critical path analysis Flashcards
1
Q
Free Float
A
EST start of next task – EST start of this task – duration
2
Q
Total Float
A
LFT of activity – EST of activity – duration
Free Float
EST start of next task – EST start of this task – duration
Total Float
LFT of activity – EST of activity – duration