CPM Flashcards
What is Float time?
The amount of leeway allowed in starting or completing an activity without delaying the project completion date.
A wood framing crew consists of two journeyman carpenters, a first-year carpenter apprentice, and a laborer. The laborer and carpenter apprentice will move the lumber and equipment and the two journeyman carpenters will do the framing. During the job, who would generally be the one to collect scrap and clean the worksite?
The laborer
O&M Manuals include which of the following?
Manufacturer’s instructions about equipment, including diagrams and parts lists
Document used for tracking actual progress of a submittal which can identify unnecessary delay in the submittal process:
Submittal log
Definable tasks that support the goals of a particular project, typically include completion in a time frame, at a level of quality, with cost control, customer satisfaction, safety, and effective management of subs:
Objectives
A key indicator of the productivity of a project and the effectiveness of project management:
Cost Control
The submittal process is primarily intended for who’s review?
The architect
Which of the following is not a typical objective for a successful, profitable project?
Break Even Bidding
What type of event log records objective information on the jobsite?
Daily report
The project management team typically includes all of the following except
Delivery Driver
Documentation of cost information has two primary purposes?
To transmit information to the company’s accounting system and to accumulate information to control the projects cost.
What is the purpose for using cost codes to track cost during a construction project?
To allow the comparison of actual cost data with estimated values
What action should be taken by the project manager when a subcontractor submits a field question regarding a conflict found in the project specifications?
Analyze the impact of the conflict
Can an RFI be handled with just a phone call?
No
Costs information is derived from all of the following except:
Dynamic cost
Which of the following are NOT examples of documents used in the Startup phase of construction
Change orders
What should a budget be based on?
The estimate
Which of the following documents are not in the Construction Progress phase of construction?
Punch lists
Which of the following is not considered an important technique in project management?
Licensure
A matrix of organization, with formal and informal contractual relationships between participants of a construction project is called:
Project Delivery System
What is not a document used in the Project Closeout phase of construction?
Submittals
A traditional contract delivery system is comprised of which parties?
The owner, the contractor and the architect
What is done during a Project Closeout?
Spare Parts turned over
Basic delivery systems options for a construction project include all of the following except:
CQM
Cash flow projections should relate the schedule of values to the?
Construction schedule
Who is the principal manager of the work on the jobsite?
The Superintendent
Who does the Project Engineer usually report directly to on the job-site?
The project manager
In what type of project delivery method does the owner have separate contracts with the designer, the contractor and construction manager?
Agency construction management
In which delivery system does the construction manager act as an agent of the owner, but the contracts for the architect and contractors are written directly with owner and not the construction manager?
Construction Management (CM)
The delivery system that is the least cumbersome for the owner, by providing a single source procurement for the owner:
Design Build
Construction Documents typically consist of what two major physical components?
Project Manual and Drawings
Which of the following project personnel is the least likely to create accurate as-built drawings during the course of a building project?
Project manager
Which division of the contract documents includes the specifications for finishes?
Division 09
Some sealants are NOT compatible with other materials. How is the contractor to determine which sealant to use in a particular application?
Refer to the technical specifications
Bulletins of additional information that are germane to the contract documents issued during the bid period. This information is added to the contract documents after completion and prior to contract award are called?
Addenda