What is Work Breakdown Structure (WBS)?

A

Decomposing scope of work to more manageable parts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a Work Package?

A

The lowest level of WBS components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Decomposition?

A

Technique used in for breaking down project scope and project deliverables into smaller, more manageable parts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the 5 steps in Decomposition?

A

1) Identify deliverables and work, 2) Organize WBS, 3) Decompose WBS to lower level components, 4) Assign codes (Code of Accounts), 5) Verify decomposition of the deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a Scope Baseline?

A

Approved version of Scope Statement, WBS, and WBS Dictionary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Control Account?

A

Management control point where scope, budget, actual cost, and schedule are compared to earned value for performance measurements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Planning Package?

A

WBS component below control account with known work content without detailed schedule activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a WBS Dictionary?

A

Document that provides deliverables, activity, and scheduling information about each component in the WBS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the inputs to create a WBS process?

A

Scope Management Plan, Project Scope Statement, Requirements Documentation, OPA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Chart of Accounts?

A

A list detailing all accounts used by the organization to identify areas of expenditures (not part of the WBS itself)