Critical Path Analysis Flashcards

1
Q

Define

Activity Chart

A

A table that lists, in order, the activities that are essential to the completion of a project, how long they will take, and which activity immediately precedes another.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define

Immediate predecessor

A

An activity that must be completed before another activity can commence. An activity may have several immediate predecessors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define

Dummy Activity

A

These are edges that are represented by dotted lines and represent imaginary edges, which are useful when a task is an immidiate predecessor of two other activities and these activities have other predecessors that are not shared.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define

Earliest Starting Time (EST)

A

The earliest a task could possibly be started after the beginning of the project. It can be worked out using forward scanning, adding the lengths of predecessors together.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define

Latest Starting Time (LST)

A

The latest a task could be started without the project finishing late. It can be worked out using backward scanning, taking the lengths as you move backwards through the networks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Definition

Float Time

A

The time that an individual task in a project can be delayed without impacting the finishing time of the entire project. To calculate float time we subtract the earliest start time (EST) from the latest start time (LST).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Definition

Minimum Completion Time

A

The earliest this project could be completed. The EST at the end of the final critical activity gives us the overall minimum completion time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define

Source

A

The beginning or origin of flow through a network.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define

Sink

A

The endpoint of flow through a network.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define

Maximum Flow

A

The capacity of the smallest pipe in the system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly