Crude 2 Questions Flashcards

1
Q
  1. What is the purpose for the C-6101 Recycle Wash Water?

Why do we inject ammonia into the Wash Water?

A

The purpose of the Recycle Wash Water is to protect the overhead-to-crude exchangers from ammonium chloride corrosion and fouling.

To do this enough recycle wash water must be injected so that some of the water remains as liquid water instead of vaporizing.

It is necessary to have liquid water throughout the E-6101s to dissolve chloride.

If liquid water is not present, the ammonium chloride plates out on the tubes. This increases the corrosion
rate considerably.

The electric motor driven water injection pumps, P-6150 and P-6150A pump water from D-6101 into C-6101 overhead vapor line.

An injection nozzle is used in the vapor line for better dispersion of the wash water into the vapor stream.

This injection rate is controlled by FC-1038.

This water keeps the ammonium chloride salts dissolved and thus prevents chloride pitting of the overhead exchangers.

Excess water from D-6101 is routed through
LC-1049 to D-6106 on level control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. What should we do if the level in C-6101 reaches the fifth rams horn?

Explain why this is important.

A

Anytime the liquid level is above the 5th Ram’s Horn, stripping steam
should be pulled to prevent tray damage in the stripping section.

If the level rises above the steam inlet, then the steam throws the liquid against the stripping trays.

This usually damages and displaces these trays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Why should we limit our exposure to Benzene?

What is the permissible exposure limit – time weighted average (PEL-TWA) for an eight-hour workday?

A

Present in LSR and HSR streams.
Hazards:
Known Carcinogen
Exposure must be limited
Slightly toxic to internal organs
Can cause severe damage to lungs

Exposure should be limited.
Permissible exposure limit – time weighted average (PEL – TWA) is 1 PPM for a normal eight hour workday.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. What are the Triconex chopper valve trips for F-6101? Include LOPA conditions.
A
  • Low fuel gas header pressure (PT-428) *Start up permissive only
  • Low fuel gas burner tip pressure (PT-4159 / 5159)
  • Low pass flow (FT-181B/C through FT-188B/C)
  • Loss of draft fan (FT-374/375)
  • C6101 over pressure (PT-307A/B/C)
  • Big Red Pushbutton (HS-432A/B)
  • C-6101 High Level (LN-0106A/B)
  • C-6102 High Level (LN-0138A/B)

F-6101 is equipped with a Triconex safety shutdown system.

The system monitors critical process information and will automatically shut down the furnace if the process violates established Triconex trip parameters.

In most cases dual redundancy is provided for greater
reliability.

Triconex will require both transmitters indicate a shutdown condition before the
system will activate a shut down sequence.

The LOPA Safety System, installed in 2010, is part of the Triconex safety shutdown system.

Triconex is equipped with a pretrip warning system.

If pretrip conditions are reached, an alarm activates alerting the operator of the process approaching shutdown conditions.

In order to activate the pretrip alarm both transmitters must be in pretrip condition.

Triconex pretrip is only a warning and will not initiate a system shutdown.

A furnace shutdown is accomplished by closing the fuel gas supply chopper valves, XV409, XV4006, and the LER II waste gas chopper valve.

Closing these valves stops all fuel supply to the furnace burners.

When a Triconex shutdown is activated, a solenoid trips the latch at each fuel gas chopper valve causing the valve to close.

To reset the system, process conditions must be corrected before the chopper valves can be latched.

Under certain conditions Triconex will take the furnace to minimum fire for a designated time period before initiating a full shut down by closing flow controller.

If process conditions can be corrected before the system times out, a shutdown can be avoided.

When a Triconex trip activates calling for minimum fires, a solenoid trips the latch on the fuel gas control valve causing the valve to close.

To reset the system, process conditions must be corrected before the fuel gas control valve can be latched.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. What are the Triconex chopper valve trips for F-6102? Include LOPA conditions.
A
  • Low fuel gas header pressure (PT-433) *Start-up permissive only
  • Low fuel gas burner tip pressure (PT-4158 / 5158)
  • One low pass flow (FT-284B/C through FT-291B/C)
  • Loss of Draft Fan (FT-374/375)
  • C-6102 Overpressure Shutdown (PT-317A/B/C)
  • C6101 Overpressure Shutdown (PT-301A/B/C)
  • Emergency Shutdown Switch
  • C-6102 High Level (LN-0138A/B)

F-6102 is equipped with a Triconex safety shutdown system.

The system monitors critical process information and will automatically shut down the furnace if the process violates established Triconex trip parameters.

In most cases dual redundancy is provided for greater reliability.

Triconex will require both transmitters indicate a shutdown condition before the system will activate a shutdown sequence.

Triconex is equipped with a pretrip warning system.

If pretrip conditions are reached, an alarm activates alerting the operator of the process approaching shutdown conditions.

In order to activate the pretrip alarm both transmitters must be in pretrip condition.

Triconex pretrip is only a warning and will not initiate a system shutdown.

A furnace shutdown is accomplished by closing the fuel gas supply chopper valves.

Closing the valves stops the fuel supply to the furnace burners.

When a Triconex shutdown is activated, a solenoid trips the latch at the fuel gas chopper valve causing the valve to close.

To reset the system, process conditions must be corrected before the chopper valves can be latched.

Under certain conditions Triconex will take the furnace to minimum fire for a designated time period before initiating a full shut down by closing the fuel gas control valve.

If process conditions can be corrected before the system times out, a shutdown can be avoided.

When a Triconex trip activates calling for minimum fires, a solenoid trips the latch on the fuel gas control valve causing the valve to close.

To reset the system, process conditions must be corrected before FC-167 can be latched.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. What is the purpose of the Preheat Train?
A

The Primary Preheat Train raises the temperature of incoming crude to 270-280°F prior to entering D-6125A Desalter

It also reduces duty on F-6101 Atmospheric furnace thus reducing fuel gas demands and cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. What function does PC-102 serve?

Where is it located and where does it sense its signal from?

A

Crude Feed Pressure Controller

It controls the pressure of the primary preheat train.

It senses it’s signal from the outlet of E-6175 or Upstream of LC-1026

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. Why is it important to routinely sample unit products?
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. What is the purpose of the Desalters (D-6125A&B)?
A

Crude oil contains impurities that would cause problems in CU2 equipment if not removed.

Salts, solids, and water are removed from the crude in a process called desalting. Desalting is carried out in crude units to control three problems:
* Corrosion
* Fouling
* Water in crude oil

The most typical salts are chlorides, sulfates, and carbonates of sodium, magnesium, and calcium.

Most of the salts in crude are dissolved in water, but, in some cases, crystalline
and/or organic salts may be dispersed in the oil.

Although salt composition depends on the crude and the formation it was taken from, in most cases the primary salts are chlorides.

Chlorides are acid producing salts that create hydrogen chloride.

Hydrogen chloride causes corrosion in the overhead systems of crude columns.

Sulfates and carbonates are hardness salts that form scale when water vaporizes.

Scale and solids cause fouling.

Corrosion: Magnesium and calcium chloride are the primary sources of corrosion due to the hydrochloric acid that is produced.

Sodium chloride also contributes to corrosion but to a much lesser extent.

The high temperatures in CU2 promote a chemical reaction known as hydrolysis in which chloride salts break down to form chloride gas (Cl).

This mixes with water vapor to form hydrochloric acid (HCl), which is extremely corrosive.

The other products of hydrolysis, calcium and magnesium hydroxide, leave in the Bottoms stream of the C-6101 along with un-reacted calcium chloride.

These may cause problems in downstream processing of heavy ends if they are left in high concentrations, for example, sodium poisoning of catalyst in the RDS.

Caustic injection is used to help stabilize the magnesium and calcium chloride salts that break down due to hydrolysis.

Fouling: Hardness salts produce different kinds of problems than chlorides do.

The sulfates and carbonates of magnesium and calcium form scale when water vaporizes in the heat exchanger trains, causing fouling.

Fouling in heat exchangers reduces heat transfer and therefore requires extra fuel in the Furnaces to achieve the same crude temperatures.

Water vaporization explains why the crude must be desalted before the crude oil temperature is preheated beyond 300°F.

Water should not vaporize at this temperature given the pressure present in this exchanger train, which should be at least 250 psig.

The other contributor to fouling is solids. Solids are divided by size into two categories:
* Sediment - larger than 20 microns
* Suspended solids - smaller than 20 microns
Sediment has the following characteristics:
* Generally 0.05 to 1.0 percent by volume of crude oil
* Particle size ranges from 20 to 2,000 microns
* Derived from formations or production techniques
* Water insoluble inorganic solids such as sand, silt, clay, and silicates
* Surfaces that are water wettable
* Relatively easy to remove from the crude oil

Along with brine, sediment is one of the main impurities in crude oil.

More than 90 percent of sediment is normally removed in the desalting process, which is why mud washing the desalters on a routine basis is necessary.

Solids removal efficiency depends on residence time, temperature, oil viscosity, wettability, and particle size.

Larger particles settle out faster than small ones.

Suspended solids of less than 20 microns are small, inorganic solid particles that remain suspended in the oil.

They originate primarily as corrosion products and as contaminants introduced during transportation.

Suspended solids have the following characteristics:
* Amounts range from 1-200 ptb (pounds per thousand barrels)
* Size smaller than 20 microns
* Inorganic solids, insoluble in oil or water
* Gather in the surfaces of brine droplets and prevents their coalescence
* Composition (silicon, sand, silt, alkali metal salts not dissolved in brine)
* Surfaces are saturated with oil

One of the most notable characteristics is that these solids have surfaces saturated with oil.

Instead of collecting in water droplets, suspended solids gather around the water’s surface and prevent coalescence.

Stabilized by these particles, small brine droplets tend to gather at the desalter interface layer where they cause the emulsion band to grow, making the separation of water from the oil more difficult.

Because these very fine particles are saturated with oil and attached to the outside of water drops, removal requires water wetting the particles so that they will migrate into the water droplets and be removed.

The wetting agent is called a surfactant. Another aid in wetting these particles is to ensure adequate mixing of the crude oil and the injection water.

Water in Crude Oil: The last function of desalting is removing the water that came in with the crude oil.

Mixing and the use of the surfactant chemical are important.

Water that carries over the top of the desalter with the oil is called carryover.

The amount of carryover must be minimized because of the wasted energy required to heat it in the preheat train and Furnaces.

Large amounts of carryover also results in vapor loading of the Furnace
and Column.

Oil that does not separate from the brine at the bottom of the desalters is
carried out to a tank where it is skimmed off the top and called skim oil or recovered oil when it is fed again.

Feeding this oil again is also wasteful and can upset Column operation if it
brings brine back with it.

The brine stream leaving the plant is sampled.

The oil residue is called carry under.

The separation of the oil and water is aided with a chemical called demulsifier, which helps eliminate the oil/water emulsion or cuff at the interface of the two.

This chemical is injected into the crude in front of the Primary Feed Pumps to give good mixing.

Desalter summary.
The Desalter system is the most important in terms of long run-time for
2CU.

It is possible to run the plant with them by-passed, but fouling and corrosion increase.

The currently-projected five-year runs could never be realized without crude oil desalting.

Some important concepts of Desalter operation are:

  • The acceptable salt content in the desalted crude is set by the processing
    requirements of the receiving Unit. Salt contents of 0.3 ptb or below are always
    acceptable. If lab analysis indicates that salt content is too high, Desalter operation
    must be corrected.
  • The main control on salt content is water make-up rate. Use of seal drum
    condensate, 27 Plt. & 84 Plt. waters should be maximized. Then bring in process
    water after making sure that the other Desalter operation variables are within their
    normal ranges. Desalter temperature should be at maximum limited by the Teflon
    bushings.
  • The main controls on oil carry-under and cuff thickness are desalting chemical
    addition rate, mixing valve pressure drop and pH. The pH should be checked first.
    If pH has increased above 7, check pH of Desalter make-up water sources. If pH
    is normal, increase desalting chemical addition rate. If this does not clear up water
    after two hours, decrease mixing valve pressure drop.

If Desalter temperature is too low, carry-under will increase.

Sufficient Desalter crude preheat is more of a problem at low feed rates.

There are several strategies used to try to trade heat around under this condition. It may be impossible to achieve a Desalter temperature close enough to 300°F to assure good separation at low feedrates.

  • A high percentage of heavy crude oil in the plant feed also makes good separation
    more difficult. Remember that all oil carried-under to 184tk has to be eventually
    re-fed.

Check the Desalter effluent for carried-under oil frequently each shift.

The Desalters remove water, salts, and suspended solids from the crude prior to additional heat exchange.

Salts found in crude are primarily sodium chloride with small amounts of
calcium, magnesium, iron, aluminum chlorides, sulfates, and bicarbonates.

Chloride salts decompose to form hydrogen chloride (HCl) in the atmospheric and Vacuum Furnaces.

HCl forms hydrochloric acid in the presence of water.

This acid can severely corrode Atmospheric and Vacuum Column overhead systems.

Salts and solids foul heat exchanger and furnace tube surfaces resulting in reduced heat transfer and higher pressure drop in these units.

The desalters operate at 280-320° F because a higher temperature in the primary train would promote salt lay down in the exchangers.

Also, any temperature above 320°F would affect the Teflon insulators on the electrical grids.

The crude oil should contain, on the average, about 30-70 pounds of salt per thousand barrels (PTB).

It will also contain about 0.5 LV% of water and solids (BS&W).

The desalters are located in the primary preheat train between exchangers E-6104 and E-6105.

There are two desalting stages.

The oil/water mixture flows through the two desalters in the series.

The first stage desalter, D-6125A, removes about 96% of the salt.

The second stage, D-6125B, removes the remaining 3.3%.

The two stage desalter will decrease the salt level in the crude to about 0.5 PTB from an incoming level of 30-70 PTB.

The BS&W leaving the desalter should be 0.1 LV%.

Water mixes with the crude at three locations.

The total amount of water added to the crude is about 5 liquid volume %.

Three fifths (3 LV %) is added at the discharge of the feed pump, P-6101.

This water helps protect the heat exchangers ahead of the desalter from salt
deposits.

The remaining two fifths of the water are added to the crude between the first and
second stage desalters.

Water recovered in the second stage is recycled back to the inlet of the first stage where it mixes with the incoming crude.

The water recovered in the first stage desalter is the net water removed from the crude.

The water flows through exchanger E-6119, which preheats the fresh water going to the inlet of the second stage desalter.

The water is cooled to about 200°F in E-6119 and flows to the API separators or tankage where the water is de-oiled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. What is the purpose of the mix valves?
A

Ensures water contacts salt compounds in crude feed for removal

Mix valve operation:
Too much mixing allows salt and water carry over to Flash Drum
Too little mixing allows salt and water carry over to Flash Drum

The degree of mixing imparted to the oil and water is a function of the pressure differential, Delta P, across the mix valve.

Mix valves are designed to shear the large water droplets in to many smaller droplets.

Mix valves.
The key to successful salt and solids removal in the desalting operation is water contact of the contaminants in the oil phase.

This is primarily accomplished through a good mix/water rate ratio.

The degree of mixing imparted to the oil, water, and chemical as they flow through the mix valve is a function’ of the pressure differential Delta P across the valve.

Mix valves are normally double ported globe valves that are designed to shear the large water droplets into many smaller droplets.

This action creates greater water surface contact area and produces patterned spray dispersion for maximum water coverage inside the pipe diameter.

The goal is to disperse the fresh process water as thoroughly as possible without over mixing and forming an emulsion so highly stabilized that it is difficult or impossible to break.

The mix Delta P is the most important and frequently used variable in the desalting process utilized by the Crude unit operators to control the performance of this system.

Optimum mix Delta P’s vary with different crude and different crude combinations so a “feel” for each feed composition must be acquired through operating experience and adjustments made to maximize the effectiveness in that particular situation.

The recommended procedure to establish the optimum mix requirement for new crude is as follows:

Set wash water rate at a given point normally 4-5% to start and leave this rate and
other variables as constants while mix requirement is being determined.

Both “A” and “B” stage mix valves should be started wide open and then increased in 3-5# increments.

Testing for salt and BS&W should be conducted on the desalted crude out of each stage after a sufficient time at each Delta P setting normally 45 minutes to 1 hour.

Continue to increase the mix Delta P until an increase in water and/or salt is noted in the desalted crude sample.

When this occurs, mix valve should be opened slightly to eliminate the increase and
maximum mix is considered established.

It should be pointed out that with some oil/water mix may be attained by velocity of crude though the primary train and a naturally greater tendency of the higher salt and BS&W raw crude entering the first stage to form emulsions; typically the mix on D-6125A will be less than with the cleaner crude entering D-6125B. For this reason, mix requirements for each stage should be established separately.

If excessive mix is required to attain desired salt removal by the above procedure, mix valves should be opened, wash water rate increased 1-2%, and procedure repeated at the higher water rates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. What purpose does mud washing serve?
A

Uses clean water from MP-6124/A to help remove sediment and solids from the Desalters

Mud washing:
To assist the Utilities Area with the effluent treating system, the mud washing
will be performed between 12:00 midnight and 02:00 daily.

Many of the solids that are removed from the oil phase have a tendency to settle to the bottom of the desalting vessel.

This reduces volume capacity of the desalter and affects valuable residence time.

Clean water at the Tricocks and dirty effluent is normally an indication that solids have accumulated on the bottom of desalter and the effluent has to channel through this buildup to get out.

This condition would indicate a need for mud washing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. How can the interface level in the Desalters be tested to assure the LC is reading correctly? Explain, be specific.
A

Each desalter has five Tricock sample valves which extend into D-6125A from the bottom of the vessel from 24” to 72” which can be used to determine exact level of oil/water interface, cuff thickness and to double check level transmitters.

Two capacitance level alarms, LH-5017 and LL-5018, have been installed in D-6125A,
Desalter, which alarm when the interface level rises and drops.

The probes are permanently installed and are not to be retracted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. Where can the Desalter effluent water be routed? What is the normal routing?
A

Ballast Tank
OWS

slip stream to suction of P-6101/A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. What is the purpose of the Flash Drum (D-6130)? Where are the streams from the flash drum routed?
A

The purpose of D-6130 Flash Drum is to vaporize ”flash” all of the water in the desalted crude oil along with the light ends.

This reduces fouling in the downstream exchangers.

Water that is not flashed causes fouling since the dissolved salt is converted to salt crystals that plate out on the exchanger tubes.

Flashing the crude also removes light ends from the crude.

This reduces the pressure drop through the secondary preheat exchangers and the furnace thus reducing pumping cost.

The vapors from the flash drum flows directly to the atmospheric column flash zone.

The Flash Drum liquid flows to the P-6102 Crude Booster Pumps.

This flashing process also reduces the load on F-6101.

This subsection discusses Flash Drum control mechanisms for:
* Pressure control
* Level control
* Foaming
* Temperature control
* Flow control

Pressure Control.
The Flash Drum pressure controller, PC-1027, is located on the vapor line leaving the Flash Drum. It is routed directly to the Atmospheric Column flash zone.

The Flash Drum pressure is determined by C-6101 pressure.

The controller is locked open allowing the Flash Drum to ride on the atmospheric column pressure.

This will maximize the vapors sent directly to the atmospheric column.

PC-1027 was removed during the 2007 rebuild.

Level Control.
The level controller for the Flash Drum is located downstream of the E-6105 exchanger.

The Flash Drum is elevated to hold good suction head on the secondary crude feed pumps without increasing Flash Drum pressure.

The Flash Drum level controller, LC-1026 regulates the desalted crude oil flow to the Flash Drum.

The level should be kept at about 65 percent of scale to provide surge volume for the
crude booster pumps.

This level provides about five minutes of surge.

Foaming.
The most serious problem that can occur in the flash drum is foaming.

If it foams and carries over into the atmospheric column, the crude will contaminate the fourth sidecut draw.

This crude contaminated HDN feed will seriously damage the Isomax catalyst.

When indications shows the flash drum is starting to foam, then the fourth sidecut stream should be watched closely for crude contamination.

If this occurs switch the fourth sidecut to off test until it clears up.

Foaming causes the LC transmitter to give a false indication.

This could cause lose of level and cavitation would occur in the secondary feed pumps, P-6102’s. Also the false indication could cause the crude level to go up and result in crude going overhead in the vapor line ending up with cool crude in the flash zone of C-6101.

Having too low a temperature in the flash drum usually causes foaming.

Normal operating temperature range for the A.

Heavy crude mixture is 315°-320°F.

Temperature Control.

A hot crude recycle stream from E-6109 is used to maintain the bottoms temperature at around 310°F.

TC-2134 controls the flow (usually around 16MBPD) of hot crude recycle that enters the bottom of the Flash Drum which provides the correct temperature to prevent foaming and the right amount of flashing.

Flashing cools down the crude oil because vaporization is a heat-consuming process.

When the Flash Drum is operating properly, the Flash Drum bottoms temperature should be about 5°-15°F below the Flash Drum feed temperature.

Flow Control.
Desalted crude oil from the Flash Drum flows to P-6102/A, Secondary Feed Pumps.

Immediate action is required if one of the P-6102 pumps shut down and the APS
pump does not come on line.

P-6102s are also responsible for maintaining sufficient
pressure upstream of the furnace pass flow controllers to prevent vaporization.

If flashing were to occur, the pass flow control valves would lose control.

This would greatly increase the chances of coking up one or more furnace passes.

The minimum crude oil pressure is about 340 psig.

This is sufficient for crude oil leaving the secondary preheat train at 570°F or below.

If the pressure falls below the minimum, check spill-back of P-6102.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Where do the PRD’s from the Desalters relieve to?
A

The Flash Drum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. What product stream does the secondary preheat train primarily cool?

Where does this stream come from, and what equipment is it routed through?

A

The flashed crude from the bottom of the Flash Drum (D-6130) is pumped through the secondary preheat train with the secondary crude feed pumps P-6102 and P-6102A.

This increases the preheat temperature from 315°F to approximately 480°F.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  1. Explain the purpose of the Air Pre-heater and how it operates.
A

The purpose of the Ljungstrom air preheater is to absorb waste heat from the flue gases and then transfer this heat to the ambient air before it enters the fireboxes.

Thousands of specially formed metal plates are spaced and compactly arranged within a radially divided cylindrical shell called the rotor.

As the rotor revolves, the mass of metal plates alternately rotates through the hot flue gas and cool combustion air passages.

Heat is absorbed by the metal surfaces passing through the hot flue gas stream, then as these same surfaces pass through the ambient air stream they release the stored up heat.

This greatly increases the temperature of the incoming combustion air and decreases the temperature of the outgoing flue gas.

Combustion air to F-6101 and F-6102 is provided by K-6104.

K 6104 air blower is driven by a 150 PSIG steam turbine exhausting to the 40# steam.

K-6104 takes suction on the atmosphere and forces the ambient air through the air preheater, E-6113.

In the preheater the fresh air absorbs approximately 500°F of heat from the flue gases from F-6101 and F-6102, depending on feed rates.

The preheated air travels through a forced-air duct to the burners in both F-6101 and F-6102.

Flue gas removal from F-6101 and F-6102 is provided by K-6105.

K-6105 exhaust fan is driven by a 600 PSIG steam turbine that exhausts to the 40 PSIG steam.

K-6105 takes suction on the flue gas after the preheater, E-6113.

The blower pulls the flue gas through the preheater and forces it to the common stack.

The furnaces can be operated on natural draft without the preheater and draft fans.

Operating the furnaces on natural draft will limit the crude feed to the unit to approximately 100 MBPD due to preheat limitations.

In order to bypass the air preheater both the draft fans must be shut down and the natural draft doors on each furnace (F-6101 and F-6102) must be open.

Isolating the air preheater is done with the guillotine blinds in the hot and cold sections of the preheater.

18
Q
  1. What is the purpose of the minimum flows on the Fuel Gas to a furnace?
A

It provides a constant minimum fuel gas pressure to the burners lit so they won’t go out if the fuel gas flow controller were to go completely closed.

19
Q
  1. How are the tubes in F-6101 & F-6102 protected when feed is lost?
A

F-6102 Bypass Line

A bypass around F-6102 was installed during the Clean Fuels Project.

This is designed to take a load off of F-6102 from the increase of Atmos. Bottoms due to feeding more Maya crude.

It comes off the suction of P-6115/A and goes to the F-6102 Transfer line.

The amount of flow is controlled by FC-0031.

This line is designed for 40,000 BPD.

If crude feed stops due to power failure, then atmospheric reduced crude must be circulated through the atmospheric furnaces to avoid damage and to minimize coking.

To do this, a special emergency circulation line is provided on the discharge system of the atmospheric bottoms pumps, P-6115 and P-6115A.

An emergency circulation line branches off upstream of the bottoms control valve LC-106 and circulates the atmospheric bottoms stream back through the atmospheric furnace, F-6101.

This emergency line is equipped with a console mounted control valve, HC-115 to regulate circulation rate.

This system is to be used on startup and in case of loss of flow through F-6101 tubes.

20
Q
  1. Explain how to bypass a control valve to be taken out of service for maintenance?
A
21
Q
  1. Why is the Stripping Steam superheated in the convection section of F-6102?

Name all vessels that use 60# stripping steam and all that use 40# striping steam.

A

It is superheated to make sure that the stripping steam is always dry.
Any liquid water remaining in the stripping steam would expand violently, about 5,000 times in the column and damage the internals.

60#: C-6101, D-6105, D-6106, D-6107

40#: C-6102

22
Q
  1. As an outside operator, what are some indications of a bogged furnace, and the proper response for an outside operator to this situation.
A
23
Q
  1. What is the purpose of E-6155, surface condenser?
A

The purpose of the surface condenser is to increase the power from the steam, driving the feed pump turbines, by condensing the steam in a low pressure, i.e. vacuum.

Operate at the lowest vacuum possible to reduce steam
requirements for turbines.

24
Q
  1. Where is the water from D-6101 & D-6102 routed? Include control valves.
A

The water is returned to C-6101 as wash water for the column overhead and the excess water is routed to D-6106, slop oil drum, to provide wash water for the Desalters.

Water is pumped from D-6101 water boot though the P-6150’s & FC-1038 to C-6101 Overheads
D-6101 water boot is on level control via LC-1049 routed to Seal Drum
D-6102 water boot is on level control via LC-0330 routed to Seal Drum

25
Q
  1. What is the purpose of D-6101? Where are the hydrocarbon streams from the drum routed? Include valve numbers.
A

The drum separates the cooled overhead vapors, liquid hydrocarbon and water.

Uncondensed vapors are routed to D-6102, along with any excess
hydrocarbon liquid not used for reflux back to C-6101.

The water is returned to C-6101 as wash water for the column overhead and the excess water is routed to D-6106, slop oil drum, to provide wash water for the Desalters.

26
Q
  1. What is the purpose of D-6102?

Where are the hydrocarbon streams from the drum routed? Include valve numbers.

A

The drum separates the cooled overhead vapors, liquid hydrocarbon and water.

Uncondensed vapors are routed to D-6103; the liquid
is pumped to C-6104 as stabilizer feed.

The excess water is routed to D-6106, slop oil drum, to provide wash water for the Desalters.

27
Q
  1. What is the purpose of D-6103?
A

The purpose of the drum is to separate the vapors
from the liquid, before the suction of K-6190/90A.

28
Q
  1. What is the purpose of D-6190?

Where are the streams from D-6190 routed?

A

The purpose of the drum is to separate the liquids and the gas vapors.
The liquid streams consist of liquid hydrocarbon and water, the hydrocarbon is routed to the GRU or LER II.

29
Q
  1. What are the shutdowns associated with K-6190/A?
A

Alarm panels are located, outside, in the process unit for each compressor.

The alarm panel is equipped with lighted indicators that will indicate the alarm condition or which of the shutdown devices caused the compressor to shutdown.

The shutdown system can be bypassed so that the operating personnel can test the compressor alarms, without causing the compressor to be shutdown.

Switching to bypass position will cause the normal operating
green light to go out and the bypass red light to come on.

The alarm panels will indicate the following equipment shutdown alarms:

  • D-6103 suction K.O. drum, LSH-391, common to K-6190/90A.
  • K-6190, lube oil shutdown, PSL-3104.
  • K-6190A, lube oil shutdown, PSL-3105.
  • K-6190, vibration shutdown, XA-392.
  • K-6190A, vibration shutdown, XS-3102.
  • K-6190, cylinder high temperature shutdown,
  • K-6190A, cylinder high temperature shutdown,
  • K-6190, 1st cylinder high temperature shutdown, TSH-3129.
  • K-6190, 2nd cylinder high temperature shutdown, TSH-397.
  • K-6190, 1st cylinder high temperature shutdown, TSH-3128.
  • K-6190, 2nd cylinder high temperature shutdown, TSH-396.
30
Q
  1. What are the products from C-6101, and what are the possible routings?
A
  • Stabilizer Overheads => LER 2
  • Stabilizer Bottoms (LSR) => AFP (Sour) or HDS 2 (Sweet)
  • First Sidecut (HSR Naphtha) => HDS 1, Tankage
  • Second Sidecut (Jet) => 18 plt (caustic treats, salt dries, and clay polishes) 22 plt (Hydrotreater)
    Tankage via Crude 1
    Off Test
  • Third Sidecut (Diesel) => To Iso 2 via Hot or Cold LT HDN or RDS via Hvy HDN at 61 Plot Limit

Plant 67/CHDN/Storage via Plant 68 Plot Limit

  • Fourth Sidecut (Isomax Feed or HDN Feed) => ISO 1, ISO 2, Tankage
  • Fifth Sidecut (Lt HDN) => ISO 1, ISO 2, Tankage
  • Seventh Sidecut (Hvy HDN) => PBOP, RDS, ISO 1, Tankage
  • Vacuum Residuum => VDU, Coker, Tankage
31
Q
  1. What is controlled by PC-109? Explain how this is accomplished.
A

PC-109 split range controller senses C-6101 pressure

PC-109 sends signal to PC-109B, fuel gas control valve, opening valve raising column pressure to set point, at same time tells PC-109A to close

PC-109 sends signal to PC-109A on high column pressure opening valve to relief lowering column pressure, at same time tells PC-109B to close

K-6190/A normally set to pump enough overhead gases to ensure fuel gas valve, PV-109B stays open slightly and PV-109A to relief closed

32
Q
  1. The 3rd sidecut is to be fed to Plant 67. They have requested to have the feed heated.

What moves can be made in the Crude unit to accomplish this?

A

TC-131 BP ? Bypasses E-6133 A-D

33
Q
  1. Where can products be routed that do not meet product specifications?
A

Off Test

34
Q
  1. What is the purpose of the Stabilizer Column (C-6104)?
A

The purpose of the Stabilizer is to separate Butane and lighter
components from the LSR.

35
Q
  1. How is the pressure on C-6104 controlled? Be specific.
A

Split range controller PC-158 is located on the column overhead line and regulates the flow of cooling water to E-6134 and E-6136 and controls the amount of vent gas from D-6105 to the sour gas header.

36
Q
  1. What is the purpose of D-6104 Coalescer?
A

To knock out entrained water from the Stabilizer feed.

Naphtha feed from the atmospheric column product drum, D-6102 is pumped by P-6112&A through a level controller, LC-165 into the stabilizer feed coalescer, D-6104.

This rate is indicated by FC-222. Liquid hydrocarbon from D-6190 is also pumped to D-6104 using P-6190/A to D-6104 through a level controller LC-1034.

D-6104 is a horizontal vessel with a capacity of three barrels.

The drum is partially packed with organic fiber cartridges to separate entrained water from the stabilizer feed stream.

The coalescer has a water boot equipped with an interface gauge glass and a high level alarm.

Water from D-6104 water boot is routed through LC-328 and into D-6106 seal drum.

A measuring device PDI-478 is located on the bypass line around D-6104 to indicate the pressure drop through the coalescer.

When the pressure drop reaches 15 PSIG the fiber cartridges must be changed out.

The dry feed from D-6104 flows through the shell side of the stabilizer feed/bottoms exchanger, E-6135 and into the stabilizer column, C-6104 between trays 17 and 18.

C-6104 feed is preheated to approximately 190°F.

37
Q
  1. What is the routing of the product streams & water from D-6105? Include control valves.
A
38
Q
  1. What is the purpose of D-6106 Seal Drum? Be specific, explain how it works.
A

The purpose of the seal drum is to create a seal between the atmosphere and the vacuum atmosphere required of C-6102.

The seal is maintained using barometric legs, which extend below the water level in the seal drum.

Water is condensed from the steam of the overhead jets, which pull the required vacuum pressure of C-6102.

Foul water from other drums, D-6101, D-6102 and D-6104, in the unit has been routed to the seal drum.

This water is pumped from the seal drum to the D-6125B as wash water from the raw crude feed.

The oil, slop oil, which separates from the water flows over the weir and is pumped to C-6101 flash zone (above tray 5A) or LHDN or recovered oil.

39
Q
  1. How are the water, hydrocarbon, and vapors separated in D-6106, and where is each routed?
A

The purpose of the seal drum is to create a seal between the atmosphere and the vacuum atmosphere required of C-6102.

The seal is maintained using barometric legs, which extend below the water level in the seal drum.

Water is condensed from the steam of the overhead jets, which pull the required vacuum pressure of C-6102.

Foul water from other drums, D-6101, D-6102 and D-6104, in the unit has been routed to the seal drum.

This water is pumped from the seal drum to the D-6125B as wash water from the raw crude feed.

The oil, slop oil, which separates from the water flows over the weir and is pumped to C-6101 flash zone (above tray 5A) or LHDN or recovered oil.

40
Q
  1. List the Vacuum Column products and what are the possible routings?
A

Lt HDN => ISO 1, ISO 2, Tankage

Hvy HDN => PBOP, RDS, ISO 1, Tankage

Residuum => VDU, Coker, Tankage

41
Q
  1. Draw in detail a one-line diagram of the Overhead System of the Vac column:
A
42
Q
  1. Draw in detail a one-line diagram of the Primary Preheat Train from feed in to D-6130. Include material on both sides of each exchanger.
A