with A201, the Contractor should offer a credit charge change order for _________

A

$5K (nothing taken out for overhead of profit, since that was established in contract)

46
Q

Mechanics’ Lien / Lien

A

A claim against someone’s property, not on the person’s assets.

  • Secures that labor and materials supplied will be paid. Clear title to the property cannot be obtained until the claim is settled.
  • Not permitted on public projects; Miller act requires Contractors to acquire labor and material bonds
47
Q

Division 16

A

Electrical

48
Q

For wheelchair to make 180 degree turn

A

60”

49
Q

Division 15

A

Mechanical

50
Q
Which of the following are considered security for a project?
A. Bid Bond
B. Payment Bond
C. Completion Bond
D. Performance check
E. Certified check
F. Lien Bond
A

A. Bid Bond

E. Certified check

51
Q

Under the terms where there is a construction manager, in what order do the parties review shop drawings?

A

Contractor - Construction Manager - Architect

52
Q

Architects have the duty to protect the general public. What public interests does the Architect endeavor to protect? Name 3

A

Safety
Health
Welfare

53
Q

Division 13

A

Special construction

54
Q

When a performance bond is required by the contract documents, it must be delivered to the Owner _____

A

Prior to the commencement of work

55
Q

Standard minimum width for an exit corridor?

A

44 inches

56
Q

An architect carries ________ to help protect against any lawsuits arising from mistakes in drawings

A

Professional liability insurance

57
Q

Expansion Joints vs. Control Joint

A

Expansion joints = not filled with mortar; allow masonry to move independently of a structural steel or concrete frame. Control joints = filled with mortar; relieve forces that may build up within individual masonry or concrete elements

58
Q

What type of test equipment is used to check for air infiltration on an already constructed exterior wall system?

A

Smoke pencil

59
Q

The owner occupies a portion of the building after the Architect has deemed the project substantially complete. The owner notices a hole in the wall that wasn’t noted on the architect’s punchlist. Who is responsible for fixing the issue?

A

The owner has taken occupancy and is therefore responsible as the cause of damage cannot be established

60
Q

Division 09

A

Finishes

61
Q

Which party is responsible for administering the contract?

A

The Architect is responsible for administering the contract and making sure the completed work aligns with the contract documents

62
Q

How often is the Architect required to make visits to the site?

A

At intervals appropriate to the stage of construction

63
Q

A full-size mock-up is appropriate when:
1.
2.
3.

A
  1. Material or system is to be used repetitively on the project
  2. The installation will be the first use of an untested material or system
  3. The project is to serve as a prototype
64
Q

What is the maximum length of a corridor with a dead end?

A

20 feet standard

65
Q

What is the standard width of an exit corridor?

A

44 inches

66
Q

G701

A

Change Order

67
Q

Schedule of Values

A

Statement from the Contractor to the Architect serving as a guide for reviewing contractor’s applications for payment. Reflects amounts to be allotted for divisions of the work

68
Q

Quality Assurance

A

Requires that in designing, documenting, and constructing a building, proper resources and scrutiny are applied to each part of the process to prevent errors beforehand / early.

Compare to Quality Control; requires review only before distribution

69
Q

Poor indoor air quality can result in sick building syndrome. What are 3 factors that can contribute to sick building syndrome?

A
  1. Tobacco smoke
  2. Inadequate ventilation
  3. Off-gassing from installed products
70
Q

The specifications are NOT divided into _____

A
  • Chapters

They are divided into;
Divisions, sections, and parts

71
Q

According to ADA guidelines, a curb ramp running slope shall not exceed ____

A

1:12

72
Q

Accessory occupancy

A

A space or room that is an accessory to a main occupancy but doesn’t exceed 10% of the main occupancy. (I.e. A gift shop within a hospital)

73
Q

The owner occupies a portion of the building after the Architect has deemed the project substantially complete. The owner notices a hole in the wall that wasn’t noted on the architect’s punchlist. Who is responsible for fixing the issue?

A

The owner has taken occupancy and is therefore responsible as the cause of damage cannot be established

74
Q

The maximum rise of an ADA ramp is _____

A

30 inches

75
Q

Minimum clear width for accessible route

A

36”

76
Q

Division 08

A

Openings / doors and windows

77
Q

Poor indoor air quality can result in sick building syndrome. What are 3 factors that can contribute to sick building syndrome?

A
  1. Tobacco smoke
  2. Inadequate ventilation
  3. Off-gassing from installed products
78
Q

Where are close-out procedures found?

A

In division 01 general requirements

79
Q

The specifications are NOT divided into _____

A
  • Chapters

They are divided into;
Divisions, sections, and parts

80
Q

An area of refuge is designed to ________

A

Keep individuals who are unable to exit a building safe during a fire

81
Q

Planned Unit Development

A

(PUD) is similar to cluster development, but is larger in scale and may include commercial and industrial development as well as housing. Since PUD utilizes the cluster zoning concept, it generally doesn’t require a zoning variance.

82
Q

The 3 parts of a spec and what is in them

A
  1. General - What’s covered/the scope, related sections, required submittals (if applicable), guarantees, warranties
  2. Materials - the materials, products, and equipment to be used (can list multiple options if an open spec)
  3. Execution - instruct how to install the products and perform the work
83
Q

Accessible door hardware

A

Mounted 48” max abv finished floor

84
Q

Division 03

A

Concrete

85
Q

The elements that comprise an exit to the outside, including aisles, corridors, doors, and stairways are called what?

A

Means of Egress

86
Q

On-site field observations by the architect are used to determine (name 3):

A
  1. Progress and quality of work
  2. Amount of work completed for progress payment
  3. Whether work is being completed in accordance to contract docs
87
Q

Indemnification

A

Aka ‘Hold Harmless Clause’
A contractual obligation where one party agrees to guarantee another party against loss or damage from specified liabilities

88
Q

An architect carries ________ to help protect against any lawsuits arising from mistakes in drawings

A

Professional liability insurance

89
Q

Architects have the duty to protect the general public. What public interests does the Architect endeavor to protect? Name 3

A

Safety
Health
Welfare

90
Q

Subrogation

A

When the insurance company tries to get back their money by going after the third party responsible.

NO SUBROGATION should be kept as a provision in the AIA 201 document so the insurance company, after paying out, doesn’t go after the Contractor or whoever else might be responsible

91
Q

Electrolysis

A

Also known as Galvanic Action; occurs when two reactive materials such as aluminum and steel come in contact w/ each other, which may lead to corrosion

92
Q

Correct order for drawing set

A

Civil, arch, struct, plumb, mech, elec

93
Q

Where would you find information on the number of screws that are required for securing light gauge steel studs for a partition wall?

Division 9
Division 5

A

Division 09 - finishes

tricky but impossible to talk about the number of screws without describing the drywall

94
Q

The change order always describes changes to what 3 aspects of contract?

A

Time, sum, and scope!

95
Q

Project fee distribution per each phase in percentage

A
SD - 15%
DD - 20%
CD - 45%
B - 5%
CA - 15%
96
Q

Which of the following is not part of a zoning analysis?

Use
FAR
Easements
Build Heights

A

Easements,

Not actually part of Zoning. Property owner driven / included as part of the deed

97
Q

A construction worker is hurt in an unshored trench on a construction site in which all of the companies are working under AIA contracts.

Is this statement true:

The work may sue the Architect, and who wins will depend on the architects actions at the job site.

A

Yes,

The worker can sue anyone they want if they feel they were responsible. The Architect likely is not but if they were on the job site when it happened and interfered ..

98
Q

Define Standard of care

A

The level of skill and care that the average typical architect, similarly situated would employ

99
Q

Handrail height

A

34-38 inches

100
Q

Distance between two doors (in secession)

A

48 inches

101
Q

what does ANSI and ASTM stand for and do they write standards?

A

American national standards institute and

American society for testing and materials

NO. They are accrediting institutions. They do not write standards.

102
Q

High vs low u-factor.

A

High: rapid heat gain or loss
Low: minimal heat gain or loss

When U value is low, R value is high (good thermal resistance)

103
Q

Requirement for a smoke proof enclosure is determined by what?

A

A buildings height

Regardless of area, construction type, or occupancy

104
Q

Minimum clear width for an accessible door?

A

32 inches

105
Q

Height of a handrail for barrier-free design

A

34 to 38 inches

106
Q

You are designing toilet rooms to make them accessible. Which of these is the least expensive option?
A. Power-assisted door opener that meets AFA standards
B. Plan for accessible toilet rooms in another location

A

A. Power assisted doors

Cheaper and least amount of construction time required

107
Q

Clear width for standard ADA toilet stall

A

60 inches