Critical path analysis 3.3.4 Flashcards
What is critical path analysis?
A project management tool that identifies the most efficient and cost-effective way of completing a complex project
What does it involve?
- list of all activities required to complete the project
- the time that each activity will take
- the order the activities must be completed
- the earliest and latest each project can start and finish without delaying completion
activities that can be completed simultaneously
Calculating EST
Working forward from node 1 it is possible to calculate the EST for each activity by adding the duration of each task
Calculating LFT
Working backwards from the last node it is possible to calculate the LFT for each activity by subtracting the duration of each task
Calculating float time
Float time exists where there is a difference between EST and LFT. Managers may transfer resources as there is extra time to complete these tasks.
Float = LFT- duration - EST
Identifying the critical path
If any critical activities are delayed the project as a whole will be delayed. The critical path follows nodes where the EST and LFT are equal.
Limitations of Critical Path Analysis
- very complex projects involve a very large number of activities
- network analysis often relies on estimates and forecasts
- does not guarantee success
- resources may not prove to be as flexible when float periods are identified