Costing Flashcards
Define ‘Fixed Capital’
Total cost of the plant ready for start-up.
Give 2 examples of fixed capital costs
1) Equipment & installation
2) Design costs
Define ‘Working Capital’
Additional investment needed to start the plant & operate until income is earned.
Give 2 examples of working capital costs
1) Cost of start-up
2) Catalyst & raw materials
How do you calculate the total investment required
Total investment = fixed capital + working capital
Give 2 examples of fixed operating costs
1) Labour costs
2) Insurance
Give 2 examples of variable operating costs
1) Utilities
2) Feed materials
Give an example of direct & indirect overheads
Direct - site facilities
Indirect - research & development
What are the 4 methods used to estimate capital costs
1) Find a similar plant & adjust size
2) Time adjustment from the past/for future
3) Estimate cost of individual units & add together
4) Factorial method
How do you calculate the cost of a new plant from a similar plant?
Cost plant A = Cost of plant B x [Size A/SizeB]^n
where n = 2/3 (typically)
What is the purpose of ‘n’ when calculating plant costs based on similar plants? What is the general range & duplicate value of ‘n’?
Acknowledges scalability that doubling throughput does not double plant costs. When directly duplicated n=1 but generally n ranges between 0.4-0.8.
How do you calculate the cost of a plant using time adjustment from the past?
Using the Annual Chemical Engineering Plant Cost Index (Annual CEPCI) for each year then;
Cost (now) = Cost (then) x [CEPCI (now)/CEPCI (then)]
How do you calculate the cost of a plant using time adjustment for the future?
Use current inflation rate 1.4% and increase factor (1.014) to the power of the number of years ahead (y);
Cost (future) = Cost (now) x [1.0.14]^y
What does the factorial method take into account? Give 2 examples.
It takes account of costs of associated equipment & installations as well as the major process equipment. eg. storage & instruments.
How do you calculate the total physical plant cost (PPC) using the factorial method?
PPC = F x PCE
where; F = sum of individual factors & PCE = physical cost (major) equipment.